HomeMy WebLinkAboutRES 24-299BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on July 18, 2023, by Resolution 23-191, City Council awarded a contract to
Gulf Coast Electric Co., of Beaumont, Texas, in the amount of $249,000.00, for the Rue Street
Lift Station Electrical and Controls Improvements Project; and,
and,
WHEREAS, previous Change Order No. 1, resulted in no change to the contract amount;
WHEREAS, proposed Change Order No. 2, has no dollar amount, but will add one
hundred and fifty-three (153) calendar days to reflect the actual time used to complete the
project; and,
WHEREAS, the project has been inspected by the Water Utilities Staff and found to be
complete in accordance with the provisions and terms set forth in the contract;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT an additional one hundred and fifty-three (153) calendar days are added to
complete the work; and,
THAT the City Manager be and he is hereby authorized to execute Change Order No. 2,
accept maintenance, and make final payment to Gulf Coast Electric Co., of Beaumont, Texas, in
the amount of $12,450.00, for the Rue Street Lift Station Electrical and Controls Improvements
Project; and,
BE IT FURTHER RESOLVED THAT the Rue Street Lift Station Electrical and Controls
Improvements Project be and the same is hereby accepted.
The meeting at which this resolution was approved was in all things conducted in strict
compliance with the Texas Open Meetings Act, Texas Government Code, Chapter 551.
PASSED BY THE CITY COUNCIL of the City of Beaupont this the 19th day of
November, 2024.
- Mayor Rby West -
Pro ectmates.
C ITYOFBEAU MONT. P ROJ ECTMATES.COM
Change Order #001.002
WU1023-02 - RUE LIFT STATION UPGRADES, 1350 Langham, Beaumont, TX 77701 USA
Thursday, Oct 31, 2024
Change Order Details Grand Total:
I
Description
CO#001.002: Final
Division
26 - Electrical
Scope of Work
Change Order No. 2 will be to add 153 days to the project and start the close out process. The days
proposed are for an extensive wait time receiving the pump control panel submittal from the vendor and a
material shortage.
Notes
Final change order to closeout this project.
j Awarded to
Wendy Mullins (Gulf Coast Electric), 92645
Created By
Makenzie Watts (City of Beaumont)
Create Date
Aug 01, 2024 02:10 PM CST
Reason Code
Time Extension
I Days Changed
153
Attachments
extension reauest.odf
{
Close-out Letter - Gulf Coast.odf
I
Additional Info
Line Item Type
Group
Dates
Created On
Capital Planning
Lump sum
3.0 Construction
Sep 03, 2024
Capital Planning Construction - Rue Street LS - Electrical and Controls Improvements - SEP
Capital Project Fiscal Year 2024
I
Accounting
i
I
Item Id 582
PO Number 441216
Summary
Original Contract Sum
277.000.00
Net Cost by Previous Approved Change Order
-28,000.00
Contract Sum Before This Change Order
249,000.00
Contract Sum Changed By This Change Order
0.00
New Contract Sum
249,000.00
Substantial Completion Date
N/A
Net Time Change By Previous Change Order
— ---------------
0 day(s)
- -----
Substantial Completion Before This Change Order
N/A
Time Changed By This Change Order
153 day(s)
New Substantial Completion Date
N/A
All Change Orders of the Original Contract
-10.108303249097472924187725630%
Approval (Approved)
User / Role
Status Comments
Wendy Mullins (Extemal-GC)
Approved
Oct 03, 2024 02:45 PM CST
John Pippins (Project Manager)
Approved
Oct 04, 2024 09:38 AM CST
Bart Bartkowiak (Director)
Approved
Oct 04, 2024 10:16 AM CST
Crystal Valencia (Admin)
Approved
Oct 04, 2024 10:27 AM CST
CITY OF BEAUMONT
DAIS:
July 10,2023
Project.
Rue St Lift Station Electdcal and Control Improvements - Supplemental Environmental Project
County:
Jalforsan
District:
Beaumont
Contract Number:
WU1023-02
Owner.
Cityof8oaumont
Contractor.
Gulf Coast Electric Co., far,
C.O. No.,
1
THE FOLLOWING C G S I N THE PLANS A DIORSPECIFICATONSAREHEREBYMADE:
TNs change Is tequlred to clady the material of the variable frequency drive bid Item and reduce the overall project cost. The Item was bid YAh on assumed alelniom steel enclosure.
whereas plastlowIll be aufffclont.
Item No.
Item Coda
F DESCRIPTION
Unit
Ortglnlol
uanllQuantll
Chenpe In
Unit Prlca
Total
ADD
11
Furnish and Install (4) variable frequency drives and all
appurtenances, In NEMA 1-plaslto enclosures, all to Strict
accordance Wit the plans and specl0callons for.
LS
1
-
S 97,000.OD
j 97.000.00
SUBTOTAL j 07,000.00
DELETE
q
Fumish and Install (4) variable froquencydrives and all
appurtenances, all lnsldclaccordance wIththe plans and
speclllcallons for,
LS
1
-
j 126,60D.00
$ 126,000.00
SUBTOTAL
j 126,000.00
TOTAL AMOUNT OF THIS CHANGE ORDER $ (28,000.00)
0 CALENDAR DAYS WILLBEADDED TO THIS CHANGE ORDER
ORIGINAL CONTRACTA,MOUNT:
$ 277,000.00
NET FROM PREVIOUS CHANGE ORDERS:
$
TOTALAMOUNTOFTHIS CHANGE ORDER,
_$ (28.00DADI
PERCENT OF THIS CHANGE ORDER:
-10,11%
TOTAL PERCENT CHANGE ORDER TO DATE:
-10.1i%
NEWCONTRACTAMOUNT.
$ 249,000.00
CONTRACTTIME
ORIGINAL CONTRACT TIME:
_ 150 Calends r Diva
ADDITIONAL CONTRAOTTIME PER PREVIOUS CHANGE ORDERS:
0
ADDITIONAL CONTRACTTIME PER THIS CHANGE ORDER:
0
REVISED CONTRACTTIME:
160 Calendar Doys
CONDITION OF CHANGE:
'Contrarlarecknowledges and egroes Ihat the adjustments In contract pike and contract 0me sUpulated In thIs Change Ordorropresonls fug compensa0on forallIncreases
end dectooss3 In the cost of, and We lore requtted to pederm the Salim work underthe contractadstng dlrocUy orfadfrodty hem Ihis Change Ordarend all prevlaus Change Orders.
Acceptance of thls WalverconsIllutes on agreementbolvnen Ownerand ConVaclorthol Iho Chango 0rdarroprasonts an a0 incluslvo, muluolly agreed upon adjustmanito Iho Conbacl,
and thatContractorvAlvalveaUdghtstofileaclalmonthisChangeOrder atterillsproperty executed *
ACCEPTED BY:. PREPA D BY:
GULF COA ELECTRIC DATE JONN PPINS 13 DATE
INC. WA URLITIESDESIGN MANAGER
REVIEWED BY:
REM ED BY
R BATE
B A CWIAK
DATE
CRY ENGINEER
DIRECT13RCF PUBLIC WORKS
APPRO D BY:
A BY:
7
KENNETH R.\YILLIAa19 DATE
TINABROUB D
DATE
CrTYMANAGER
CITYCLERN
Projectmates
C ITYOFB EAU MONT. PROJ ECTMATES.COM
Invoice #001.005 for Invoices/Pay Apps
WU1023-02 - RUE LIFT STATION UPGRADES, 1350 Langham, Beaumont, TX 77701 USA
Thursday, Oct 31, 2024
Invoice Details Amount Due: 12,450.00
I
Contract
Contract - 001 RUE LIFT STATION ELECTRICALAND CONTROLS IMPROVEMENTS - SEP
Invoice #
001.005
Description
Gulf Coast Electric- RUE LIFT STATION ELECTRICAL AND CONTROLS IMPROVEMENTS- SEP
'
Invoice Date
Oct 18, 2024
Pay Period
May 01, 2024 to Jun 26, 2024
Final Invoice
Yes
—.._.-...._..,. --.
Grand Total
_.. _... -- — - -- - ----. _ __._....- - ..._ _ ....-.._...
$0.00
i
Payment To
Wendy Mullins 92645 (Gulf Coast Electric) '
Payment From
Wendy Mullins 92645 (Gulf Coast Electric)
Created By
Makenzie Watts (City of Beaumont) j
Create Date
Oct 18, 2024 11:31 AM CST j
Invoice ID
1295
Attachments Warranty & Release of Lien.pdf
i
I
Retainage
Work Completed % 5.00
Materials Stored % 5.00
Line Items
Item Account WBSI Description Contract Previous Work Materials Total
# Code Section Total Payments Completed Stored (MS) Amount
(WC)
3.0 Construction
001 GC Contract 01000 Furnish and Install (4) VFDs 125,000.00 125,000.00 0.00 0.00 125,000.00
Grand Total 249,000.00
Item Account WJBS/ Description Contract Previous Work Materials Total
# Code Section Total Payments Completed Stored (MS) Amount
(WC)
002
GC Contract
01000
Mobilization
5,000.00
5,000.00
0.00
0.00
5,000.00
003
GC Contract
01000
Furnish and Install (4) New
9,500.00
9,500.00
0.00
0.00
9,500.00
Backup Float Switches
004
GC Contract
01000
Relocation of the
1,500.00
1,500.00
0.00
0.00
1,500.00
FleetZOOM Panel
005
GC Contract
01000
Bypass Pump
14,000.00
14,000.00
0.00
0.00
14,000.00
006
GC Contract
01000
Furnish and Install (1)
70,000.00
70,000.00
0.00
0.00
70,000.00
Pump Control Panel
007
GC Contract
01000
Terminate Existing and
39,500.00
39,500.00
0.00
0.00
39,500.00
Install New Conduit
Conductors
008
GC Contract
01000
Furnish and Install (1)
5,000.00
5,000.00
0.00
0.00
5,000.00
Transducer
009 GC Contract 01000
Remove and Dispose of
5,000.00
5,000.00
0.00
0.00
5,000.00
Existing Electrical and
Controls
010 GC Contract 01000
Testing/Start Up
2,500.00
2,500.00
0.00
0.00
2,500.00
Total
277,000.00
277,000.00
0.00
0.00
277,000.00
CO#001.001. VFD NEMA Rating Adjustment - 3.0 Const
001 GC Contract 01000
Furnish and Install (4) VFDs
-28,000.00
-28,000.00
0.00
0.00
-28,000.00
Total
-28,000.00
-28,000.00
0.00
0.00
-28,000.00
Grand Total
249,000.00
Summary
1. Contract Sum + Amendments 277,000.00
2. New Change by Change Request -28,000.00
--3-. Contract Sum -To-Da le -1 -+--L-i-n e-,2-)- 249,000.00
I
4. Total Completed & Stored To Date 249,000.00
5. Retainage
5a. 5.00% of Completed Work (Column I on Continuation Sheet) 0.00
5b. 5.00% of Stored Material (Column J on Continuation Sheet) 0.00
Total Retainage (5a + 5b) 0.00
6. Total Earned Less Total Retainage 249,000.00
7. Less Previous Certificates for Payment 236,550.00
8. Current Amount Due 12,450.00
9. Balance to Finish, Including Retainage (Line 3 less Line 6) 0.00
Additional Info
Line Item Type
Group
Accounting and Status
Lump sum
3.0 Construction
Capital Funding Source Construction - Rue Street LS - Electrical and Controls Improvements - SEP
Capital Project Fiscal Year 2024
- - ----- -- --- -- - -- ---- ---- --
PO Number 441216
..... .....
Approval (Approved)
User/ Role
Status Comments
Makenzie Watts (Project Manager)
Approved
Oct 21, 2024 10:11 AM CST
Amalia "Molly" Villarreal (City Engineer)
Approved
Oct 21, 2024 10:19 AM CST
Bart Bartkowiak (Director)
Approved
Oct 21, 2024 10:29 AM CST
Dara Woodruff (Admin)
Approved
Oct 31, 2024 10:29 AM CST