HomeMy WebLinkAboutRES 24-277RESOLUTION NO. 24-277
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on January 24, 2023, by Resolution 23-030, City Council awarded a
contract to Callan Marine, of Galveston, Texas, in the amount of $16,879,376.00, for the
Riverfront Park Restoration; and,
WHEREAS, previous Change Order Nos. 1-4, in the annount of $159,745.46, increased
the contract amount to $17,039,121.46; and,
WHEREAS, proposed Change Order No. 5, in the amount of $65,000.00, is necessary to
account for a design change from access stairways to an access ramp that meets the Americans
and Disabilities Act (ADA) Standards; and,
WHEREAS, the contract includes a contingency allowance of $1,000,000.00, if approved
Change Order No. 5, in the amount of $65,000.00, will be deducted from the contingency
allowance resulting in no change to the current contract amount; and,
WHEREAS, forty-two (42) calendar days are being requested to reflect actual time used
in the completion of the project;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order No. 5,
in the amount of $65,000.00 for additional work described above to be paid from the
contingency allowance, thereby resulting in no change to the current contract amount of
$17,039,121,46 for the Riverfront Park Restoration Project.
THAT, forty-two (42) calendar days are added to the contract,
The meeting at which this resolution was approved was in all things conducted in strict
compliance with the Texas Open. Meetings Act, Texas GoveriLment Code, Chapter 551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 29th day of
October, 2024.
t
- Mayor Roy West -
Projectmates
CITYOFBEAU MONT.PROJECT MATES. C0M
Change Order #001.005
PW1023-02 - Riverfront Park Restoration, 001 Main Street, Beaumont, Texas 77701 USA
Thursday, Oct 10, 2024
Change Order Details
Description
Division
Scope of Work
Notes
Awarded to
Created By
Create Date
Reason Code
Days Changed
Attachments
Additional Info
Line Item Type
Group
Dates
Grand Total. $0.00
Change Order No. 5
01 - General Requirements
This Change Order is necessary to account for a design change from access
stairways to an access ramp meeting the Americans with Disabilities Act (ADA)
standards. This design change will allow for the safety of pedestrians and
compliance with ADA regulations.
Due to the design change and extensive submittal process to account for the
change, Callan Marine is requesting an additional forty-two (42) Calendar days to
be added to the project. With the (42) calendar days being added the new Date of
Completion for this project is November 26, 2024,
Rick Alexander (Callan Marine Ltd), 29143
Chaz Duke (Callan Marine Ltd)
Sep 26, 2024 11:32 AM CST
Time Extension
42
22227-SL003 Letter Engineering Review Delay z lgned,pdf
Lump sure
3.0 Construction
Created On
Capital Planning
Capital Planning
Capital Project Fiscal Year
Accounting
Sep 26, 2024
Construction - Riverfront Park Restoration
2024
item Id 609
PO Number 441200
FEMA Number 6499
Accounting Project Code H13015
Summary
Original Contract Sum
Net Cost by Previous Approved Change Order
Contract Sum Before This Change Order
Contract Sum Changed By This Change Order
New Contract Sum
Substantial Completion Date
Net Time Change By Previous Change Order
Substantial Completion Before This Change Order
Time Changed By This Change Order
New Substantial Completion Date
All Change Orders of the Original Contract
16,879,376.00
159, 745.46
17,039,121.46
0,00
17,039,121.46
NIA
40 day(s)
NIA
42 day(s)
NIA
0.946394345383383840729667300%
Line Items
Item Account WBS/
# Code Section
Change Order 5
014 001
025 002413
Description
Total
Amount
Sidewalks - Labor (Design Change from access stairways to access 65,000.00
ramp for ADA compliance)
Project Contingency .65,000,00
Total 0.00
Approval (Pending)
User l Bole
Status
Brett Roebuck (External -Inspector)
Approved
Oct 10, 2024 09:57 AM CST
Cathrine Westerkamp (External -Engineer)
Approved
Oct 10, 202411:17 AM CST
David Tingle (Project Manager)
Approved
Oct 10, 202411,39 AM CST
Bart Bartkowiak (Director)
Approved
Oct 10, 2024 01:26 PM CST
Admin
Pending
Assistant City Manager
City Clerk
Due Date: Oct 17, 2024
Comments
Proectmates
CET YOFFIFAUMONT.PROJECT MAT FS.COM
Change Order #001.004
PW1023-02 e Riverfront Park Restoration, 801 Main Street, Beaumont, Texas 77701 USA
Monday, Aug 12, 2024
Change Order Details Grand Total: $0.00
Description
COff001.004; Change Order 4
Division
01 -General Requirements
Scope of Work
This Change Order is necessary to add or modify contract items in order to ensure safety to the public
or to adjust current contract bid items to meet current site conditions The costs for the following items
shall be credited to the contract's contingency budget: Construct an additional 94 linear feet of
handrail around the outfall structure to enhance safely; Install two Tideflex valves in the 48" storm
sewer outfall pipes located within the outfall structure; Add 11 feet 6 inches of sheet pile return wall on
the south end to accommodate the pending construction of the Port of Beaumont's sheet pile wall;
Rernove and replace 10 feel of 48" RCP storm sewer; Cut concrete piles to the specified grade;
Adjust the quantity of dredge material based on the results of the post -dredge survey.
Notes
Lanier & Associates submitted Rev 001- Rev 008 on the Construction Drawings and they have been
included in this Change Order for record purposes. Please see the attachment "Explanation of
Drawing Revisions".
Awarded to
Rick Alexander (Callan Marine Ltd), 29143
Created By
David Tingle (City of Beaumont)
Create Date
Jul 22, 2024 09:02 AM CST
Reason Code
Owner Requested
Days Changed
28
Attachments
24-02-27 Rev 5 IFC Drawings Riverfront Park 10888-1.pdf
24-04-26 Rev 6 IFC Drawings Rlverfront Park 10888-1.pdf
24-05.17 Rev 7 IFC Drawings Riverfront Park 10888-1.p ff
24-07-30Rev 8_ IFC Drawings Rivezfront Park 10888-1.pdf
23-04-19 Rev I. IFC Drawings Riverfront..Park 10888-1_.pdf
23-05-10 Rev 2 lFC Drawings Riverfront Park 10888-1.pdf
W70888-1.pdf
23-08-12 Rev 3 IFC Drawings Riverfront Park
23-11-15 Rev I1=C Drawings Riverfront Park 10888-1 pdf
006 Dredge uan! y Callan Beaumont AD.pdf
001 Ad6Hanal Handrail King Fab G�uote.pdf
002 Tideflex Check valve quntes.msg
003 New Sheets.msg
004 Replace 48 RCP - Beaumont 04.12.2024.pdf
Callan Marine Concrete rile Invoice 07.08 24 2.pdf
Explanation of Drawing Revisions- LA10888-1 pdf
Additional Info
Line Item Type Lump sum
Group 3.0 Construction
Dates
Created On Jul 22, 2024
Capital Planning
Capital Planning Construction - Riverfront Park Restoration
Capital Project Fiscal Year 2024
Accounting
E
Item ld 576
PO Number 441200
FEMA Number 6490
Accounting Project Code 1-113015
Summary
Original Contract Sum
16,879,376,00
Net Cost by Previous Approved Change Order
159,745.46
Contract Sum Before This Change Order
17,039,121.46
Contract Sum Changed By This Change Order
0.00
New Contract Sum
17,039,121.46
Substantial Completion Date
NIA
Net Time Change By Previous Change Order
12 day(s)
Substantial Completion Before This Change Order
NIA
Time Changed By This Change Order
28 day(s)
New Substantial Completion Date
N/A
All Change Orders of the Original Contract
0.946394346383303840729667300%
Line Items
Item Account
41 Code
Change Order 4
001
002
003
004
005
WBSI Description Total
Section Amount
002413
Installation of(] 021-F) Addition at Handrail Around Outfall Structure ($527.16/LF)
53,770.55
002413
Installation of (2) Tide Rex Valves In the 48' pipe at Oulfall Structure
94,224.10
002413
Inslallatlon of (18'4TF) of Additional Sheelpile for Return Wall ($4,756.19&1`)
53,105.85
002413
Installation of an Additional (16LF) of 48" RCP Pipe ($591.89/LF)
9,470.25
002413
Quantity adjustment for Dredge Material Fallowing the Completion of the After-Dredge
-53,292.65
Survey
002413
Cut Concrele Piles to Grade
14,764.85
002410
Additional (50') FrameTuhing on Large Pavilion ($53.98/LF)
2,699.05
002413
ProJeot Contingency
-174,742.00
Total
0.00
Approval (Pending)
User I Role
Brett Roebuck (External -inspector)
Cathrine Westerkamp (External -Engineer)
David Tingle (project Manager)
City Engineer
Director
Admin
Assistant City Manager
City Clerk
Status
Approved
Aug 12, 2024 11:22 AM CST
Approved
Aug 12, 202411:22 AM CST
Approved
Aug 12, 2024 11:26 AM CST
Pending
Due Date: Aug 19, 2024
Comments
In
f {atc
Prvjectl r r� res CtTYOFBEAUMONT.AROJECTMATE&COM
Change Order #001.003
PW1023-02 - Riverfront Park Restoration, 801 Main Street, 8eaurnont, Texas 77701 USA
Monday, Aug 12, 2024
Change Order Details Grand Total:
Description
CO#001.003: Change Order 3
Division
01 - General Requirements
Scope of Work
This change order is required to make an administrative adjustment to include the RESTORE Council
Financial Assistance Standard Terms and Conditions to the executed contract documents with Callan
Marine. These Terms and Conditions are required to be Incorporated into the Contract Documents as
a condition of receiving grant funding by the Texas Commission on Environmental Quality (TCEQ)
under the RESTORE grant for this project.
Notes
Attached are the RESTORE Council Financial Assistance Standard Terms and Conditions that are
now included as a part of the Executed Contract Documents for Construction with Callan Marine,
Awarded to
Rick Alexander (Callan Marine Ltd), 29143
Created By
David Tingle (City of Beaumont)
Create Date
Jul 22, 2024 08:18 AM CST
Reason Code
Owner Requested
Days Changed
0
Attachments
61tachments for Amendment Nag - Riverfrorit Park Restoration FE fA No6499 Contract.(1),pdf
Executed Riverfront Park Restoration FEMA No6499 Contract with Amendment Not pdi
Additional info
Line Item Type
Lump sum
Group
3.0 Construction
Dates
Created On
Jut 22, 2024
Capital Planning
Capital Planning
Construction - Riverfront Park Restoration
Capital Project Fiscal Year 2024
Accounting
Item Id 576
PO Number 441200
FEMA Number 6499
Accounting Project Code H13015
Summary
Original Contract Sum
16,879,376.00
Not Cost by Previous Approved Change Order
159,745.46
Contract Sum Before This Change Order
17,039,121.46
Contract Sum Changed By This Change Order
0,00
New Contract Sum
17,039,121.46
Substantial Completion Date
NIA
Net Time Change By Previous Change Order
12 day(s)
Substantial Completion Before This Change Order
NIA
Time Changed By This Change Order
0 day(s)
New Substantial Completion Date
NIA
All Change Orders of the Original Contract
0.946394345383383840729657300%
Approval (Approved)
User / Rote Status Comments
Chaz Duke (Exte(nal-GC) Approved
Jul 22, 2024 08:40 AM CST
Cathrine Westerkamp (External -Engineer) Approved
Jul 22, 2024 08:42 AM CST
David Tingle (Project Manager) Approved
Jul 22, 2024 08:46 AM CST
Amalia "Molly" Villarreal (City Engineer) Approved
Jul 22, 2024 09:54 AM CST
User / Role
Bart Bartkowiak (Director)
Crystal Valencia (Admin)
June Ellis (Assistant City Manager)
Tina Broussard (City Clerk)
Status
Approved
Jul 22, 2024 01:17 PM CST
Approved
Jul 22, 2024 02:20 PM CST
Approved
Jul 23, 2024 08:32 AM CST
Approved
Ju123, 2024 05:29 PM CST
Comments
Projectmates
CITYO FBEAU MO N T. PROJ ECT M AT ES.CO M
Change Order #001.002
PW1023-02 - Riverfront Park Restoration, 801 Main Street, Beaumont, Texas 77701 USA
Monday, Aug 12, 2024
Change Order Details
Grand Total,. $0.00
Description
Change Order No, 2: Steel Sheet Pile Anchored Wall Itern Breakout (RESTORE Funds and FEMA
Funds)
Division
01 - General Requirements
Notes
This change order was required to make an administrative adjustment to separate the single line item
for the Steel Sheet Pile Anchored Wall into two separate line items, The adjustment of the single line
item into Wo line items will allow the City and grant auditors to track expenses between the two grant
funding sources (TCEQ RESTORE fund and FEMAICity funds) for the Steel Sheet Pile Anchored Wall
line item, The City's project management software requires this administrative change to be
processed as a change order.
Awarded to
Rick Alexander (Callan Marine Ltd), 29143
Created By
David Tingle (City of Beaumont)
Create Date
Sep 01, 2023 09:51 AM CST
Reason Code
Owner Requested
Days Changed
0
Additional Info
Line Item Type
Lump suns
Group
3.0 Construction
Dates
Created On Sep 01, 2023
Capital Planning
Capital Planning Construction - Riverfront Park Restoration
Capital Project Fiscal Year 2023
Accounting
Item Id
457
PO Number
433176
FEMA Number
6499
i
Accounting Project Code
H13015
Summary
Original Contract Sutra
16,879,376.00
Net Cast by Previous Approved Change Order
Mo
Contract Sum Before This Change Order
16,879,376.00
Contract Sum Changed By This Change Order
0.00
New Contract Sum
16,879,376.00
Substantial Completion Pate
NIA
Net Time Change By Previous Change Order
0 day(s)
Substantial Completion Before This Change Order
NIA
Time Changed By This Change Order
0 day(s)
New Substantial Completion Date
NIA
All Change Orders of the Original Contract
0%
Line Items
Item #I Account Code
WBS/ Section
Description
Total Amount
4 - Steel Sheet Pile Anchored Wall
Doi Labor
001
Steel Street Pile Anchored Wall - Labor
-1,584,205.99
i
002 Equipment
001
Steel Sheet Pile Anchored Wall - Equipment
-797,414.55
003 Material
001
Steel Street Pile Anchored Wall - Material
-5,08,021.46
4 - Steel Sheet Pile Anchored Wall (FEMA ry CITY Fu
001 Labor
001
Steel Sheet Pile Anchored Well - Labor (FEMA & CITY Funds)
455,562.67
I
002 Equipment
001
Steel Sheet Pile Anchored Wall - Equipment (FEMA & CITY Funds)
229,30 ,75
Total
0.00
Item 4 Account Code WBS/ Section
Description
Total Amount
003 Material 001
Steel Sheet Pile Anchored Wall - Material (FEMA & CITY Funds)
1,494,770.58
4 - Steel Sheet Pile Anchored Wall (RESTORE Funds)
001 Labor 001
Steel Sheet Pile Anchored Wall - Labor (RESTORE Funds)
1,128,643.62
002 Equipment 002
Steel Sheet Pile Anchored Wall - Equipment (RESTORE Funds)
568,105.5D
003 Material 003
Steel Sheet Pile Anchored Wall - Material (RESTORE Funds)
3,703,250.88
Total 0.00
Approval (Approved)
User / Role
Status
Comments
Rick Alexander (External -GC)
Approved
Sep 07, 2023 04:12 PM CST
David Tingle (Project Manager)
Approved
Sep 07, 2023 04:13 PM CST
Amalia "Molly" Villarreal (City Engineer)
Approved
Sep 07, 2023 05:21 PM CST
Bart Bartkowiak (Director)
Approved
Sep 08, 2023 08:58 AM CST
Crystal Valencia (Admin)
Approved
Sep 08, 2023 08:59 AM CST
June Ellis (Assistant City Manager)
Approved
Sep OB, 2023 09:13 AM CST
Tina Broussard (City Clerk)
Approved
Sep OB, 2023 09:14 AM CST
Projectmates CITYOFBEAUMONT.PROJECTMATES.COM
Change Order #001.001
PW1023-02 - Riverfront Park Restoration, 801 Main Street, Beaumont, Texas 77701 USA
Monday, Aug 12, 2024
Change Order Details Grand Total., $159,745.46
Description Change Order No. 1: Concrete/ Brick Debris & Creosote Removal.
Division
36 - Waterway and Marine Construction
Scope of Work
This requested change order is necessary to remove and properly dispose of substantial amounts of
unforeseen buried concrete debris, a brick wall structure, and buried creosote pilings. The debris and
pilings were discovered once construction began, despite several surveys to identify any potential
conflicts to the new improvements. This debris conflicts with placement of both the ACBM mat and the
bulkhead wall on the north end of the Riverfront Park and must be removed and properly disposed of
for construction to continue.
Awarded to
Rick Alexander (Callan Marine Ltd), 29143
Created By
Rick Alexander (Callan Marine Ltd)
Create Date
Aug 18, 2023 02:26 f M CST
Reason Code
Unforseen Site Conditions
Days Changed
12
Attachments
RES 23-319 Riverfront Park COi.pdf
2s dumpsfers.pdf
Grange Order 1 - Concrete Debris & Creosote Removal.pdf
Change Order rep-gAs.pdf
Creosote Dorn sp ers.pdf
Additional Info
Une Item Type Lump sum
Group 3.0 Construction
Dates
Created On Oct 13, 2023
Capital Planning
Capital Planning Construction - Riverfront Park Restoration
Capital Project Fiscal Year
2023
Accounting
ltem Id
448
PO Number
433176
FFMA Number
6499
Accounting Project Code
H13015
Summary
Original Contract Sum
Net Cost by Previous Approved Change Order
Contract Sum Before This Change Order
Contract Sum Changed By This Change Order
New Contract Sum
Substantial Completion Date
Net Time Change By Previous Change Order
Substantial Completion Before This Change Order
Time Changed By This Change Order
New Substantial Completion Date
All Change Orders of the Original Contract
Line Items
Item # Account Code WBS/ Section
Concrete and Brick Debris Removai - Change Order 1
001 Concrete/ Brick 35202113
002 Creosote 352023.13
Approval (Approved)
16,879,376.00
0.00
16,879,376.00
159,745.46
17,039,121.46
N/A
0 day(s)
NIA
12 day(s)
N/A
0.946394346383383840729667300%
Description
Concrete/ Brick Debris Removal
Creosote Timber Pile Removal
Total Amount
128,214,13
31,531,33
Total 159,745.46
User / Role
Status Comments
Brett Roebuck (External -Inspector)
Approved
Oct 16, 2022 09:06 AM CST
Chris Guy (inactive) (External -Engineer)
Approved
Oct 16, 2023 10:58 AM CST
David Tingle (Project Manager)
Approved
Oct 16, 2023 11:03 AM CST
Amalia "Molly" Villarreal (City Engineer)
Approved
Oct 19, 2023 02:57 PM CST
Bart Bartkowlak (Director)
Approved
Oct 20, 2023 10:30 AM CST
Crystal Valencia (Adman)
Approved Approved on 10.31.23 by Res. No. 23-319
Nov 01, 2023 08:03 AM CST
June Ellis (Assistant City Manager)
Approved
Nov 02, 2023 09:59 AM CST
Tina Broussard (City Clerk)
Approved
Nov 02, 2023 09:59 AM CST