HomeMy WebLinkAboutRES 24-256RESOLUTION N0.24-256
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on November 7, 2023, by Resolution 23-338, City Council awarded a
contract to ALLCO, LLC, of Beaumont, Texas, in the amount of $6,847,514.00, for the Street
Rehabilitation Citywide- Phase V (REBID) Project; and,
WHEREAS, previous Change Order Nos. 1-4, in the amount of $1,661,133,75, increased
the contract amount to $8,508,647,75; and,
WHEREAS, proposed Change Order No. 5, in the amount of $108,974.28, is required for
the addition of a shoulder improvement and additional concrete repairs for the rehabilitation of
the Wastewater Treatment Plant Roadway. If approved, the new contract amount will be
$8,617,622.03; and,
WHEREAS, thirty-five (35) additional calendar days are requested for additional work;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order No. 5,
in the amount of $108,974.28, for the work described above, thereby making the new contract
amount to $8,617,622,03, for the Street Rehabilitation Citywide- Phase V (REBID) Project; and,
THAT thirty-five (35) additional calendar days are added to the contract; and,
The meeting at which this resolution was approved was in all things conducted in strict
compliance with the Texas Open Meetings Act, Texas Government Code, Chapter 551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 15th day of
October, 2024.
Projectmates
CITYOFBEAU MONT.PRO.lECTMATES. COM
Change Order #001.005
PWO823-12 - Street: Rehabilitation Citywide Phase V (REBID), 801 Main Street, Beaumont, TX
77701 United States
Tuesday, Sep 24, 2024
Change Order Details
Description
Division
Scope of Work
Created By
Create Date
Reason Code
Days Changed
Attachments
Grand Total:
$108,974.28
Change Order No.5: WWTP Repairs
01 - General Requirements
Shoulder improve mentlroadway widening from Station 40+54 to Station
42+91 of Road A to include a 12" asphalt stabilized base (ASB), with a
1.5" Type-D Level -up and a 1.25" Type-F Wearing Surface to match the
proposed paving surface cross-section of the existing roadway.
Additional concrete repairs.
Wastewater Treatment Plant (WWTP) Staff requested that a section of
the WWTP main roadway, adjacent to the admin building parking lot,
from approximate Station 40+54 to Station 42+91, receive shoulder
improvements and that the section of roadway be widened to
accommodate the passing of heavy truck traffic and other vehicles
through this narrow section of roadway. Additional concrete repairs are
needed. These additional repairs were discovered after milling
operations exposed the condition of the concrete beneath the layers of
asphalt.
Brandon Harrison (Allco, LLC), 6854
Julie Hammond (City of Beaumont)
Sep 20, 2024 09:32 AM CST
Owner Requested
35
Street Rehab - Phase V (REBID)-WWTP RDT94-A.pdf
'
. Additional Info �
�
Line Item Type Unit price .
Group 3.0Conutruot|on !
! |
'
Dates �
/
|
Created On Sep 20.2U24 �
' | �
! �
Org.Sub. Completion Jan U6.2025 �
' | �
`
Ca�`��U����nm`�KJ
| ) ' ^~�^ Planning !
'
. �
Capital Planning Construction ' Street Rehabilitation Phase V/REB|D\ !
� .
Capital Fiscal 20�4 !
' ' |
Year
!
|
A������t]��
`
�
~ |
'
' |
�
Item N 805
PO Number 442398/444080
� ! �
'
. .
| Summary
�
/
!
|
! | |
' Original 8.847`51�/}0
� | �'`'—� |
!
! '
! ! Net Cost bvPrevious Approved Change Order 1.661`133.75 |
Contract Sum Before This Change Order 8.508/647.75 |
. ,
Contract Sum Changed By This Change Order
New Contract Sum
Substantial Completion Date
Net Time Change By Previous Change Order
Substantial Completion Before This Change
Order
Time Changed By This Change Order
New Substantial Completion Date
All Change Orders of the Original Contract
Line Items
Item
Account
WBS/
#
Code
Section
Contract Items
247
6002
999
340
6002
999
340
6005
999
Description
108,974.28
8,617,622.03
Jan 06, 2025
231 day(s)
Aug 25, 2025
35 day(s)
Sep 29, 2025
25.850374749142535524571399200%
Quantity UoM Unit Total
Price Amount
FLEX BASE (CMP IN 275.22
PLACE) (TY A GR 2)
(6") WWTP
D-GR HMA TY-D PG70- 18.50
22 (1.5°) (LEVEL -UP)
WWTP
D-GR HMA TY-F PG70- 15.50
22 (1.25") (WEARING
SURFACE) WWTP
SY 44.00 12,109.68
TON 201.00 3,718.50
TON 206.00 3,193.00
Total 108,974.28
Item Account WBS/
Description Quantity UoM Unit
Total
# Code Section
Price
Amount
351 6002 999
REPAIR OF FLEXIBLE 306.30 SY 138.50
42,422.55
PAVEMENT (W) (ASI3
PG 64-22) WWTP
361 6002 999
REPAIR CONCRETE 275.22 SY 167.25
46,030,55
PAVEMENT (6")
WWTP
502 6002 9999
BARRICADES, SIGNS & 1.00 MON 1,500.00
1,500.00
TRAFFIC HANDLING
WWTP
Total
108,974.28
Approval (Pending)
Due Date:
Oct 01, 2024
User I Role
Status
Comments
Brandon Harrison (External GC)
Approved
Sep 24, 2024 09:31 AM CST
David Tingle (Project Manager)
Approved
Sep 24, 2024 09:37 AM CST
Amalia "Molly" Villarreal (City Engineer) Approved
Sep 24, 2024 01:27 PM CST
Bart Bartkowiak (Director)
Approved
Sep 24, 2024 02:39 PM CST
Admin
Pending
User 1 Role Status Comments
Assistant City Manager
City Clerk
Projectmates
CITY0FBEAUMONTYROJECTMATE&COM
Change Order #001.004
PWO823-12 - Street Rehabilitation Citywide Phase V (REBID), 801 Main Street, Beaumont, TX
77701 United States
Thursday, Sep 26, 2024
Change Order Details
Description
Division
Notes
Grand Total:
$9,986.00
Change Order No* Coburn Drive Quiet Zone
01 - General Requirements
A representative of Benesch, Union Pacific Rail Road's (UPRR)
consultant, made a site visit to Coburn Drive at UPRR's rail road
crossing for a scheduled pre -pour inspection on Friday, September
13th. During the inspection, the UPRR consultant contacted the Federal
Railroad Administration (FRA). The consultant stated that the
preapproved median design was compliant with UPRR standards,
however noncompliant for FRA standards. Design improvements to the
quiet zone median have been made and are reflected through the items
in this change order in order to construct a median both UPRR and FRA
compliant.
Awarded to Brandon Harrison (Allco, LLC), 6854
Created By Julie Hammond (City of Beaumont)
Create Date Sep 18, 2024 09:43 AM CST
Reason Code Owner Requested
Days Changed
Attachments
Additional Info
21
2024091811683181 5.pdf
Line Item Type Unit price
Group 3.0 Construction
Dates
Created On Sep 18, 2024
Org. Sub. Completion Jan 06, 2025
Capital Planning
Capital Planning Construction - Street Rehabilitation Phase V (REBID)
Capital Project Fiscal 2024
Year
Accounting
Item ld 603
PO Number 4423981444080
Summary
Original Contract Sum 6,847,514.00
Net Cost by Previous Approved Change Order 1,651,147.75
Contract Sum Before This Change Order 8,498,661.75
Contract Sum Changed By This Change Order 9,986.00
New Contract Sum 8,508,647.75
Substantial Completion Date
Jan 06, 2025
Net Time Change By Previous Change Order
210 day(s)
Substantial Completion Before This Change
Aug 04, 2025
Order
Time Changed By This Change Order
21 day(s)
New Substantial Completion Date
Aug 25, 2025
All Change Orders of the Original Contract
24.258931781665579654163540230%
Line Items
Item Account WBS/ Description
Quantity
UoM Unit Total
# Code Section
Price Amount
Contract Items
529 9999 500 CONC CURB (QUIET
-178,00
LF 58,00-10,324.00
ZONE) (CLASS P)
529 9998 500 CONC VERTICAL CURB
200.00
LF 84.00 16,800,00
(QUIET ZONE) (CLASS
P) (10")
658 6051 600 INSTIL OM ASSM (OM
2.00
EA 400.00 800.00
3L) (FLX) SRF
9999 6002 9900 RAILROAD FLAGGER
1.00
LS 2,710.00 2,710.00
Total 9,986.00
Approval (Approved)
User / Role
Status
Brandon Harrison (External -GC)
Approved
Sep 18, 202412:42 PM CST
David Tingle (Project Manager)
Approved
Sep 18, 202412:43 PM CST
Amalla "Molly" Villarreal (City Engineer)
Approved
Sep 20, 2024 04:55 PM CST
Bart Bartkowiak (Director)
Approved
Sep 23, 2024 01:57 PM CST
Crystal Valencia (Admin)
Approved
Sep 23, 2024 01:59 PM CST
June Ellis (Assistant City Manager)
Approved
Sep 23, 2024 04:25 PM CST
Tina Broussard (City Clerk)
Approved
Sep 23, 2024 04:59 PM CST
Comments
Projectmates
CITYUBEAUMONT.PROJECTMATES.COM
Change Order #001.003
PWO823-12 - Street Rehabilitation Citywide Phase V (REDID), 801 Main Street, Beaumont, TX
77701 united States
Monday, May 13, 2024
Grand Total:
Change Order Details
$1,026,822.00
Description
Change Order No.3: WWTP
Division
01 - General Requirements
Scope of Work
The costs for the rehabilitation of the roads at the Wastewater
Treatment Plant were bid as additive bid items. Additive bid items are
not part of the original scope of work, they are optional and can be
added later if the budget allows. This proposed Change Order will add
these items to the contract at the prices received at the time of bidding.
Awarded to
Brandon Harrison (Allco, LLC), 6854
Created By
Julie Hammond (City of Beaumont)
Create Date
May 08, 2024 02:18 PM CST
Reason Code
Owner Requested
Days Changed
60
Additional Info
Line Item Type
Unit price
Group
3.0 Construction
Dates
Created On May 08, 2024
Org. Sub. Completion Jan 06, 2025
Accounting
Item Id 555
Summary
Original Contract Sum
Net Cost by Previous Approved Change Order
Contract Sure Before This Change Order
Contract Sum Changed By This Change Order
New Contract Sum
Substantial Completion Date
Net Time Change By Previous Change Order
Substantial Completion Before This Change
Order
Time Changed By This Change Order
New Substantial Completion Date
All Change Orders of the Original Contract
Line Items
6,847,514.00
624,325.75
7,471,839.75
1,026, 822.00
8,498,661.75
Jan 06, 2025
150 day(s)
Jun 05, 2025
60 day(s)
Aug 04, 2025
24.113097833753972609621535640%
Item
Account
WBS/
Description
Quantity
UoM
Unit
Total
#
Code
Section
Price
Amount
Contract items
100
6002
999
PREP ROW (NOT TO
79.00
STA
290.00
22,910.00
EXCEED $300 PER
STATION) WWTP
247
6002
999
FLEX BASE (CMP IN
1,152.00
SY
44,00
50,688.00
PLACE) (TY A GR 2)
(6") WWTP
275
6013
999
CEMENT TRT (MIX
1,747.00
SY
25.00
43,675.00
EXISTING MATERIAL)
(8") WWTP
340
6002
999
D-GR HMA TY-D
1,108.00
TON
201.00
222,708.00
PG70-22 (1.5")
(LEVEL -UP) WWTP
340
6005
999
D-GR HMA TY-F
1,075.00
TON
206.00
221,450,00
PG70.22 (1.25")
(WEARING SURFACE)
WWTP
351
6002
999
REPAIR OF FLEXIBLE
192.00
SY
138.50
26,592.00
PAVEMENT (8") (ASB
PG 64 22) WWTP
354
6096
999
PLANE ASPH CONC
10,712.00
SY
6.25
66,950.00
PAV (1"TO 3") WWTP
361
6002
999
REPAIR CONCRETE
1,152.00
SY
167,25
192,672.00
PAVEMENT (6")
WWTP
Total
1,026,822.00
Item
Account
WBS/
Description
Quantity
UoM
Unit
Total
#
Code
Section
Price
Amount
500
6002
999
MOBILIZATION (NOT
1.00
LS
44,000.25
44,000.25
TO EXCEED 5%)
WWTP
502
6001
999
BARRICADES, SIGNS
3.00
MON
1,500.00
4,500.00
& TRAFFIC
HANDLING WWTP
530
6012
999
INTERSECTIONS,
226.00
TON
297.00
67,122.00
DRIVEWAYS, AND
TURNOUTS (ACP)
666 6005 999
713 6006 999
Approval (Pending)
User 1 Role
Brandon Harrison (External -GC)
u�:
REFL PAV MRK TY 1 140.00 LF
(WHITE) (4°) (SOLID)
(100 MIL) (NO
SEALER REQUIRED)
WWTP
CLEANING AND 11,867.00 LF
SEALING JOINTS
AND CRACKS WWTP
8,95 1,253,00
5.25 62,301.75
Total 1,026,822.00
Due Date: May 20, 2024
Status
Approved
May 13, 2024 09:16 AM CST
Comments
User 1 Role
David Tingle (Project Manager)
Amalia "Molly" Villarreal (City Engineer)
Bart Bartkowiak (Director)
Admin
Assistant City Manager
City Clerk
Status
Approved
May 13, 2024 09:17 AM CST
Approved
May 13, 2024 09:22 AM CST
Approved
May 13, 202411:30 AM CST
Pending
Comments
Projoctmates
CITYOFBEAUMONT. PROJECTMATES.COM
Change Order #001.002
PWO823-12 - Street Rehabilitation Citywide Phase V (REDID), 801 Main Street, Beaumont, TX
77701 United States
Monday, May 13, 2024
Change Order Details
Description
Division
Scope of Work
Notes
Awarded to
Created By
Create Date
Reason Code
Days Changed
Grand Total:
$473,489.00
Change Order No. 2
01 - General Requirements
Angelina Street: Items to remove and replace damaged and collapsed
storm sewer infrastructure discovered at three different intersections
after construction commenced. CC&G point repairs to realign gutterlines
on Angelina Street for conveyance of stormwater runoff. Zavalla Drive:
Items for point repairs to remove and replace broken pin -on curb on
Zavalla Drive, Rusk Street: A change in curb inlet type from a standard
curb inlet to a Type R curb inlet is needed after an existing grate inlet
was removed and roots were discovered from a nearby oak tree that
presented difficulties in relocating the inlet to the back of the curb. Also,
an additional 33-sy for Item 361- Repair Concrete Pavement (6") is
needed for the repairs at the intersection of Rusk & 6th (scoped out in
C.O.#1) as the paving area was adjusted 4-ft to the east due to a crack
in the existing concrete pavement and also due to actual field
measurements. The contractor is requesting an additional 90 calendar
days for the additional work to be performed on Angelina Street and
Zavalla Drive. No additional calendar days will be required for the
change in inlet type and additional concrete repair for Rusk Street.
See attachments. '2024.03.05RDT1 02-106 repair details' attachment
for reference.
Brandon Harrison (Allco, LLC), 6854
Julie Hammond (City of Beaumont)
Apr 18, 2024 09:09 AM CST
Unforseen Site Conditions
.o
Attachments
Additional info
Line Item Type
Group
Dates
Created On
Org. Sub. Completion
Capital Planning
Capital Planning
Capital Project Fiscal
Year
Accounting
Item Id
PO Number
Summary
RES 24-121.pdf
2024.04.23 Angelina CC&G, Pavement & Drainage Repairs.pdf
2024,03.05 RDT102-106 repair details.pdf
Unit price
3.0 Construction
Apr 18, 2024
Jan 06, 2025
Construction - Street Rehabilitation Phase V (REBID)
2024
547
442398
Original Contract Sum
6,847,514.00
Net Cost by Previous Approved Change Order
150,836.75
Contract Sum Before This Change Order
6,998,350.75
Contract Sum Changed By This Change Order
473,489.00
New Contract Sum
7,471,839.75
Substantial Completion Date
Jan 06, 2025
Net Time Change By Previous Change Order
60 day(s)
Substantial Completion Before This Change
Mar 07, 2025
Order
Time Changed By This Change Order
90 day(s)
New Substantial Completion Date
Jun 05, 2025
All Change Orders of the Original Contract
9.117553465389044841675387590%
Line Items
Item Account
WBSI
# Code
Section
Contract Items
104 6021
100
104 6022
100
247 6001
200
Description Quantity UoM Unit Total
Price Amount
REMOVING 394,00 LF
CONCRETE (CURB)
REMOVING 174.00 LF
CONCRETE (CURB &
GUTTER)
FLEX BASE (CMP IN 1,057.00 SY
PLACE) (TY A OR 2)
8.00 3,152.00
19.00 3,306.00
40.00 42,280,00
Total 473,489.00
Item
Account
WBS/
#
Code
Section
361
6001
300
400
6002
400
4122
9999
4000
465
6001
400
465
6003
400
465
6002
400
496
6002
400
496
6003
400
502
6001
500
529
6002
500
529
6008
500
Description
Quantity
UoM
Unit
Total
Price
Amount
(8.)
REPAIR CONCRETE
1,038.00
SY
180.00
186,840.00
PAVEMENT (6")
CEMENT STABILIZED
126,00
CY
114.00
14,364.00
BACKFILL (2SK/CY
SAND)
HP STORM PIPE (15")
239.00
LF
189.00
45,171.00
(INCLUDES REMOVAL
OF EXISTING PIPE)
CURB INLET (COMPL)
5.00
EA
7,778,00
38,890.00
CURB INLET (TYPE R)
5.00
EA
8,170,00
40,850.00
(COMPL)
MANHOLE (COMPL)
3.00
EA
10,736.00
32,208.00
REMOVE STR (INLET)
10.00
EA
1,494.00
14,940.00
REMOVE STR
3.00
EA
2,626.00
7,878.00
(MANHOLE)
BARRICADES, SIGNS &
3.00
MON
5,000.00
15,000.00
TRAFFIC HANDLING
(NOT TO EXCEED
$5,000 PER MONTH)
CONC CURB (TY II)
344.00
LF
25.00
8,600,00
CONC CURB &
174.00
LF
115,00
20,010.00
GUTTER (TY II)
(INCLUDES 6" FLEX
BASE)
Total 473,489.00
Approval (Approved)
User / Role Status Comments
Brandon Harrison (External- Approved
GC) Apr 24, 2024 01:19
PM CST
David Tingle (Project Approved
Manager) Apr 24, 2024 02:02
PM CST
Amalia "Molly" Villarreal
Approved
(City Engineer)
Apr 25, 2024 05:30
PM CST
Bart Bartkowiak (Director)
Approved
Apr 29, 2024 04:32
PM CST
Crystal Valencia (Admin)
Approved Approved by City Council on May 7, 2024, by
May 07, 2024 05:25 Resolution No, 24-121.
PM CST
June Ellis (Assistant City
Approved
Manager)
May 08, 2024 09:30
AM CST
Tina Broussard (City Clerk)
Approved
May 08, 2024 09:50
AM CST
Piro ectmates
CITYOF8EAU MONT.PROJECTMATES.COM
Change Order #001.001
PWO823-12 A Street Rehabilitation Citywide Phase V (REBID), 801 Main Street, Beaumont, TX
77701 United States
Monday, May 13, 2024
Change Order Details
Description
Division
Scope of Work
Awarded to
Created By
Create Date
Reason Code
Days Changed
Attachments
Additional Info
Grand Total:
$1500836.75
CO#001.001: 001
01 - General Requirements
Rusk Street: Items to remove and replace damaged or collapsed parts
of storm sewer infrastructure discovered after construction commenced.
CC&G point repairs to realign gutterlines on Rusk Street for conveyance
of stormwater runoff. The contractor is requesting an additional 60
calendar days for delays and the additional work to be performed on
Rusk Street. Masterson Drive & Potter Drive: Change in scope of work
for Masterson and Potter from mill & ASB repairs to mixing the existing
base with cement slurry. No additional calendar days will be required for
the change in scope of work to be performed on Masterson Drive and
Potter Drive.
Brandon Harrison (Alice, LLC), 6854
Julie Hammond (City of Beaumont)
Mar 08, 2024 03:36 PM CST
Unforseen Site Conditions
2024.03.12 Rusk CC&G Repairs.p ff
RES 24-094 Street Rehab Phase V.pdf
2024.03.11 Rusk Pavement & Drainage Repairs.pdf
Line Item Type Unit price
Group 3.0 Construction
Dates
Created On Mar 08, 2024
Org. Sub. Completion Jan 06, 2025
Capital Planning
Capital Planning Construction - Street Rehabilitation Phase V (REBID)
Capital Project Fiscal 2024
Year
Accounting
Item Id 524
PO Number 442398
Summary
Original Contract Sum
6,847,514.00
Net Cost by Previous Approved Change Order
0.00
Contract Sum Before This Change Order
6,847,514.00
Contract Sum Changed By This Change Order
150,836.75
New Contract Sum
6,998,350.75
Substantial Completion Date
Net Time Change By Previous Change Order
Substantial Completion Before This Change
Order
Time Changed By This Change Order
New Substantial Completion Date
All Change Orders of the Original Contract
Jan 06, 2025
0 day(s)
Jan 06, 2025
60 day(s)
Mar 07, 2025
2.2027957883693264446045674400%
Line Items
Item Account
WBS/
Description
Quantity
UoM
Unit
Total
# Code
Section
Price
Amount
Contract Items
104 6021
100
REMOVING
98,00
LE
8.00
784.00
CONCRETE (CURB)
104 6015
100
REMOVING
20.00
SY
80.00
1,600.00
CONCRETE
(SIDEWALKS)
104 6022
100
REMOVING
481.00
LF
19.00
9,139,00
CONCRETE (CURB &
GUTTER)
247 6001
200
FLEX BASE (CMP IN
316.00
SY
40.00
12,640.00
PLACE) (TY A GR 2)
275 6012
200
CEMENT TRT (MIX
5,531.00
SY
15.50
85,730.50
EXISTING MATERIAL)
Total
150,836.75
Item
Account
WBS/
Description
Quantity
UoM
Unit
Total
Code
Section
Price
Amount
(8" TO 10")
351
6001
300
REPAIR OF FLEXIBLE
-1,235.00
SY
90.00
-111,150.00
PAVEMENT (8" ASB)
354
6096
300
PLANE ASPH CONC
4,939.00
SY
5,25
25,929.75
PAV 0 " TO 3")
361
6001
300
REPAIR CONCRETE
316.00
SY
180.00
56,880.00
PAVEMENT (6")
401
6001
400
FLOWABLE BACKFILL
23.00
CY
408.00
9,384.00
4122
9999
4000
HP STORM PIPE (15")
48.00
LF
189.00
9,072.00
(INCLUDES REMOVAL
OF EXISTING PIPE)
465
6001
400
CURB INLET (COMPL)
5.00
EA
7,778.00
38.890.00
465
6002
400
MANHOLE (COMPL)
1.00
EA
10,736.00
10,736.00
496
6002
400
REMOVE STIR (INLET)
5.00
EA
1,494.00
7,470.00
496
6003
400
REMOVESTIR
1.00
EA
2,626.00
2,626.00
(MANHOLE)
502
6001
500
BARRICADES, SIGNS &
2.00
MON
5,000.00
10,000.00
TRAFFIC HANDLING
(NOT TO EXCEED
$5,000 PER MONTH)
529
6002
500
CONIC CURB (TY 11)
98.00
LF
25,00
2,450.00
529
6008
500
CONC. CURB &
481,00
LF
115.00
55,315,00
GUTTER (TY II)
Total 150,836.75
Item
Account
WBSI
Code
Section
531
6001
500
713
6005
700
Approval (Approved)
Description Quantity UoM Unit Total
Price Amount
(INCLUDES 6" FLEX
BASE)
CONC SIDEWALKS (4") 20.00 SY
CLEANING AND-6,000.00 LF
SEALING JOINTS AND
CRACKS
User / Role Status
Brandon Harrison (External- Approved
GC) Mar 12, 2024 03:44
PM CST
David Tingle (Project
Approved
Manager)
Mar 12, 2024 03:56
PM CST
Amalia "Molly" Villarreal
Approved
(City Engineer)
Mar 12, 2024 04:01
PM CST
Bart Bartkowiak (Director)
Approved
Mar 12, 2024 05:03
PM CST
230.00 4,600.00
4.90-29,400.00
Total 150,836.75
Comments
User / Role
Status
Crystal Valencia (Admin)
Approved
Apr 17, 2024 08:53
AM CST
June Ellis (Assistant City
Approved
Manager)
Apr 17, 2024 0411
PM CST
Tina Broussard (City Clerk) Approved
Apr 17, 2024 04:25
PM CST
Comments
Approved by City Council on April 16, 2024,
by Resolution No. 24-094.