HomeMy WebLinkAboutRES 24-131RESOLUTION NO. 24-131
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on November 7, 2023, the City Council of the City of Beaumont, Texas
passed Resolution No. 23-338 awarding a contract in the amount of $6,847,514.00 to ALLCO,
LLC, of Beaumont, Texas, for the Street Rehabilitation Citywide -Phase V (REBID) Project;
and,
WHEREAS, previous Change Orders Nos. 1-2, in the amount of $624,325.75 increased
the contract amount to $7,471,839.75; and,
WHEREAS, Change Order No. 3, in the amount of $1,026,822.00, is needed for the
rehabilitation of the roads at the Wastewater Treatment Plant that were originally bid as additive
bid items; thereby increasing the total contract amount to $8,498,661,75;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in all
things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order No. 3
in the amount of $1,026,822.00 for additional work described above; thereby increasing the total
contract amount to $8,498,661.75 for the Street Rehabilitation Citywide -Phase V (REBID)
Project.
The meeting at which this resolution was approved was in all things conducted in strict
compliance with the Texas Open Meetings Act, Texas Government Code, Chapter 551.
2024.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 21st day of May,
OArr
2'44f---
Mayor Roy West -
P
Projectmates
CITYOFBEAU M0NT.PROJECTMATES. COM
Change birder #001.003
PW0823-12 - Street Rehabilitation Citywide Phase V (REBID), 801 Main Street, Beaumont, TX
77701 United States
Monday, May 13, 2024
Change Order Details
Description
Division
Scope of Work
Awarded to
Created By
Create Date
Reason Code
Days Changed
Grand Total:
$100261822.00
Change Order No.3: WWTP
01 - General Requirements
The costs for the rehabilitation of the roads at the Wastewater
Treatment Plant were bid as additive bid items. Additive bid items are
not part of the original scope of work, they are optional and can be
added later if the budget allows. This proposed Change Order will add
these items to the contract at the prices received at the time of bidding.
Brandon Harrison (Allco, LLC), 6854
Julie Hammond (City of Beaumont)
May 08, 2024 02:18 PM CST
Owner Requested
60
Additional Info
Line Item Type Unit price
Group 3.0 Construction
Dates
Created On May 08, 2024
Org, Sub. Completion .tan 06, 2025
Summary
Original Contract Sum
Net Cost by Previous Approved Change Order
Contract Sum Before This Change Order
Contract Sum Changed By This Change Order
New Contract Sum
Substantial Completion Date
Net Time Change By Previous Change Order
Substantial Completion Before This Change
Order
Time Changed By This Change Order
New Substantial Completion Date
All Change Orders of the 01 iginal Contract
Line Items
6,847,514,00
624, 325.75
7,471, 839.75
1,026,822.00
8,498,661.75
Jan 06, 2025
150 day(s)
Jun 05, 2025
60 day(s)
Aug 04, 2025
24.113097833753972609621535640%
Item Account WBS/ Description
# Code Section
i
Contract Items
i
Quantity UoM Unit Total
Price Amount
100
6002
999
PREP ROW (NOT TO
79.00
STA
290.00
22,910.00
EXCEED $300 PER
STATION) WWTP
247
6002
999
FLEX BASE (CMP IN
1,152.00
SY
44.00
50,686.00
PLACE) (TY A GR 2)
(
(6") WWTP
i
275
6013
999
CEMENT TRT (MIX
1,747.00
SY
25.00
43,675.00
EXISTING MATERIAL)
(8„) WWTP
340
6002
999
D-GR HMA TY-D
1,108.00
TON
201.00
222,708.00
PG70-22 (1.5")
(LEVEL -UP) WWTP
340
6005
999
D-GR HMATY-F
1,075.00
TON
206.00
221,450.00
PG70 22 (1.25")
(WEARING SURFACE)
WWTP
351
6002
999
REPAIR OF FLEXIBLE
192.00
SY
138.50
26,592.00
PAVEMENT (8") (ASB
PG 64-22) WWTP
354
6096
999
PLANE ASPH CONC
10,712.00
SY
6.25
66,950.00
PAV (1"TO 3") WWTP
E 361
6002
999
REPAIR CONCRETE
1,152,00
SY
167.25
192,672.00
PAVEMENT (6")
WWTP
Total 1,026,822.00
Item Account WBS/ Description
# Code Section
Quantity UoM Unit Total
Price Amount
500 6002 999 MOBILIZATION (NOT 1.00 LS 44,000.25 44,000.25
502 6001 999
i
i
I
530 6012 999
666 6005
999
Approval (Pending)
User I Role
Brandon Harrison (External -GC)
TO EXCEED 5%)
WWTP
BARRICADES, SIGNS
3.00
MON
1,500.00
4,500.00
& TRAFFIC
HANDLING WWTP
INTERSECTIONS,
226.00
TON
297.00
67,122.00
DRIVEWAYS, AND
TURNOUTS (ACP)
WWTP
REFL PAV MRKTY 1
140,00
LF
8.95
1,253.00
(WHITE) (4") (SOLID)
(100 MIL) (NO
SEALER REQUIRED)
WWTP
CLEANING AND
11,867.00
LF
5.25
62,301.7E
SEALING JOINTS
AND CRACKS WWTP
Total 1,026,822.00
Due Date: May 20, 2024
Status Comments
Approved
May 13, 2024 09:16 AM CST
user / Role
David Tingle (Project Manager)
Amalia "Molly" Villarreal (City Engineer)
Bart Bartkowiak (Director)
Status
Approved
May 13, 2024 09:17 AM CST
Approved
May 13, 2024 09:22 AM CST
Approved
May 13, 202411:30 AM CST
Pending
Comments
i
Projeotmates
CITYOFBEAUMONT.PROJECTMATES.COM
Change Order #001.002
PW0823-12 - Street Rehabilitation Citywide Phase V (REBID), 801 Main Street, Beaumont, TX
77701 United States
Monday, May 13, 2024
Change Order Details Grand Total:
$4731489.00
Description Change Order No. 2
Division
01 - General Requirements
Scope of Work
Angelina Street; Items to remove and replace damaged and collapsed
storm sewer infrastructure discovered at three different intersections
after construction commenced. CC&G point repairs to realign gutteriines
on Angelina Street for conveyance of stormwater runoff. Zavalla Drive:
Items for point repairs to remove and replace broken pin -on curb on
Zavalla Drive. Rusk Street: A change in curb inlet type from a standard
curb inlet to a Type R curb inlet is needed after an existing grate inlet
was removed and roots were discovered from a nearby oak tree that
presented difficulties in relocating the inlet to the back of the curb. Also,
an additional 33-sy for Item 361- Repair Concrete Pavement (6") is
needed for the repairs at the intersection of Rusk & 6th (scoped out in
C.O41) as the paving area was adjusted 4-ft to the east due to a crack
in the existing concrete pavement and also due to actual field
measurements. The contractor is requesting an additional 90 calendar
days for the additional work to be performed on Angelina Street and
Zavalla Drive. No additional calendar days will be required for the
change in inlet type and additional concrete repair for Rusk Street.
Notes
See attachments. '2024.03.05_RDT102-106 repair details' attachment
for reference.
Awarded to
Brandon Harrison (Allco, LLC), 6854
Created By
Julie Hammond (City of Beaumont)
Create Date
Apr 18, 2024 09:09 AM CST
Reason Code
Unforseen Site Conditions
Days Changed
90
Attachments R E S 24-121.pdf
2024.04.23 Angelina CC&G, Pavement & Drainage Rep airs.pdf
2024.03.05 RDT102-106 repair details.pdf
Additional Info
Line Item Type Unit price
Group 3.0 Construction
Dates
Created On Apr 18, 2024
Org, Sub, Completion Jan 06, 2025
Capital Planning
g
Capital Planning Construction - Street Rehabilitation Phase V (REBID)
Capital Project Fiscal 2024
Year
Accounting
Item Id 547
PO Number 442398
Original Contract Sum
Net Cost by Previous Approved Change Order
Contract Sum Before This Change Order
Contract Sum Changed By This Change Order
New Contract Sum
Substantial Completion Date
Net Time Change By Previous Change Order
Substantial Completion Before This Change
Order
Time Changed By This Change Order
New Substantial Completion Date
All Change Orders of the Original Contract
I ina Ita miz
6,847,514.00
150,836,75
6,998,350.75
473,489.00
7,471,839.75
Jan 06, 2025
60 day(s)
Mar 07, 2025
90 day(s)
Jun 05, 2025
9.117563465389044841675387690%
Item
Account
Wes/
Description
Quantity
UoM
Unit
Total
#
Code
Section
Price
Amount
Contract Items
104
6021
100
REMOVING
394.00
LF
8.00
3,152.00
CONCRETE (CURB)
104
6022
100
REMOVING
174.00
LF
19.00
3,306.00
CONCRETE (CURB &
GUTTER)
247
6001
200
FLEX BASE (CMP IN
1,057.00
SY
40.00
42,280.00
PLACE) (TY A GR 2)
Total
473,489.00
Item
Account
WBS/
Description
Quantity
UoM
Unit
Total
#
Code
Section
Price
Amount
' 361
6001
300
REPAIR CONCRETE
1,038.00
SY
180.00
186,840.00
PAVEMENT (6")
400
6002
400
CEMENT STABILIZED
126.00
CY
114.00
14,364.00
BACKFILL (2SK/CY
SAND)
4122
9999
4000
HP STORM PIPE (15'
239.00
LF
189.00
45,171.00
(INCLUDES REMOVAL
OF EXISTING PIPE)
465
6001
400
CURB INLET (COMPL)
5,00
EA
7,778.00
38,890.00
465
6003
400
CURB INLET (TYPE R)
5.00
EA
8,170.00
40,850.00
(COMPL)
465
6002
400
MANHOLE (COMPL)
3.00
EA
10,736.00
32,208.00
i
496
6002
400
REMOVE STR (INLET)
10,00
EA
1,494.00
14,940.00
496
6003
400
REMOVE STR
3.00
EA
2,626.00
7,878.00
(MANHOLE)
502
6001
500
BARRICADES, SIGNS &
3.00
MON
5,000.00
15,000.00
TRAFFIC HANDLING
(NOT TO EXCEED
$5,000 PER MONTH)
529
6002
500
CONC CURB (TY II)
344.00
LF
25.00
8,600.00
529
6008
500
CONC CURB &
174.00
LF
115.00
20,010.00
GUTTER (TY II)
(INCLUDES 6" FLEX
BASE)
Total 473,489.00
Approval (Approved)
User / Role
Status Comments
Brandon Harrison (External-
Approved
GC)
Apr 24, 2024 01:19 j
PM CST
I
David Tingle (Project
Approved
Manager)
Apr 24, 2024 02:02
PM CST
Amalia "Molly" Villarreal
Approved
(City Engineer)
Apr 25, 2024 05:30
PM CST
Bart Bartkowiak (Director)
Approved
Apr 29, 2024 04:32
PM CST
Crystal Valencia (Admin)
Approved Approved by City Council on May 7, 2024, by
May 07, 2024 05:25 Resolution No. 24-121.
PM CST
June Ellis (Assistant City
Approved
Manager)
May 08, 2024 09:30
AM CST
Tina Broussard (City Clerk)
Approved
May 08, 2024 09:50
AM CST
0
Pro)ectmates
CITYMEAUMONT.RROJECTMATES.COM
Change Order #001.001
PWO823-12 - Street Rehabilitation Citywide Phase V (REBID), 801 Main Street, Beaumont, TX
77701 United States
Monday, May 13, 2024
Change Order Details
Grand Total:
$1501836.75
Description CO##001.001: 001
Division 01 - General Requirements
Scope of Work Rusk Street: Items to remove and replace damaged or collapsed parts
of storm sewer infrastructure discovered after construction commenced.
CC&G point repairs to realign gutterlines on Rusk Street for conveyance
of stormwater runoff, The contractor is requesting an additional 60
calendar days for delays and the additional work to be performed on
Rusk Street. Masterson Drive & Potter Drive: Change in scope of work
for Masterson and Potter from mill & ASB repairs to mixing the existing
base with cement slurry. No additional calendar days will be required for
the change in scope of work to be performed on Masterson Drive and
Potter Drive.
3
Awarded to Brandon Harrison (Allco, LLC), 6854
Created By Julie Hammond (City of Beaumont)
Create Date Mar 08, 2024 03:36 PM CST
Reason Code Unforseen Site Conditions
I
Days Changed 60
Attachments 2024.03.12 Rusk CC&G Repairs.pdf
RES 24-094 Street Rehab Phase V.pdf
2024,03,11 Rusk Pavement & Drainagee Repairs.pdf
Additional Info
Line Item Type
Group
Dates
Created On
Org. Sub, Completion
Capital Planning
Capital Planning
Capital Project Fiscal
Year
Accounting
Unit price
3.0 Construction
Mar 08, 2024
Jan 06, 2025
Construction - Street Rehabilitation Phase V (REBID)
2024
524
442398
Original Contract Sum
Net Cost by Previous Approved Change Order
Contract Sum Before This Change Order
Contract Sum Changed By This Change Order
New Contract Sum
i
6,847,514.00
0.00
i
6,847,514.00
I
150,836,75
i
6,998,350.75
Substantial Completion Date
Net Time Change By Previous Change Order
Substantial Completion Before This Change
Order
Time Changed By This Change Order
New Substantial Completion Date
All Change Orders of the Original Contract
Line Items
Jan 06, 2025
0 day(s)
Jan 06, 2025
60 day(s)
Mar 07, 2025
2.2027957883693264446046674400%
Item
Account
WBS/
Description
Quantity
UoM
Unit
Total
#
Code
Section
Price
Amount
Contract Items
104
6021
100
REMOVING
9&00
LF
8.00
784.00
CONCRETE (CURB)
104
6015
100
REMOVING
20.00
SY
80.00
1,600.00
CONCRETE
(SIDEWALKS)
104
6022
100
REMOVING
481.00
LF
19.00
9,139.00
CONCRETE (CURB &
GUTTER)
247
6001
200
FLEX BASE (CMP IN
316.00
SY
40.00
12,640.00
PLACE) (TY A GR 2)
(8n)
275
6012
200
CEMENT TRT (MIX
5,531.00
SY
15.50
85,730.50
EXISTING MATERIAL)
Total 150,836.75
Item
Account
WBS/
Description
Quantity
UoM
Unit
Total
#
Code
Section
Price
Amount
(8" TO 10")
351
6001
300
REPAIR OF FLEXIBLE
-1,235.00
SY
90.00
-111,150.00
PAVEMENT (8" ASS)
i
354
6096
300
PLANE ASPH CONC
-4,939.00
SY
5.25
-25,929,75
PAV (1 " TO 3")
361
6001
300
REPAIR CONCRETE
316.00
SY
180.00
56,8B0,00
PAVEMENT (6")
401
6001
400
FLOWABLE BACKFILL
23.00
CY
408.00
9,384.00
4122
9999
4000
HP STORM PIPE (15")
48.00
LF
189.00
9,072.00
(INCLUDES REMOVAL
OF EXISTING PIPE)
465
6001
400
CURB INLET (COMPL)
5.00
EA
7,778.00
38,890.00
465
6002
400
MANHOLE (COMPL)
1.00
EA
10,736.00
10,736.00
496
6002
400
REMOVE STR (INLET)
5.00
EA
1,494.00
7,470.00
496
6003
400
REMOVE STR
1.00
EA
2,626.00
2,626.00
(MANHOLE)
502
6001
500
BARRICADES, SIGNS &
2.00
MON
5,000.00
10,000.00
TRAFFIC HANDLING
(NOT TO EXCEED
$5,000 PER MONTH)
529
6002
500
CONC CURB (TY II)
98.00
LF
25.00
2,450.00
529
6008
500
CONC CURB &
481.00
LF
115.00
55,315.00
GUTTER (TY II)
Total 150,336.75
Item Account WBSI Description Quantity UoM Unit Total
# Code Section Price Amount
531 6001 500
713 6005 700
(INCLUDES 6" FLEX
BASE)
CONC SIDEWALKS (4") 20.00 SY 230.00 4,600,00
CLEANING AND-6,000,00 LF 4.90-29,400.00
SEALING JOINTS AND
CRACKS
Approval (Approved)
User / Role
Status
Brandon Harrison (External-
Approved
GC)
Mar 12, 2024 03:44
PM CST
David Tingle (Project
Approved
Manager)
Mar 12, 2024 03:56
PM CST
Arnalia "Molly" Villarreal
Approved
(City Engineer)
Mar 12, 2024 04:01
PM CST
Bart Bartkowiak (Director)
Approved
Mar 12, 2024- 05:03
PM CST
Comments
Total 150,836.75
User / Role Status
Comments
Crystal Valencia (Admin) Approved
Apr 17, 2024 08:53
AM CST
June Ellis (Assistant City Approved
Manager) Apr 17, 2024 04:11
PM CST
Tina Broussard (City Clerk) Approved
Apr 17, 2024 04:25
PM CST
Approved by City Council on April 16, 2024,
by Resolution No. 24-094.