HomeMy WebLinkAboutRES 24-066RESOLUTION NO.24-066
BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF BEAUMONT:
WHEREAS, on June 14, 2022, the City Council of the City of Beaumont, Texas passed
Resolution No. 22-152 awarding a contract in the amount of $1,664,700.00 to ALLCO LLC, of
Beaumont, Texas, for the Pine Street SWTP Polymer System and Chemical Storage Tank
Improvements (REBID) Project; and,
WHEREAS, previous Change Order Nos. 1-5, in the amount of $39,514.00, increased the
contract amount to $1,704,214.00; and,
WHEREAS, proposed Change Order No. 6, in the amount of $14,532.00, is required to
add a contairunent area around the new polymer tank system installed for the project; and,
WHEREAS, adding an additional twenty-one (21) calendar days to the contract is
necessary for the competition of the work.
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order No. 6,
in the amount of $14,532.00 for additional work described above, thereby increasing the total
contract amount to $1,718,746.00 for the Pine Street SWTP Polymer System and Chemical
Storage Tank Improvements (REBID) Project; and,
THAT adding an additional twenty-one (21) calendar days to the contract is necessary to
acconu-nodate for the competition of the work.
The meeting at which this resolution was approved was in all things conducted in strict
compliance with the Texas Open Meetings Act, Texas Government Code, Chapter 551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 19t11 day of March,
2024,
RESOLUTION NO.22-152
WHEREAS, the City of Beaumont solicited bids for furnishing all labor, materials,
and equipment for the Pine Street SWTP Polymer System and Chemical Storage Tank
Improvements (REBID) Project; and,
WHEREAS, Allco, LLC, of Beaumont, Texas, submitted a qualified bid in the
amount of $1.664,700.00; and,
WHEREAS, the City Council is of the opinion that the bid submitted by Allco,
LLC, of Beaumont, Texas, is the, lowest qualified bidder providing services at the best
value to the City and should be accepted;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Council hereby approves the award of a contract to Allco, t,.t.C, of
Beaumont, Texas, in the amount of $1,664,700,00 for the Pine Street SWTP Polymer
System and Chemical Storage Tank Improvements (REBID) Project; and,
BE IT FURTHER RESOLVED THAT the Interim City Manager be and he Is
hereby authorized to execute a contract with Allco, LLC, of Beaumont, Texas, for the
purposes described herein.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Art, Texas Government Code, Chapter
651,
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 14th day of
Jane, 2022.
- Mayor Rabbi Mouton R
Contract - 002.006
29-Feb-2024 08:40 AM CST
PINE STREET SWTP POLYMER SYSTEM AND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
1360 Langham Rd Beaumont, TX 77707
Project Number. WJ0422-19
002.006: CO#002.006: Polymer Area Changes
Grand Total: $14,552.00
For 002 PINE STREET SWTP POLYMER SYSTEM AND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
Division 99
Line Item unit price
Type
Group 3.0 Construction
Scope of Change Order No, 6 will add a containment area around the new polymer tank system installed for this project. There was a conflict
Work between the contract and the drawings for the polymer tank. One called for a double walled tank, and the other called for a specific type
of valve on the tank, which cannot be double walled. The bought tank was the tank without a double wall, and to prevent possible spills, a
concrete containment area was proposed.
Notes
Awarded To Allco, LLC
Brandon Harrison
6854
Reason Owner Requested
Code
Days 21
Changed
Attachments 20240216144232963.pdf
Change Order Summary
Original Contract Sum
Net Cost by Previous Approved COs
Contract Sum Before This CO
Contract Sum Changed By This CO
New Contract Sum
All Change Orders make up 3.26% of the Original Contract
Accounting and Status
1,664,700.00 Substantial Completion Date
39,514.00i Net Time Change By Previous COs
1,704,214.00 Substantial Completion before This CO
14,632.00 Time Changed By This CO
i
1,718,746.00 New Substantial Completion gate
1
52 days
21 days
Accounting Status
Item Id
608
PO Number
441208 FNMA Number
Accounting Project Code
WUP004 Custom Accounting Field 04
Custom Accounting Field 05
i
i Custom Accounting Field 06
1
Custom Accounting Field 07
Custom Accounting Field 08
Line Items
Item # Account Code WBSI Section Description
Change order Items
002 000000 PolymerArea Changes
Total
Approval 'Pending
Quantity UoM Unit Price Total Amount
1.00 LS 14,532.00 14,532.00
14,532.00
Grand Total: 14,532.00
Due: 6-Mar-2024
Name or (tole
1 External -GC
2 Project Manager
3 City Engineer
4 Director
5 Admin
6 Assistant City Manager
7 City Clerk
Status
Approved
Brandon Harrison
21-1=eb-2024 02:54 PM CST
Approved
Makenzie Watts
22-I~eb-2024 12:54 PM CST
Approved
Amalia "Molly" Villarreal
27-Feb-2024 05:55 PM CST
Approved
Bart Bartkowiak
28-Feb-2024 09:22 AM CST
Pending
Actions
Waiting for previous approvals.
Waiting for previous approvals.
t
Created by: Brandon Harrison on 16-Feb-2024 Last Modified by: Bart Bartkowlak on 28-Feb-2024
Contract # 002,005
06-Nov-2023 01:62 PM CST
PINE STREETSWTP POLYMER SYSTEM AND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
1360 Langham Rd Beaumont, TX 77707
Project Number: WU0422-19
002.005: C0##002.005: Caustic Removal & Disposal
Grand Total: $7,968.00
For 002 PINE STREETSWTP POLYMER SYSTEMAND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
Division 99
Line Item Unitprice
Type
Group 3.0 Construction
Scope of The original design consisted of transferring all the existing caustio from the old tanks to the now tanks, During construction, Water
Work Production staff discovered that sine existing caustic contained excessive debris which had settled into the bottom of the tank leafing to
the decision to dispose of the existing caustic rather than risk potential plant treatment upsets from disturbing the debris during the
transfer. The existing caustic will be used up to the lowestpossible tevai, and the remainderwill be properly disposed of through a
oartified hazardous waste haular. This change order covers the disposal of the remaining oaustio and debris..
Notes
Awarded: To Allco, LLC
Brandon Harrison
6854
Reason Owner Requested
Code
Days 7
Changed
Attachments
CO -Caustic Removal & Disposal.pdf
Change Order Summary
Original Contract Sum 1,664,700.00 Substantial Completion Date
Net Coal by previous Approved Cos 31,646.00 Net Time Changa By previous Cos 45 days
Contract Sum Before This CO 1,M,246,00 Substantial Completion before This CO
Contract Sum Changed By This CO 7,958.00 Time Changed By This CO 7 days
New Contract Sum 1,704,214.00.New Substantial Completion Dale
All Change Orders make up 2.37% of the Original Contract
Accounting and Status
Accounting Status
Item Id
472
PO Number
441208 FEMANumber
Accounting project Code
WUP004 CustomAccounling Field 04
Custom Accounting Field 05
Custom Accounting Field 06
Custom Accounting Field 07
CustomAccounting Field Of)
Line Iteins
Item 11 Account Code W1391 80clion Description
Change Order Items
001 000000 Causlio Removal i& pisposal
Total
Approval Approvod
Name or Role
$talus
1
Externai-GC
Approved
Brandon Harrison
03-Nov-202311:21 AM CST
2
PrgeotManager
Approved
Mekenzie Watts
03-Nov202311:28 AM CST
3
City Engineer
Approved
Amalia "Molly" Villarreal
03-Nov-2023 03:42 PM CST
4
Director
Approved
Hart Bartkowi ek
08-Nov-2023 08:44 AM CST
ti
Admin
Approved
Dara Woodruff
06-Nov-2023 08:50 AM CST
6
Assistant City Manager
Approved
June Ellis
06-Nov-202301:35 PM CST
7
City Cletk
Approved
Tina Broussard
06-Nov 2023 01:41 PM CST
Quantity UOM U nit Price Total Amount
Created by: Brandon Harrison on 26-Oot-2023 LastModfled by: Tina Broussard on 06-Nov-2023
1.00 LS 7,968.00 7.968.00
7,960,00
Grand Total: 7,960.00
Due: 13-Nov-2023
Actions
Contract - 002.004
2"ep-2023 00-.28AM CST
PINE STREET SWTP POLYMER SYSTEM AND CHEMICAL STORAGE, TANK IMPROVEMENTS (REBID)
1350 Langhnm Rd Beaumont, TX 77707
Project Number. WU0422-19
002.004, 00#002,004: Chem Feed Area Repairs andAdditional
Programming/Input Modules
Grant! Total: $7,467.00
For 002 PINE STREETSWTP POLYMER SYSTEM AND CHEMIGALSTORAGE TANK IMPROVEMENTS (REBID)
Division 99
Line Item Unit price
Type
Group 3.0 Consvuctiion
Scope of 1) TCEQ has requested that the City Gil in a cavity found In ilia concrete next to the sump pump catch basin in the older alum U
Work 2) The main PLC (prog€ammoble logic ocntroller) panel in Iho chemical building didn't have enough space for the new analog w
the new tanks. Additional Installation and programming needed for the two (2) new analog carats for the PLC.
Notes
Awarded To Allco, LLG
Brandon H ardson
Q664
Reason Unforseen Site Conditicna
Code
Days 0
Changed
Allachments C04--Chem Feed Area Repairs.pdf
Change Order 8umInarjl
Original Contract Sum
1,664,700.00 Substantial Completion Date
Net Cost by Previous Approved
2079.00 Net Time Change By Previous 37 days
COS
GO$
Gonfro ctSum Hof ere This CO
1,088,779.00 Substantial Completion before
This CO
Contract sum Changed By This
7.467.00 Time Changed By This CO 8days
CO
New Contract Sum
1,894,240,00 New Substantial Completion
D ate
All Change Orders make up 1.89% of he Original Contract
Accounting and Status
Accounting Stalua
Itom ld 453
PO Number 431634 FFMA plumber
Accounting Project Code WUP004 Custom Accounting Field 04
Custom Accounting Field 05 Custom Accounting Field 06
Custom Accounting Fidd 07 Custom Accounting Field 08
Line Items
Account WBSI
Item S Code Section Description
Change 4rdar item s
001 00000 Repairs
002 250000 Integrated Automation
Total
ApprOVal Approved
Unit Total
Quantity UoM Price Amount
Name or Rafe
Status
1
Extemal-GC
Approved
Brandon Harrison
11-Sep-202303:18 pM CST
2
Pro)eclManager
Approved
Maken2ie Watts
11-5 ep-2023 03:1 Q PM CST
3
City Engineer
Approved
Amalia °Molly" Villarreal
20Sep-2023 12:14PM CST
4
Director
Approved
Bar; Bartko4Aak
20-Sep-2023 03:07 PM CST
5
Admin
Approved
Crystal Garza
21Sep-2023 O8:45AM CST
6
A%Ielant City Manager
Approved
June Ellis
21Sep-2023 12:65 PM CST
7
Cily Clerk
Approved
Tina Broussard
21Sep-2023 01:42 PM CST
1.00 LS 2.000.00 2,900.00
1.00 LS 4.607.00 4,667,00
Grand Total: 7,467.00
Due: 28Sep.2023
Actions
Croated by. Brandon Harrison on 31-Aug-2023 Last Modified by: Tina Broussard on 21-Sep-2023
Contract 002.003
03•Aug-2023 02:20 PM CST
PINE STREETSWTP POLYMER SYSTEM AND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
1360 Langham Rd Beaumont, TX 71707
Project Number: WU0422-19
002.003: COtf002.003., Furnish/Install Polymer Scale and Tank Mixer, Remove Flowmoter
Grand Total: $10,217.00
For 002 PINE STREETSWTP POLYMER SYSTEM AND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
Division 99
Line Item Urtitprioe
TYpe
Group 3.0 Construction
Scope of Proposed Change Order Na 3Is requested due to changes to the polymer system lhathave been made during construction. A new
Work welcgrtscate will be added to the project to replace tl3e existing one thatw€ll be salvaged. Tice new scalewili be used to measure the
polymer dosage in replacement of the f€owmeter. A new lank mixer will be added to the project, as the existing tank mixer Ihatwas
planned to be used was discovered to be too short for adequate Mxing of the polymer. The liowmeter and Its installation will be removed
from the project, as there Is no lowmater that meats the required standards and project Criteria.
Notes
Awarded To Allco, LLC
Brandon Harrison
0854
Reason Drawing and Spec Clarification
Code
Days 30
Changed
Attachments RES 23-205 003 Pine SWTP Polymer Rebid. pdf
00 3 Combined.pdf
20230720 i 5 060t3965.pdf
004-•Mixer t? Day Tank(1),pcif
Change Order Summary
Original Contract Sum
1,064,700,00 Substantial Completion Date
Net Cost by Previous Approved Cos
13,862.00 Not Time Change By Previous Cos 7 days
Contract Sum Before This CO
1,075,562.00 Substantial Completion before This CO
Contract Sum Changed By This Co
10,217.00 Time Changed By This CO 30 days
New Contract Sum
1,6W,779.00 Now Substan lial Completion Dale
All Change Orders make up 1.45% of the otig€nal Contract
Accounting and Status
Accounting Status
Item Id
PO Number
Accounling Project Code
Custom Accounting Field 05
Custom Accounting Field 07
Line Items
421
431634 FEMA Number
WUP004 Custom Accounting Field 04
Custom Accounting Field 00
Custom Accounting Field 00
Item 11 Account Cade
WBs! section
Description
Change Order Items
003
463323
Liquid Chemlcal Weighing Equipment
004
463333
Polymer Blending and Feed Equipment
005
00000
Flow Meter
Total
Approval Approved
Name or Rol e
1
Extenial-GC
2
ProjeotManager
3
City Engineer
4
Direotor
5
Admin
6
Assistant City Manager
Status
Approved
Brandon Harrison
20-Jui-2023 03:05 PM CST
Approved
Makenrie Watts
20-Jul-2023 03:30 PM CST
Approved
Amalla 'Molly' Villarreal
24-Jul-2023 01:51 PM CST
Approved
Bart Bartkowiak
24-Jul-2023 01:54 PM CST
Approved
Dara Woodruff
02-Aug•2023 07:34 AM CST
Approved
June Ellis
02-Aug-2023 04:07 PM CST
Quantity UoM Unit Price Total Amount
1,00 LS 6,740.00 8,740.00
1.00 LS 8,677,00 8,677,00
1.00 LS-7,200,00-7,200,00
t 0,217.00
Grand Total: 10,217.00
Due: 9-Aug-2023
Actions
Name or Role Status Actions
7 CltyClerk
Approved
Tina Broussard
02-Aug•2023 04:10 PM CST
Created by: Brandon Harrison on 11-Jul-2023 LastModifsed by: 'Tina Broussard on 02-Aug•2023
Contract # 002.002
i r-JUJ-r. Ura u I w ruvl va i
PINE STREET8WTP POLYMER SYSTEMAND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
1350 Langham RdBeaumonl, TX 77707
ProjectNumber WU0422-19
002,002: CO#002,002: Instrument Blind Flange Mounting Assembly
Grand 'Total: $7,337.00
For 002 PINE STREET SWTP POLYMER SYSTEM AND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
Division 99
Line Isom Unitprioe
Type
Group 3.0 Construction
Scope of Change Order No. 2 will add ion (10) additional Items not originally a part of the project, to be able to mount the called for new
Work Instrumentation to replace die old instrumentation. This change order includes adding a blind flange assembly and the necessary labor
for installation of this new assembly at ten (10) chemical storage tanks at the Water Treatment Plant This Is necessary because the
current Instrumentation being replaced Is welded to He mounting equipment, and Bald mounting equipmen twas planned to be used for
tine new instrumentation. Additional mounting equipment mustbe Introduced to mount the new Instrumentation.
Notes
Awarded To Allco, LLC
Brandon Harrison
6854
Reason Drawing and Spec Clarification
Code
Days 3
Changed
Altachmente COR-Instrument MountingAssemblypdf
Change Order Summary
Original Contract Sure 1,664,700,00 substantial Completion Dale
Net Cost by Previous Approved COs 6,525.00 Net Time Change By Previous COs 4 days
Contract sum Before This Co 1,671,226.00 Substantial Completion before This CO
Contract Sum Changed By This CO 7,337.00 Time Changed By This CO 3 days
Now Contract Sum 1,678,562.00 New Substantial Completion Date
All Change Orders make up 0,03% of the Original Contraot
Accounting and Status
Accounting Status
Clem Id 413
PO Number 431634 FEMA Number
Accounting Project Code WUP004 Custom Accounting Field 04
Custom Accounting Hold 05 Custom Accounting Field 04
Custom Accounting Field 07 Custom Accounting Field 09
Line Items
Item #f Account Code WBS! Section Description
Change Order Items
001 4005t 3.13 Steel Prooess Piping
Total
..........__.�..�__.w.�...__._..._..._w_.._._..�____.._._-�.-�....�.ti._.�._�._._.u.._..
AppCOvH1 Approved
Name or Role
Status
1
External -GC
Approved
Brandon Harrison
12-Jun-2023 10:00AM CST
2
ProjeotMenager
Approved
Makenzie Waifs
12-Jun-2023 tt:25AM CST
3
City Engineer
Approved
Amalia "Molly" Villarreal
12-Jun-2023 03:15 PM CST
4
Director
Approved
Bart Bartkowiak
13-Jun-2023 08:48 AM CST
5
Admin
Approved
Dare Woodruff
i 3-Jun-2023 09:44 AM CST
6
Assistant Oily Manager
Approved
June Ellis
13-Jun-2023 05:39 PM CST
7
City Clerk
Approved
Tina Broussard
14Jun-2023 09:16AM CST
Quantity UoM Unit Price TolalAmounI
1.00 LS 7.337.00 7,337.00
7,337.00
Grand Total: 7,337.00
Created by: Brandon Harrison on 08Jun-2023 Last Modified by TinaBroussarrJ on 14-Jun-2023
Due: 21-Jun-2023
Actions
4121123, 9:42 AM Ptcjechnates Contract
Contract # 002,001
21-Apr-2023 09:42 AM CST
FINE. STREETSWTP POLYMER SYSTEM AND CHEMICAL STORAGE TANK IMPROVEMENTS (REBID)
1350 Langham Rd Beaumont, Tx 77707
Project Number: WU0422-10
002,001: CO#002.001: Bollards
Grand Total: $6,626.00
For 002 PINE STREET SWTP POLYMER SYSTEM AND CHEMICAL STORAGE -TANK IMPROVEMENTS (REBID:)
Division 99
Lineltem Unitprice
Type
Group 3.0 Construction
Scope of Change Order No, 1 will add two (2) addlftonal items not originally a part of the project, to ensure safety of the new electrical work
Work installed for this project Two (2) bollards (a short post meant to divert traffic from a certain area) to be placed on eilher side of the now
electrical box on the containmentwall for the chemical tanks at the sanitary water treatment plant Tlits box juts Into the driveway next to
the containment area, more so Uian anything else the drivers are used to driving near In this area, and that's putting the box in possible
harms way,
Notes
Awarded To Allco, LLC
Brandon Harrison
6864
Beason Owner Requested
Code
Days 4
Changed
Attachments 001 Botiards,pdf
COI-Boftards-Comments.pdf
Change Order Summary
Original Contract Sum 1,664,700.00 Substantial Completion bate
Net Cost by Previous Approved Cos 0.00 Net Time Change By Previous Cos 0 days
Contract Sum Before This CO 1,664,700,00 Substantial Completion before This GO
Conlract Sum Changed By This CO 6,625.00 Time Changed By This Co 4 days
New Contract Sum 1,671,225.00 New Substantial Completion Date
All Change Orders make up 0.39% of the Original Contract
Accounting and Status
hops:dcityofbeaumontprojectmate&ccmlPr(jsctmetes/CcoVeotMgmVCcntraclPrititerFrfendly.aspx?eno=28878D01099E 875801;61C4CO707E682578... 1/2
4121 /23. 9:42 AM
Accounting Status
Ilem ld 360
PO Number 431534
Accounting Project Code WUP004
Custom Accounting Field 05
Goatom Accounting Field 07
Line Items
Item it Accounl Cade WB915ection Description
Change Order Items
001 030000 Bollards
----........... -.....---...-.---- --- ------ --------
Total
Approval Approved
Projachnates Contract
FEMA Number
Custom Accounting Field 04
CustomAccounling Field 06
Custom Accounling Field 09
Quantity Uom
1.00 LS
Name or Role
Status
1 External -GC
Approved
Brandon Harrison
19-Apr-2023 09:43 AM CST
2 ProjectManager
Approved
Makenz€e Watts
19-Apr-2023 09:43 AM CST
3 City Engineer
Approved
Amai€a'Volly' Viliarreal
19-Apr-202305:58 PM CST
4 Director
Approved
BartBartkotalak
20•Apr-2023 08:49 AM CST
5 Admin
Approved
Dara Woodruff
20-Apr-202308:53AM CST
6 Assistant City Manager
Approved
June Ellis
20-Apr 2023 02:48 PM CST
7 City Clerk
Approved
Dina Broussard
20-Apr-2023 02:59 PM CST
Unit Price Total Amount
6,526,00 6,525.00
8,626.00
Grand Total: 0,626.00
Due: 27-Apr-2023
Actions
Created by: Brandon Harrison on 30-Mar-2023 Last Modified by: Tina Broussard on 20-Apr-2023
https:l/oltyoibesumontproj ectmeto& ccrn/Pro(ich»ates/CcnUwtMgmUC cntractPrinterFdendty. espx?ono=28878D01099DB 7580F61C4C8707E 6$2678... 212