HomeMy WebLinkAboutRES 23-246RESOLUTION NO. 23-246
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on June 14, 2022, the City Council of the City of Beaumont, Texas
passed Resolution No. 22-151 awarding a contract in the amount of $589,861.80 to To-
Mex Construction, LLC, of Houston, Texas for Street Rehab Sewer Line Pipe Bursting
Project; and,
and,
WHEREAS, Change Order Nos. 1-4, in the amount of $33,865.00 are attached;
WHEREAS, Change Order No. 5, in the amount of ($60,091.40), is requested to
adjust the estimated quantities in the contract to reflect the actual quantities used and
the addition of 37 calendar days to reflect the actual time used in the completion of the
project, thereby decreasing the total contract amount to $563,635.40; and,
WHEREAS, the project has been inspected by the Water Utilities Division and
found to be complete in accordance with the provisions and terms set forth in the
contract;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are
hereby, in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 5, in the amount of ($60,091.40), for work described above, thereby
decreasing the total contract amount to $563,635.40 for Street Rehab Sewer Line Pipe
Bursting Project; and,
BE IT FURTHER RESOLVED THAT the City Manager is hereby authorized to
make final payment in the amount of $28,181.77 to To-Mex Construction, LLC, of
Houston, Texas.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 12th day of
September, 2023.
- Mayor Roy West -
RESOLUTION NO.23-132
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on June 14, 2022, the City Council of the City of Beaumont, Texas
passed Resolution No. 22-161 awarding a contract In the amount of $689,861.80 to To-
Mex Construction, LLC, of Houston, Texas, for the Street Rehab Sewer Line ripe
Bursting Project; and,
WHEREAS, Change Orders Nos. 1-3, in the amount of $12,600.00, increased
the total contract price to $602,461.80; and,
WHEREAS, Change Order No. 4, in the amount of $21,266,00, Is required for the
addition of quantities on four (4) bid fine items due to unanticipated field conditions
found during construction;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are
hereby, in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 4, in the amount of $21,265,00 for additional work described above, thereby
increasing the total contract amount to $623,726.80 for the Street Rehab Sewer Line
Pipe Bursting Project; and,
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 9th day of
May, 2023.
r Mayor Robin Mouton -
t
Contract # 001.005
22-Aug-2023 03:17 PM CST
Street Rehab Sewer Line Pipe Bursting Project
1360 Langham Beaumont, Texas 77706
Project Number; WU0322-16
001.005: 001.005: Change Order No. 5
Grand Total: $-60,091.40
For 001 Street Rehab Sewer Line Pipe Bursting Project
Division 33
Lille Item unit price
Type
Group 4.0 EquipmenMoseout
Scope of Change Order No 5 is being requested to account for quantities not used in completing the project. The project has been completed and
Work inspected by City staff, Items removed were either over -estimated or found during construction to be in satisfactory condition. Thirty -
Seven (37) additional calendar days are requested to account for supply chain Issues with fiberglass manholes and the crew being pulled
to assist on the Calder Place Emergency Pipe Bursting Project.
Notes
Awarded To To-Mex Construction Li.0
Maribel Torres
Reason Quantity Adjustment
Code
Days 37
Changed
Attachments
Change Order Summary
Original Contract Suns 589,861.80
Substantial Completlon pate
Net Cost by Previous Approved COs 33,865.00
Net Time Change By Previous COs 12 days
Contract Sum Before This CO 623,726.80
Substantial Completion before This CO
Contract Sum Changed By This CO-60,091.40
Time Changed By This CO 37 days
New Contract Sum 563,635.40
New Substantial Completion Date
All Change Orders make up -4.451/o of the Original Contract
Accounting and Status
Accounting Status
Item id 445
PO Number
Accounting Project Code
Custom Accounting Field 05
Custom Accounting Field 07
Line Items
430950 1 FEMA Number
i
WWC0i9 j Custom Accounting Field 04
Custom Accounting Field 06
Custom Accounting Field 08
Item
Account WBS1
Unit
Total
it
Code Section
Description
Quantity
UoM
Price
Amount
3.0 Construction
002
GC Contract 2
Full Depth Repair of Concrete Pavement (10")
-128.80
SY
80.00
-10,304.00
004
GC Contract 4
Trench Excavation Protection
-298.00
L.F.
4.00
-1,192.00
006
GC Contract 6
Remove and Replace or Install New Sid. Fiberglass Manhole, Up to 8'
-1.00
EACH
5,345.00
-5,345.00
Depth with All Joints & Connecil
008
GC Contract 8
Extra Depth for New or Replacement Sid. Manhole, Over 8 Feet
-100.00
V.F.
100.00
-10,000.00
Depth (Fiberglass)
009
GC Contract 9
Reconnect Service Connection by Excavation including Cleanouts to
-3,00
EACH
715.00
-2,145.00
Liner Complete, All Sizes and Dep
015
GC Contract 15
Pipe Bursting 12" Sewer to 12.75" OD HDPE
-580.00
L.F.
53.63
-31,105.40
Total
-60,091.40
Approval Pending
Grand Total:-60,091.40
Due; 28-Aug-2023
Name or Role
1 External -GC
2 Project Manager
3 City Engineer
4 Director
Status
Approved
Maribel Torres
21-Aug-2023 02:10 PM CST
Approved
Kevin Young
21-Aug-2023 02:19 PM CST
Approved
Amapa "Molly" Villarreal
21-Aug-2023 02:24 PM CST
Approved
Bart Bartkow€ak
21-Aug-2023 02:33 PM CST
Actions
5 Admin Pending
8 Assistant City Manager Waiting for previous approvals.
7 City Clerk Waiting for previous approvals.
Contract - 001.004
11-May-2023 03:00 AM CST
001.004: Change Order No. 4
Street Rehab Sewer Line Pipe Bursting Project
1350 Langharn Beaumont, Texas 77706
Project Number: M0322-16
Grand Total: $21,265.00
For 001 Street Rehab Sewer Line Pipe Bursting Project
Division 33
Line Item Unit price
Type
Group 3.0 Construction
Scope of The Contractor will perform Pipe Bursting tasks as noted and In accordance with the details provided in the project contract documents or
Work as directed by the Engineer.
Notes Change Order No. 4 Is requested to add additional quantities to four (4) bid items to reflect quantities used in the field.
Awarded To To-Mex Construction LLC
Maribel Torres
Reason Quantity Adjustment
Code
Days 0
i Changed
Attachments Pending Pay Item Street Rehab Project.xisx
RES 23-132 St. Rehab Sewer Line PB C_04,pdf
i
i
Change Order Summary
Original Contract Sum
Net Cost by Previous Approved Cos
Contract Sum Before This CO
Contract Sum Changed By This CO
New Contract Sum
All Change Orders make up 5.74%n of the Original Contract
Accounting and Status
Accounting Status
589,861.80 Substantial Completion Date
12,600.00 Net Time Change By Previous Cos 12 days
602,461.80 Substantial Completion before This CO
21,265.00 Time Changed By This CO 0 days
623,726.80 New Substantial Completion Date
Item Id 389
PO Number 430950
FEMA Number
Accounting Project Code WWC019
Custom Accounting Field 04
Custom Accounting Field 05
Custom Accounting Feld 06
Custom Accounting Field 07
! Custom Accounting Field 08
I
Line Items
Item
Account WDSI
Untl
Total
#
Code Section
Description
quantity UoM
Price
Amount
3.0 Construction
003
GC Contract 3
Flexible Pavement Structure Repatr (4')
130.00 SY
65.00
8,450,00
i
006
GC Contract 6
Remove and Replace or Install New Sid. Fiberglass Manhole, Up to 8'
2.00 EACH
5,345,00
10,690,00
Depth with All Joints & Connect!
011
GC Contract 11
Obstruction Removal by Fxcavatton, All Sizes, All Depths, With Project
2.00 EACH
425.00
850.00
Manager's Approval
3 014
GC Contract 14
Pipe Bursting 6" Sewer to 8.625" OD HDPE
30.00 L.F.
42.50
1,275.00
Total
21,265.00
Grand 'total: 21,266.00
Approval Approved
Due: 17-May-2023
Name or Role
Status Actions
1 External -GC
Approved
Maribel Torres
25-Apr-2023 02:30 PM CST
2 Project Manager
Approved
Kevin Young
25-Apr-2023 03:31 PM CST
3 City Engineer
Approved
Arnalia "Molly" Villarreal
28-Apr-2023 03:42 PM CST
4 Director
Approved
Bart Rartkowiak
28-Apr-2023 03:58 PM CST
5 Admin
Approved
Dara Woodruff
10-May-2023 08:52 AM CST
6 Assistant City Manager
Approved
June Ellis
10-May-2023 10:50 AM CST
Name or Role Status
7 City Clerk Approved
Tina Broussard
10-May-2023 11:02 AM CST
Created by: Kevin Young on 24-Apr-2023 Last Modified by: Tina Broussard on 10-May-2023
Aattons
Contract - 001,003
06-Dec-2022 02:23 PM CST
001,003: Change Order No, 3
Street Rehab Sewer Line Pipe Bursting Project
1360 Langham Beaumont, Taxes 71706
Project Number: WU0322-16
Grand Total: $4,600.00
For 001 Street Rehab Sewer Line Pipe Bursting Project
Division 33
Line Item Uall price
Type
Group 3.0 Construction
Scope of To add an addition bid Item for point repair and cast Iron pipe removal, sealing of manhole Inside and outside of storm drain, and
Work replacement of the 6 inch pipe with 8,026 Inch HOPE from MH-234 to 3 ft. past conglct box.
Notes
Awarded To To -Max Construction LLC
Maribel Torres
Reason Unforsean Site Condltlons
Code
Days 6
Changed
Attachments EXTERNAL City of Beaumont Street Rehab Point Repair Quole,pdf
Change Order Summary
Original Contract Sum 58g,861.80
Substantial Completion Date
Net Cost by Previous Approved Cos 8,100.00
Not Time Change By Previous COO 6 days
Contract Sum Before This CO 897,981.80E
Substantial Completion before This CO
Contract Sum Changed By This CO 4,600.00
Time Changed By This CO 6 days
New Contract Sum 602,461.80
New Substantial Completion Date
All Change Orders make up 2.14% of the Original Contract
' Accounting and Status
Accounting Status
Item Id 325
PO Number
Accounting Project Code
Custom Accounting Field 05
Custom Accounting Field 07
Line Items
430950 FEMA Number
W VC019 Custom Accounting Piold 04
Custom Accountin u Flold 00
Custom Accounting Field 00
item Account W BSI Unit Total
# Code Section Description quantity UoM Price Amount
3.0 Construction
017 GC Conlracl 17 Point Repair, Cast Iron Pipe removal & replacement wish 8,025" HDPE; 1.00 LS 4,500.00 4,600.00
pipe, sealing of conflict box
Total
Approval Approved
Name or Role
Status
1
External -GC
Approved
Modbel Torres
05-Dec-2022 02:07 PM CST
2
ProjeclManage€
Approved
John Plppins
06-Dec-2022 0&50 AM CST
3
City Engineer
Approved
Amapa "Molly" Villarreal
06-Dec-2022 0916 AM CST
4
Director
Approved
Bart Barikowiak
08-Dec-2022 09:42 AM CST
5
Admin
Approved
Dora Woodruff
00-Dec-2022 09 58 AM CST
APPROVED BY; ATA STED BY;
Kcnncth R. Williams Da
City Mal1ngcl.
u�
4.600.00
Grand Total: 4,600.00
Due: 13-Dec-2022
Actions
Date
Contract # 001.002
i 10-Oct-2022 08:44 AM CST
Street Rehab Sewer Una Pipe Bursting Project
1350 Langham Beaumont, Texas 77706
Project Number: W1.1`0322-16
001.002: Change Order No, 2
i
Grand Total: $8,100.00
For WU0322-16 To-Mex Con Street Rehab Sewer Line Pips Hursiln , Project
Division 33
Line hem Unit price
Type
Group 3.0 Construction
scope of To add an additional bid Item for the contractor to perform two (2) needed point repahs to connect to the existing 12" PVC sanllary sewer
Work line that crosses through a 72" Storm drain between MH791 and MH241 on page 4 of the plan sheets, Six (0) additional calendar days
wi➢ he added to the contract for the completion of tite Work.
Notes
Awarded To To -Max Construction, Li C
Madbsi Torres
Reason Unforseen Slue Cnndikons
Code
Days 6
Changed
Atlachmanis Street Rehab Project MH791.241Ouote.pdf
Change Order Summary
Original Contract Sum
589,861.80 Substantial Completion Date
Not Cost by Previous Approved
0.00 Net Time Change By Previous 0 days
Cos
Xos
Contract Sum Before This CO
689,851.00 I Substantial Completion before
This CO
I
Contract Sum Changed By This
6,100.€70111me Changed By This Cq 0 days
CO
Now Contract Sum
697,901.60 New Substantial Completion
Date
t
Alt change Orders make up 1.37%of the Original Contract
Accounting and Status
Accounting Status
I
Item Id
302
I
PO Number
FEMA Number
Accounting Project Code
WWC018 Custom Accounting Field 04
Custom Accounting Field 06
Custom Accounting Flnld 06
Custom Accounting Field 07
' Custom Accounting Field 08
Line Items
Account WE15! Unit Total
llem f! Code $action Doscriptlon Quantity UoM Pilco Amount
3.0 con5tructlon
0t0 GC 10 PolnlRepair 2.00 EACH 4,050.00 5,100.00
Contlact
Total 8,100,00
Grand Total: 6,100,00
Approval Approved
D114:17.Oct-2022
Nam orRole
Status Actions
1
External -CC
Approval
Mailbol Torras
05.Ort-202205:07 PM CST
2
Prefect Manager
Approvod
John Plppins
07.Oct�202201:20 PM CST
3
City Engineer
Approved
Amalin Wolly" Villarreal
07.Oct•2022 05:27 PM CST
4
Olre0or
Approved
Dart Derlkowlak
to-❑cl-2022 01JAZ AM CST
6
Admin
Approved
Dpru Woodruff
10-00-2022 00:45 AM CST
Crealod by, Kevin Young nn 05-0c1•2022 i ast Modified by: Data Woodrurf en 10-Od-2022
APPROVED BY.
Kenneth R. Williams Date
City Manager
ATTESTED BY:
99
Tian Bruussarzi Date
City Clerk
CITY CF 09AUMONT
Dtty
A, tau
Prelutl
abatlMldb64,MfUniNplDmOnOPMtti
CaVntyl
1 Noon
DIAAck
o"UtroM
ConWtlWrR*n
WOW. WWII1.11
Nmsi
gy11 'I noAs
Canbaetan
TaritACalabwtl*ALLO
0.01 110.1
1
i11:Ii0rSS1'd1:�1*S:!1:]A:l?31�111.�iI:;Ei.7LY7:114i�?Ili?d![r)lF7.f;t;lllt: (7'ISff)_
1'i,!S:�Li[ I�11Y1'id1LT!1l:1 [3 f:RiiLL;[IiT1Id�
OWINALCOfITMOrAMMIrt _{ 65/./61.IP
YET FROM PRVVMl C1 WAtOROMC; a
TOrALA11OU?frOFTWISCI MEORDM' t
PRRo4R OP Tt#$ CIw4E OROEfk omb
TOTAL P[Rmrr CI Wd0E0R0ER To DNTE, 0;001i
NuWO0UMQTAMoUi;T3 .1 610./E610_
o01rrRAOT T1AlE '
oalauuuoolrrRAar TD11a 110 uNndlrann
AaGF101Lt1QOfiTMOftFUEPfHPREV10u5aIWiaE0R0EAs; � a r�ltnda dr t
ADMi0NALWifRACTTIME PLR TOW CiWiOEOROFR: ul f
Rim3tooaNrRAW TIME: utn at
jf1f R jOkOPCHANGE,
T4*f0ottl*WAskw and gn]l&W the y.dtfanhlas &Wp%i rd cwftdBmk 0pJ.1W1nWt Mr4pOW41Ippmiab M taR ft-O IOI InhuW"
"Otm&m Im Ee omd, rd M Imt fpNd It pW*m Dk o dnnakfnfNVnw4vdLjtryelk* 41 Wildy Aamwt CMryt OrAf vid kNp,nMa Ciwgt 01dtn,
AbpWm" d witiwHK aa7tllkw tAttpnMwAbeltratOafnr trdC'+etrW xna Da Ctwa10fdlf fljlNte;t in aVdtnkk, mmliv awlid Lpm tttpdmtnllaNt oa�►kR
rd rulCoroncta H1 tW O M17dd iik k tl.+tran W/+:utaa0ldtr 1011 aliptsptA/ Ntldt0.•
lSCCE.PTm ISYf
7/20122
TOT
"L.A.-W,
REVII:i"iFYt
car raurwl
191, j�� -r/2,z
Cwwe tt V
WRA71 UNWRAMA
I"
PdtkPML0OY1
IP 'Ulk 1 ,
YMRA Vd1 kVGlgd llJ4lAalli
;fAzw
7-Z 2 -Z-
`m'^�+ VATI
V toTom
0l1D1uoYl0AR/a1[c1R10tV4r
I1ANct1
A 10DDY:
IA IIMV PATC
clrralax
Invoice - 001.007
24-Aug-2023 10:17 AM CST
Street Rehab Sewer tine Pipe Bursting Project
1350 Langham Beaumont, Texas 77706
Project Number. WU0322-16
001,007: To-Mex Construction LLC - Street Rehab Sewer Line Pipe Bursting Project
Amount Due: $28,181,77
For Contract Contract - 001 Street Rehab Sewer Line Pipe Bursting Project
Date
23-Aug-2023
Line Item
Unit price
Type
Group
3.0 Construction
Pay Period
21-Mar-2023 to 23-Aug-2023
Retainage
WC 5.00 - MS 0.00
Payment To
To-Mex Construction LLC
Maribel Torres
Date Due
Terms
Attachments
Line Items
Work Materials
Item Account WBSI Contract Previous Unit Completed Stored % WC % MS
#► Code Section Description Total Payments Quantity UoM Price (WC) (MS) Total Retainage Retainage
3.0 Construction
001 GC 1
Mobilization
1.00 @ 17,180,44 0.00 LS 17,180,44 0.00 0.00 17.180.44 0.00 0.0€
Contract
Including
17,180.44
Payment
Bond,
Performance
Bond,
Insurance,
and Moving
Equipment to
Project (N
002 GC 2
Full Depth
150.00 @ 1,696,00 0.00 SY 80.00 10.304.00 0.00 12,000.00 0100 0,0£
Contract
Repair of
80.00
Concrete
Pavement
(10")
003 GC 3
Flexible
250.00 @ 16,250.00 0.00 SY 66.00 0.00 0,00 16,250,00 0.00 0.0€
Contract
Pavement
65.00
Structure
Repair (4")
Work Materials
Item
Account
WBS1
Contract
Previous
Unit Completed
Stored
% WC
% Mz
f1
Code
Section
Description
Total
Payments quantity
UoM
Price
(WC)
(MS)
Total Retafnage Retainage
004
GC
4
Trench
350.00 @
208.00
0,00 L.F.
4,00
1,192,00
0,00
1,400.00
0.00
0.0C
Contract
Excavation
4.00
Protection
005
GC
5
Barricades,
1.000
4,783.00
0.00 LS
4,783.00
0.00
0.00
4,783.00
0.00
0.0t
Contract
Signs, and
4,783.00
Traffic
Handling
006
GC
6
Remove and
28,00 @
144,315.00
0,00 EACH
5,345.00
5,345.00
0.00
149,660.00
0.00
0.0L
Contract
Replace or
5,345.00
Install New
Std.
Fiberglass
Manhole, Up
to B' Depth
with All
Joints &
Connecti
007
GC
7
Install New
2.00 @
8,866.00
0,00 EACH
4,433.00
0.00
0.00
8,866.00
0.00
0.0c
Contract
Manhole,
4,433.00
Less than 5'
Depth, With
All Joints &
I
Connections
(Fiberglass)
008
GC
8
Extra Depth
100.00 @
0,00
0,00 V.F.
100.00
10.000.00
0.00
10,000.00
0.00
0.0C
Contract
for Now or
100,00
Replacement
Sid.
Manhole,
Over 8 Feet
Depth
(Fiberglass)
009
GC
9
Reconnect
80.00 @
55,055.00
0.00 EACH
716,00
2,145.00
0,00
57,200,00
0.00
0.0C
Contract
Service
715.00
Connection
i
by
Excavation
Including
Cleanouts to
Liner,
Complete, All
Sizes and
Dep
010
GC
10
Fumish and
1.00 @
686,00
0.00 EACH
585.00
0.00
0,00
585.00
0.00
0.0C
Contract
Instal; End-
585.00
of -Line
Cleanoutby
3
i
Excavation
I
Work Materials
Item
Account
W85!
Contract
Previous
Unit Completed
Stored
% WC
°%n MS
ti
Code
Section Description
Total
Payments Quantity
UoM
Price
(WC)
(MS)
Total Retaloage
Retainage
011
GC
11 Obstruction
6.00 @
2,550.00
0.00
EACH
425,00
0.00
0.00
2,550.00
0.00
0.0E
Contract
Removal by
425.00
Excavation,
All Sizes, All
Depths, With
Project
Manager's
Approval
012
GC
12 Clean and
1,500.00
6,150,00
0.00
L.F.
4.10
0.00
0.00
6,150.00
0.00
0.0(
Contract
Televise
@ 4.10
Sewer All
Sizes and
Depths as
Directed by
the Owners
014
GC
14 Pipe
4,268.00
181,390.00
0,00
L.F.
42,50
0,00
0.00 181,390.00
0,00
0.0E
Contract
Bursting 6"
@ 42.50
Sewarto
8.625" OD
HDPE
015
GC
15 Pipe
2,272.00
90,741.96
0,00
L.F.
53,63
31,105,40
0.00 121.847.36
0.00
0.0E
Contract
Bursting 12"
@ 53.63
Sewer to
12.76" OD
HDPE
Total
589,861.80
529,770.40
60,091.40
0.00 689,861.80
Change Order
No. 2 - 3.0 Construction
016
GC
16 Point Repair
2.00 @
8,100.00
0.00
EACH
4,050.00
0.00
0.00
8,100,00
0,00
0,0E
Contract
4,050, 00
Total
8,100.00
8,100.00
0.00
0.00
8,100.00
Change Order
No. 3 - 3.0 Construction
017
GC
17 Point Repair,
1.00 @
4,500.00
0.00
LS
4.500,00
0.00
0.00
4,500.00
0.00
0,0E
Contract
Cast iron
4,500.00
Pipe removal
replacement
with 8.625"
HDPE pipe,
sealing of
conflict box
Total 4,600.00 4,600.00
Change Order No. 4 - 3.0 Construction
003 GC 3 Flexible 130.00 @ 8,450.00 0.00 SY
Contract Pavement 65,00
Structure
Repair (4")
0.00 0.00 4,600.00
65.00 0.00 0,00 8,450,00 0.00 0.0E
Wort Materials
Item
Account
W851
Contract
Previous
Unit Completed
Stored
% WC
% MS
t!
Code
Section Description
Total
Payments Quantity UoM
Price (WC}
(MS)
Total Retainage
Relainage
006
GC
6
Remove and
2.00 @
10,690.00
0.00 EACH
5,345,00 0.00
0.00
10.690.00
0.00
0.0C
Contract
Replace or
6,345.00
Install New
Std.
Fiberglass
Manhole, Up
to 8'Depth
with All
Joints &
Connecti
011
GC
11
Obstruction
2.00 @
850.00
0.00 EACH
425,00 0.00
0.00
850.00
0.00
0.0C
Contract
Removal by
425.00
Excavation,
All Sizes, All
Depths, With
Project
Manager's
Approval
014
GC
14
Pipe
30.00 @
1,275.00
0,00 L.P.
42,50 0.00
0.00
1,275.00
0,00
0,0C
Contract
Bursting 6"
42.50
Sewer to
8.625" OD
HDPE
Total
21,266.00
21,265.00
0.00
0.00
21,266.00
Change
Order
No. S - 3.0 Construction
002
GC
2
Fuil Depth
-128.80 @
0.00
0.00 SY
80.00-10,304.00
0.00
-10,304.00
0,00
0.0C
Contract
Repair of
80.00
Concrete
Pavement
(10")
004
GC
4
Trench
-298.00 @
0.00
0,00 L.F.
4.00-1,192.00
0.00
-1,192.00
0.00
0,0C
Contract
Excavation
4.00
Protection
006
GC
6
Remove and
-1.00 @
0.00
0.00 EACH
5,345.00-5,345.00
0.00
-5,345.00
0.00
0.0C
Contract
Replace or
5,346.00
Install New
Std.
Fiberglass
Manhole, Up
to 8' Depth
with All
Joints &
Connecti
008
GC
8
Extra Depth
-100,00 @
0.00
0,00 V.F.
100.00-10,000.00
0.00
-10,000.00
0,00
0,0C
Contract for New or 100.00
Replacement
Std.
Manhole,
Over 8 Feel
Depth
(Fiberglass)
Work Materials
Item Account WBS! Contract Previous
Unit Completed Stored
% WC % MS
# Code Section Description Total Payments Quantity UoM
PYIco (WC) (MS)
Total Retalnage Retainage
009 GC 9 Reconnect -3,00 @ 0.00 0.00 EACH
715,00-2.146,00 0.00
-2.145.00 0.00 0.0C
Contract Service 715.00
Connection
by
Excavation
Including
Cleanouts to
Liner.
Complete, All
Sizes and
Dep
015 GC 15 Pipe -580m @ 0.00 0,00 L.F.
53.63-31,105.40 0.00
-31,105.40 0.00 OA€
Contract Bursting 12" 53,63
Sewer to
12.75" OD
HDPE
Total-60,091.40 0.00
-60,091.40 0.00
-60,091.40
Grand Total: $0.00
Summary
1. CONTRACT SUM +AMENDMENTS
589,861.80
2. NET CHANGE BY Change Order
-26,226,40
3. CONTRACT SUM TO DATE (Line 1+ Line 2)
563,636.40
4. TOTAL COMPLETED & STORED TO DATE
563,636.40
5. RETAINAGE
5a. 5.00% Of Completed Work (Column I on Continuation Sheet)
0.00
5b. 0.00% Of Stored Material (Column J on Continuation Sheet)
0.00
TOTAL RETAINAGE (5a + 5b)
0.00 !
6, TOTAL EARNED LESS TOTAL RETAINAGE
563,635,40
7, LESS PREVIOUS CERTIFICATES FOR PAYMENT
535,453.63
8. CURRENTAMOUNT DUE
$28,181,77
9. BALANCE TO FINISH, INCLUDING RETAINAGE (Line 3 less Line 6)
0.00
j
Change Order Summary
f
NET CHANGE by Change Order
$-26,226.40
ADDITIONS
DEDUCTIONS
Total changes approved in previous pay periods
33,865.00
0.00
i
Total approved this pay period
0.00
-60,091.40
TOTAL
33,865.00
-80,091,40
Accounting and Payment Status
Invoice Id
Payment Status
Paid Date
Pb Number
Accounting Project Code
Custom Accounting Field 06
Custom Accounting Field 07
Approval Pending
Name or Role
1 Inspector
2 Project Manager
3 City Engineer
4 Director
5 Admin
752
Check Vs
Paid Amount
430950 FEMA Number
WWC019 i Custom Accounting Field 04
Custom Accounting Field 06
Custom Accounting Field 08
Status
Approved
Terry Croft
24-Rug-2023 07:04 AM CST
Approved
Kevin Young
24-Aug-2023 W55 AM CST
Approved
Amalia "Molly" Villarreal
24-Aug-2023 10:00 AM CST
Approved
Bart Bartkowiak
24-Aug-2023 10:14 AM CST
Pending
Created by: Kevin Young on 23-Aug-2023 Last Modified by: Bart Bartkow€ak on 24-Aug-2023
$ 0.00
Due: 31-Aug-2023
Actions
f
Contract # 001.005
19-Sep-2023 01:41 PM CST
001.005: Change Order No. 5
Street Rehab Sewer Line Pipe Bursting Project
1350 Langham Beaumont, Texas 77706
Project Number: WU0322-16
Grand Total: $-60,091.40
For 001 Street Rehab Sewer Line Pipe Bursting Project
Division 33
Line Item Unit price
Type
Group 4.0 Equipment/Closeout
Scope of Change Order No 5 is being requested to account for quantities not used in completing the project. The project has been completed and
Work inspected by City staff. Items removed were either over -estimated or found during construction to be in satisfactory condition. Thirty -
Seven (37) additional calendar days are requested to account for supply chain issues with fiberglass manholes and the crew being pulled
to assist on the Calder Place Emergency Pipe Bursting Project.
Notes Accepted by City Council on September 12, 2023 by Resolution No. 23-246.
Awarded To To-Mex Construction LLC
Maribel Torres
Reason Quantity Adjustment
Code
Days 37
Changed
Attachments
RES 23-246 Sewer Line PB Final.pdf
Change Order Summary
Original Contract Sum
Net Cost by Previous Approved COs
Contract Sum Before This CO
Contract Sum Changed By This CO
New Contract Sum
All Change Orders make up -4.45% of the Original Contract
Accounting and Status
Accounting Status
Item Id
589,861.80 Substantial Completion Date
33,865.00 Net Time Change By Previous COs 12 days
623,726.80 Substantial Completion before This CO
-60,091.40 Time Changed By This CO 37 days
563,635.40 New Substantial Completion Date
445
PO Number
Accounting Project Code
Custom Accounting Field 05
Custom Accounting Field 07
Line Items
430950 FEMA Number
WWC019 Custom Accounting Field 04
Custom Accounting Field 06
Custom Accounting Field 08
Account
WBS/
Total
Item # Code
Section
Description
Quantity UoM
Unit Price
Amount
3.0 Construction
002 GC
2
Full Depth Repair of Concrete Pavement (1011)
-128.80 SY
80.00
-101304.00
Contract
004 GC
4
Trench Excavation Protection
-298.00 L. F.
4.00
-1,192.00
Contract
006 GC
6
Remove and Replace or Install New Std. Fiberglass
-1.00 EACH
5,345.00
-5,345.00
Contract
Manhole, Up to 8' Depth with All Joints & Connecti
008 GC
8
Extra Depth for New or Replacement Std. Manhole,
-100.00 V.F.
100.00
-10,000.00
Contract
Over 8 Feet Depth (Fiberglass)
009 GC
9
Reconnect Service Connection by Excavation
-3.00 EACH
715.00
-2,145.00
Contract
Including Cleanouts to Liner, Complete, All Sizes
and Dep
015 GC
15
Pipe Bursting 12" Sewer to 12.75" OD HDPE
-580.00 L.F.
53.63
-31,105.40
Contract
Total
-609091.40
Grand Total:
-60,091.40
Approval Approved
Due:21-Sep-2023
Name or Role
Status
Actions
1 External -GC
Approved
Maribel Torres
13-Sep-2023 11:51 AM CST
2 Project Manager
Approved
John Pippins
14-Sep-2023 10:02 AM CST
3 City Engineer
Approved
Amalia "Molly" Villarreal
14-Sep-2023 10:22 AM CST
4 Director
Approved
Bart Bartkowiak
14-Sep-2023 10:24 AM CST
5 Admin
Approved
Crystal Garza
14-Sep-2023 10:25 AM CST
Name or Role Status Actions
6 Assistant City Manager Approved
June Ellis
14-Sep-2023 03:39 PM CST
7 City Clerk
Approved
Tina Broussard
14-Sep-2023 03:40 PM CST
Created by: Kevin Young on 15-Aug-2023 Last Modified by: Tina Broussard on 14-Sep-2023