HomeMy WebLinkAboutRES 23-221RESOLUTION NO. 23-221
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on June 14, 2012, the City Council of the City of Beaumont, Texas
passed Resolution No. 22-153 awarding a contract in the amount of $3,670,700.00 to
King Solution Services, Inc., of Houston, Texas, for the City -Wide Pipe Bursting
Contract- Phase I Project; and,
WHEREAS, previous Change Order Nos. 1-5, in the amount of $506,325.00
increased the total contract price to $4,177,025; and,
WHEREAS, Change Order No. 6, in the amount of $76,425.00, is required to add
Map 14 plan sheets for 1,275 LF of pipe bursting and replacement of six (6) manholes
on 2161 Street. It was discovered during construction in the area that the crown of the
pipe disintegrated and is progressing toward complete failure of the line if not repaired;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 6, in the amount of $76,425.00 for additional work described above, thereby
increasing the total contract amount to $4,253,450.00 for the City -Wide Pipe Bursting
Contract- Phase I Project; and,
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 15th day of
August, 2023.
RESOLUTION NO. 23-195
BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF BEAUMONT:
WHEREAS, on June 14, 2022, the City Council of the City of Beaumont, Texas
passed Resolution No. 22-153 awarding a contract in the amount of $3,670,700.00 to
King Solution Services, Inc., of Houston, Texas, for the City -Wide Pipe Bursting
Contract- Phase I Project; and,
WHEREAS, Change Orders Nos. 1-4, in the amount of $488,825.00, are
attached for your review; and,
WHEREAS, Change Order No. 5, in the amount of $17,500.00, is requested to
add one (1) additional bid item to install 56" x 56" square concrete tops at a minimum of
6" higher than the right of way elevation and concrete encasement for five (5) manholes
along Jefferson County Drainage District No. 6 (JCDD6) ditch bank in the Piney Point
area, Map 1 of the contact plan set, thereby If approved increasing the total contract
amount to $4,177,025.00;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out In the preamble to this resolution are
hereby, in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 5, in the amount of $17,500.00 for additional work described above, thereby
Increasing the total contract amount to $4,177,025,00 for the City -Wide Pipe Bursting
Contract- Phase I Project; and,
The meeting at which this resolution was approved was in all things conducted In
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 25th day of
July, 2023.
Contract - 001.006
07-Aug-2023 11:08 AM CST
CITY WIDE PIPE BURSTING CONTRACT - PHASE 1
1360 L.angharn Rd Beaumont, Texas 77707
Project Number: WU1022-02
001.006: CO#001.006: CO # 6: Pipe Bursting Map 14 Addition - 21 st Street
Grand Total: $76,425,00
For 001 WU 1022-02 City Wide Pipe Bursting Contract -Phase I
Divlslon 33
Line Item Unit price
Type
Group 3.0 Construction
Scope of Change Order No. 6 will add Map 14, 21st Street, to the pipe bursting plan sheets. The Change Order will add 1,275 LF of pipe bursting
Work and replace 6 manholes.
Notes It was discovered recently that the pipes crown has completely disintegrated and is progressing towards complete failure of the line.
Awarded To King Solution Services LLC
Allan Negrete
27738
Reason Owner Requested
Code
Days 35
Changed
Attachments CO 6—City Wide Plpe Bursting (Executed).pdf
Change Order Summary
Original Contract Sum
3,670,700.00I Substantial Completion Date
Net Cost by Previous Approved COs
506,325.00) Net Time Change By Previous Cps 65 days
Contract Sum Before This CO
4,177,025.00 Substantial Completion before This CO
Contract Sum Changed By This CO
76,425.00 Time Changed By This CO 35 days
New Contract Sum
4,253,4%00 New Substantial Completion Date
All Change Orders make up 16.88% of the Original Contract
Accounting and Status
Accounting Status
Item Id
437
PO Number
430946 FEMA Number
Accounting Project Code
Custom Accounting Field 05
Custom Accounting Field 07
Line items
Item Account WBSI
# Code Section Description
3.0 Construction
Custom Accounting Field 04
Custom Accounting Field 06
j Custom Accounting Field 08
013 GC Contract 708 Remove and Replace or Install New Sid, Fiberglass Manhole, Less
than 5' Depth (With All Joints & Con
014 GC Contract 708 Remove and Replace or Install New Sid, Fiberglass Manhole, V to 8'
Depth (With All Joints & Connect
019 GC Contract 4020 Pipe Bursting 6"-8" Sewer to 8,626" OD, All Depths
Total
Approval Pending
Name or Rote
1 External -GC
2 Project Manager
3 City Engineer
4 Director
5 Admin
6 Assistant City Manager
7 City Cleric
Status
Approved
Allan Negrete
07-Aug-2023 11:00 AM CST
Approved
John Pippins
07-Aug-2023 t 1:03 AM CST
Pending
Created by: Kevin Young on 04-Aug-2023 Last Modified by: John Pippins on 07-Aug-2023
Actions
Unit Total
[Quantity UoM Price Amount
3.00 EACH 5,000,00 15,000.00
3.00 EACH 5,600.00 16,800.00
1,275.00 LF 35.00 44,625.00
76,426.00
Grand Total: 76,425.00
Waiting for previous approvals.
Waiting for previous approvals.
Waiting for previous approvals.
Waiting for previous approvals.
Due: 14-Aug-202"
Contract - 001,005
27-Jul-2023 02:35 PM CST
001.005: CO # 5: Manhole Top/Encasement Addition
CITY WIDE PIPE BURSTING CONTRACT -PHASE I
1360 Langham Rd Beaumont, Texas 77707
Project Number: WU1022-02
Grand Total: $17,500.00
For 001 WU1022-02 City Wide Pipe Bursting Contract - Phase I
Division 33
Line item Unit price
Type
Group 3.0 Construction
Scope of Change Order No. 5 will add one (1) additional bid item to install 56" x 56" 6quaro concrete tops at a minimum of 6" higher than the right -
Work of -way elevation and concrete encasement for five (5) manholes along the DD6 ditch bank in the Piney Point area, Map 1 of the plan set,
Notes
Awarded To King Solution Services LLC
Allan Negrete
27738
Reason Owner Requested
Code
Pays 5
Changed
Attachments
Quote -Concrete encasement and square tops for new manhoies.pdf
RES 23-195 City Wide PB Phase I C_05.pdf
Change Order Summary
Original Contract Sum
3,670,700,00 Substantial Completion Date
Net Cost by Previous Approved Cos
488,825.00 Net Time Change By Previous COs 80 days
Contract Sum Before This CO
4,159,525.00 Substantial Completion before This CO
Contract Sum Changed By This Co
17,500.00 Time Changed By This CO 5 days
New Contract Sum
4,177,025.00 New Substantial Completion Date
All Change Orders make up 13.79% of the Original Contract
Accounting and Status
Accounting Status
Item Id
423
PO Number
430946 FEMA Number
Accounting Project Code
Custom Accounting Field 04
Custom Accounting Field 05
Custom Accounting Field 06
Custom Accounting Field 07
( Custom Accounting Field 08
Line Items
Item Account WBS/
Unit
Total
# Code Section
Description Quantity UoM Price
Amount
3.0 Construction
025 GC Contract 00000
Concrete Encasement & Square Concrete Tops for 5 Manholes along 1.00 LS 17,500.00
17,5%00
DD6 Ditch Bank on Map 1
Total
17,500.00
Grand Total: 17,600.00
Approval Approved
Due: 3-Aug-2023
Name or Role
Status Actions
1 External -GC
Approved
Allan Negreto
14-Jul-2023 05:26 PM CST
2 Project Manager
Approved
i
John Pippins
17-Jul-2023 01:19 PM CST
3 City Engineer
Approved
Antalia "Molly" Villarreal
17-Jul-2023 01:40 PM CST
4 Director
Approved
Bart Bartkowiak
17-Jul-2023 06:00 PM CST
5 Admin
Approved
Dara Woodruff
26-Ju1-2023 09:32 AM CST
6 Assistant City Manager
Approved
June Ellis
27-Jul-2023 02:15 PM CST
7 City Clerk
Approved
Tina Broussard
27-Jul-2023 02:33 PM CST
Created by: Kevin Young on 14-Jul-2023 Last Modified by: Tina Broussard on 27-Jul-2023
Contract # 001.004
19-May-2023 01:22 PM CST
001.004: CO # 4: Manhole Quantity Adjustment
CITY WIDE PIPE BURSTING CONTRACT - PHASE 1
1350 Langham Rd Beaumont, Texas 77707
Project Number: WU1022-02
Grand Total: $50,000.00
For 001 WU1022-02 City Wide Pipe Bursting Contract - Phase I
Division 33
Line Item Unit price
Type
Group 3.0 Construction
Scope of The change order is required to substitute the pre -cast manholes for the fiberglass manholes because of a supply chain shortage In
Worst fiberglass manholes.
Notes
Awarded To King Solution Services LLC
Allan Negrete
27738
Reason Quantity Adjustment
Coda
Days 0
Changed
Attachments
Change Order Summary
Original Contract Sum
Net Cost by Previous Approved Cos
Contract Sum Before Tills CO
Contract Sum Changed By This CO
New Contract Sum
All Change Orders make up 13.32% of the Ortglnai Contract
Accounting and Status
Accounting Status
Item Id
3,670,700.00 ! Substantial Completion Date
430,825.00 ; Net Thne Change By Previous Cos 60 days
4,109,526.00 Substantial Completion before This CO
60,000.00' Ti ne Changed By This CO 0 days
4,159,625,00 ; New Substantial Completion Date
393
PO dumber
Accounting Project Code
Custom Accounting Field 05
Custom Accounting Field 07
Line Items
Item Account WSW
# Code Section Description
3.0 Construction
430946 FEMA Number
Custom Accounting Field 04
Custom Accounting Field 00
Custom Accounting Field 08
Unit Total
Quantity UoM Price Amount
013 GC Contract 708 Remove and Replace or Install New Sid. Fiberglass Manhole, Less -25.00 EACH 5,000.00-126,000.00
than 5' Depth (With All Joints & Con
015 GC Contract 3301 Remove and Replace or Install New Sid. Pre -Cast Concrete Manhole, 25.00 EACH 7,000.00 175,000.00
Less than S' Depth, (With All Join
Total 60,000.00
Grand Total: 50,000,00
Approval Pending
Name or Role
1 External -GC
2 Project Manager
3 City Engineer
4 Director
5 Admin
6 Assistant City Manager
7 City Clerk
Status
Approved
Allan Negrete
19-May-2023 07:45 AM CST
Approved
Kevin Young
19-May-202311:08 AM CST
Approved
Amalla "Molly" Villarreal
19-May-202311:22 AM CST
Approved
Bart Barlkowlak
19-May-2023 12:27 BM CST
Pending
Created by; Kevin Young on 10-May-2023 Last Modified by: Bart Bartkowlak on 19-May-2023
Actions
Waiting For previous approvals.
Waiting for previous approvals.
Due; 26-May-2023
Contract # 001.003
02-May-2023 09:06 AM CST
001.003: CO # 3: Map 13 Revisions - 4th Street
CITY WIDE PIPE BURSTING CONTRACT. PHASE 1
1350 Langham Rd Beaumont, Texas 77707
Project Number: WU1022-02
Grand Total: $0.00
For 001 WU1022-02 City Wlde Pipe Bursting Contract - Phase I
Division 33
Line Item Unit price
Type
Group 3.0 Construction
Scope of Proposed Change Order No. 3 wili add revised plan sheets for previous Change Order No. 2. The revisions are for Map 13, on the 4th
Work Street addition, which updates four (4) sections planned for open out to be changed to pipe bursting with 16" HDPE. No additional
quantities are needed for this change order.
Notes
Awarded To King Solution Services LLC
Allan Negrete
27738
Reason Owner Requested
Code
Days 0
Changed
Attachments CO 3 Plans—Executed.pdf
Change Order Summary
Original Contract Sum
Net Cost by Previous Approved COs
Contract Sum Before This CO
Contract Sum Changed By This CO
Now Contract Sum
All Change Orders make up 11.95% of the Original Contract
Accounting and Status
3,670,700.001 Substantial Completion Date
438,825.001 Net Time Change By Previous Cos
4,109,526.00 Substantial Completion before This CO
0= Time Changed By This CO
4,109,526.001 New Substantial Completion Date
60 days
0 days
Accounting Status
Item Id
P4 Number
Accounting Project Code
Custom Accounting Field 06
Custom Accounting Field 07
Line Items
386
1
430946 FEMANumber
F Custom Accounting Field 04
Custom Accounting Field 06
i
i Custom Accounting Field 00
Item 0 Account Code WBSf Section Description
Approval Approved
Quantity UoM
Name or Role
status
1 External -GC
Approved
Allan Negrete
01-May-2023 10:31 AM CST
2 Project Manager
Approved
Kevin Young
01-May-2023 10:41 AM CST
3 City Engineer
Approved
Amalla "Molly" Villarreal
01-May-2023 10:43 AM CST
4 Director
Approved
Bart Bartkowlak
01-May-2023 12:43 PM CST
6 Admin
Approved
Para Woodruff
01-May-2023 01:39 PM CST
6 Assistant City Manager
Approved
June Ellis
01 -May-2023 04:31 PM CST
7 City Clerk
Approved
Tina Broussard
01-May-2023 04:42 PM CST
Created by: Kevin Young on 20-Apr-2023 Last Modified by: Tina Broussard on 01-May-2023
Unit Price Total Amount
Due: 8-May-2023
Actions
| '
' %ho~�8o�1PW Pn�vNm�oconkao
| .
. Ok]ntr8ot # 001.002 _
10-Jan-2023 Oa:40 PM CST
CITY WIDE PIPFBURSTING CONTRACT ' PHASE {
1^6ou*nohumuaBeaumont, Texas r,ror
Project Number: WIL111022,02
~^'
Grand Total: $438,828.00
For 001 WU1022-02 City Wide Pipe Bursting Conifact - Phase I
Division 33
Group Construotlon
Scope of Addition of Map I a on & 4th Street to the plan set. Map 13 adds approximately 4100 LF of pipe bursting of 15" to 16" OD HDPE pipe,
Work approxImat6ly 175 LF of pipe bursting 611 to 8.62&1 OD HOPE pipe, approximately 1100 LF of open out, and 17 manholes to S. 401 Street.
Notes Map 13on8,41h Stroatis being added to replace the sewer lines and manholasheibreifia strootcan barehabill(ated. 7110sewarlInes
and manholes era In need of repair and ore recommended for replacement,
I Awarded To i(Ing Solution Services LLO
Mario Jalmos
27738
' --- -'--''- n�� Owner Requested
Co de
Days 60
qh^n000^. .......... ' ' ' ' -''^ '^ '' ' ' '' ' ' '' ' ' ' ^' ^' ' ^' ' ' ''' ' �- '' -' ' ' '- -''' ' ' ' ''''' -^
| Attmc`mvmx
k... ' ' ' ' ^ '' ' ... ... ..... '." . ... '' ''�
Change Order Summary
-
Original Contract Sum
3,670,700,00
Substantial ComPleflOn Date
Not Cost by Previous Approved C09
0,00
Not Time Clionge By Previous COs 0 days
contraot Sum Before This CO
3,670,700.00
Substantial Completion before Tills GO
Contract Sum Chalig ad By Tills GO
438,826.00iTime
ClIongod By This GO 60 days
4,1109,826-00
Now Substantial Completion Date
L--_-' --'--------�---------'--------------~------'
Accounting and Status
A00ounting Status
1/18123,3:411 PM projeolmate8 contract
340
PO Number 430946
Custom Accounting Field 05
Custom Accounting Field 07
FEMA Number
'------'---------------'---'------
Custom Accounting Field o*
custom Amvvw000uField uu
.....
Custom Acrounting Fluid OU
Line Items
' '......''
.......
'''.....
'.........
...........
Ran)
Account W1381
Unit
Total
jj
Coda 600110"
Description
Quantity UoM
priao
Amount
016
GCConiraot 3301
Remove and Replace or Install Now Sid. Pro -Cast Concrete Manhole,
2,00 EACH
7,000.00
14,000M
Less than Vlopth, (Willi Alt Join
016
GO Contract 3301
Remove and Replace or Inglell Now Sid. Pre -Cost Concrete M anholo,
16.00 EACH
7.200.00
108,000-00
mo,8ox»o
Total
Grand Totw8436,626.00
ApproVal Approved
Due: 25-Jan-2023
Name mriots
_ Status Actions _ _
_----
----__'—'--'--_—_'----._—_
1 *mwmal-mo
Approved
NlaoN«orale
1a-Jon-2V23mosoPM.CST
,...,.____,.._�__.
2 Proj*mMpuunmr
A»o,mmo
JohopippIno
%-Jen-2V o.ouAoPM,oaT___~,^,'~`^_^
o city Engineer
x»»mvo
Amalie "MWkpVillarreal
m-Joo-2023O0:03PMCST _____
4 o|moto/
Approved
BonBorlkmN°k
io-Ja»-20m.O3�xMW.ouT~____^___,_~__''____`___`,_,~__�_._^_._~..^,_�
u /dmtn
'���������.���
xppnwo
Darw"o*mx
____m'J°o*mmo»41PMCST ___..._____________________________ _
1f18123, 3:91 Pm Projeotmetes Contraot
Created by: Kevin Young on 22•Der-2022 Lai Modlfled by: Uara Woodruff on 18-Jan•2023
APPROYED BY:
xcluieth R. Williams
City Manager
ATTESTED BY:
�2��
Date Tina Broussard Date
City Cleric
httAs:I]af lyoiboaumonkprajeotmates,comlPra)eotmoteslConira otMgmtIContraotPr4 nterrriendly.oapx7ancm28878t70100ODB7580F61 C408707EB82578... 313
CITY OF BEAUMONT
DAier
July 20, 2022
PfoJecl;
Cllywtds Plpa Dursllnpcontrail •PhAI0I
Counlyl
JHf+non
1111111011
nlaumonl
contrailNum4rr
01DNOMPIM42
OWnfn
01y of ummont
Conlr+clort
ltlnp8olutlonSowlcos,LLO
G.O. NO,I
I
ORIOINALCONTRACT AMOUNT;
S 8,0?0700.OD
NET FROM PREVIOUS CHANGE CRDERB.
5
TOTAL AMOUNT OF THIS CHANGE ORDER;
�
PERCENT Of THIS 011410E ORDER;
0.06Y�
TOTAL PERCENT OHANO E ORDER TO DATfi.
0,00%
NEW QONTRACTMOUNT,
3-,670.70000.
CONTRAOT T11AH
ORIOINALCONTRAOTTIM& 206celenderda s
ADDITIONALCONTRAOTTIMBPER PREMOU8CHANCE ORDER& ocslan ±rdcyt
ADDITIONAL CONTRAOT TIME PER TII18 CHANGE ORDER; �. O ctllnder dsys
REWIRED CONTRAQTWE! =caIndstdeys _
CQNDITJON QF CHANO�c
•Conuerlar ecknoyled0esand s0nss UtelVfs edjwlntentslneonVsclpdu arfdaonutetBme ttlpWsled 3n pstf Ch Inpe Oldit lepufsnu NII compenf+tlan (or sll hve ues
anddeffuuiln+hecoslol,and lhelffnef+yIAH4topil(olmthe ontrawarkunder the mUsclerhfnydirectl 0)Inds4d0(Comm chiNd0fdrearAillpfarfousChur loAtrs.
Acceptance alIhhYMA eenitMfeansplitmealhehYfInOmerandQoAlfectorthatNeOhenyeOrd1ff plifantsohoil lnclurtfs,mvWllU e0tsadupo6s4fufImamtoNsCQnu4ct
end tholConirsdo: Wit Vohs MI flphte to bta a clelm anft Oh1A0a 01df r sMf RlsplspUEy sauulfd,'
ACCEPTED DY1
._.-----
A -7 2p 2027,
rlOttOt 1101 RVIOEI,LL4.REP A
REVIEWED DYI
l
APPROVED DYt
myY 1AARA02ft }r
L5
PREPARED DYs
41 pIFP NIII, OATrs
WATtnUlkeltlt/ +IOIiMANA4RR
z
22 -
MI bA€1TROYPAlf v RW
RIREOTOR OF PUatlO IV4 RKa 8 TCOIINOLU OY
/EnVICEI
ATI(WISO DYI
Contract # 001.006
17-Aug-2023 09:04 AM CST
CITY WIDE PIPE BURSTING CONTRACT - PHASE 1
1350 Langham Rd Beaumont, Texas 77707
Project Number: WU1022-02
001.006: CO#001.006: CO # 6: Pipe Bursting Map 14 Addition - 21 st Street
Grand Total: $76,425.00
For 001 WU1022-02 City Wide Pipe Bursting Contract - Phase
Division 33
Line Item Unit price
Type
Group 3.0 Construction
Scope of Change Order No. 6 will add Map 14, 21 st Street, to the pipe bursting plan sheets. The Change Order will add 1,275 LF of pipe bursting
Work and replace 6 manholes.
Notes It was discovered recently that the pipes crown has completely disintegrated and is progressing towards complete failure of the line.
Awarded To King Solution Services LLC
Allan Negrete
27738
Reason Owner Requested
Code
Days 35
Changed
Attachments
CO 6_City Wide Pipe Bursting (Executed).pdf
RES 23-221 City Wide PB Phase I C_06.pdf
Change Order Summary
Original Contract Sum
Net Cost by Previous Approved COs
Contract Sum Before This CO
Contract Sum Changed By This CO
New Contract Sum
All Change Orders make up 15.88% of the Original Contract
Accounting and Status
3,670,700.00 Substantial Completion Date
506,325.00 Net Time Change By Previous COs 65 days
4,177,025.00 Substantial Completion before This CO
76,425.00 Time Changed By This CO 35 days
4,253,450.00 New Substantial Completion Date
Accounting Status
Item Id 437
PO Number 430946
Accounting Project Code
Custom Accounting Field 05
Custom Accounting Field 07
Line Items
Item Account WBS/
# Code Section Description
3.0 Construction
FEMA Number
Custom Accounting Field 04
Custom Accounting Field 06
Custom Accounting Field 08
013 GC Contract 708 Remove and Replace or Install New Std. Fiberglass Manhole, Less
than 5' Depth (With All Joints & Con
014 GC Contract 708 Remove and Replace or Install New Std. Fiberglass Manhole, 5' to 8'
Depth (With All Joints & Connect
019 GC Contract 4020 Pipe Bursting 6"-8" Sewer to 8.625" OD, All Depths
ij
Total
Approval Approved
Name or Role
Status
1 External -GC
Approved
Allan Negrete
07-Aug-2023 11:00 AM CST
2 Project Manager
Approved
John Pippins
07-Aug-2023 11:03 AM CST
3 City Engineer
Approved
Amalia "Molly" Villarreal
07-Aug-2023 06:30 PM CST
4 Director
Approved
Bart Bartkowiak
07-Aug-2023 06:32 PM CST
5 Admin
Approved
Dara Woodruff
16-Aug-2023 09:28 AM CST
6 Assistant City Manager
Approved
June Ellis
16-Aug-2023 01:22 PM CST
7 City Clerk
Approved
Tina Broussard
16-Aug-2023 02:45 PM CST
Unit Total
Quantity UoM Price Amount
3.00 EACH 5,000.00 15,000.00
3.00 EACH 5,600.00 16,800.00
1)275.00 LF 35.00 44)625.00
769425.00
Grand Total: 76,425.00
Due: 23-Aug-2023
Actions
Created by: Kevin Young on 04-Aug-2023 Last Modified by: Tina Broussard on 16-Aug-2023