HomeMy WebLinkAboutRES 23-132RESOLUTION NO. 23-132
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on June 14, 2022, the City Council of the City of Beaumont, Texas
passed Resolution No. 22-151 awarding a contract in the amount of $589,861.80 to To-
Mex Construction, LLC, of Houston, Texas, for the Street Rehab Sewer Line Pipe
Bursting Project; and,
WHEREAS, Change Orders Nos. 1-3, in the amount of $12,600.00, increased
the total contract price to $602,461.80; and,
WHEREAS, Change Order No. 4, in the amount of $21,265.00, is required for the
addition of quantities on four (4) bid line items due to unanticipated field conditions
found during construction;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are
hereby, in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 4, in the amount of $21,265.00 for additional work described above, thereby
increasing the total contract amount to $623,726.80 for the Street Rehab Sewer Line
Pipe Bursting Project; and,
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 9th day of
May, 2023.
Mayor Robin Mouton -
RESOLUTION NO.22-161
WHEREAS, the City of Beaumont solicited bids for furnishing all tabor, materials,
and equipment for the Street Rehab Sewer Line Pipe Bursting Project; and,
WHEREAS, To-Mex Construction, LLC, of Houston, Texas, submitted a bid in
the amount of $589,861.80; and,
WHEREAS, the City Council is of the opinion that the bid submitted by To-Mox
Construction, I_L.C, of Houston, Texas, is the lowest responsible bidder providing
services at the best value to the City and should be accepted;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT-.
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Council hereby approves the award of a contract to To-Mex
Construction, LLC, of Houston, Texas, in the amount of $689,861.50 for the Street
Rehab Sewer Line Pipe Bursting Project; and,
BE IT FURTHER RESOLVED THAT the Interim City Manager be and he is
hereby authorized to execute a contract with To-Mex Construction, LLC, of Houston,
Texas, for the purposes described herein.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551,
"Exhibit A"
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 14th day of
June, 2022,
- Mayor robin Mouton ..
Contract # 001.004
01-May-2023 07:34 AM CST
001,004: Change Order No, 4
Street Rehab Sower Line Pipe Bursting Project
1360 Longham Boam"nt, Toxas 77706
Project Number; WU0322-1G
Grand Total, $21,265.00
For 001 Street Rehab Sewer Line Pipe Bursting Projool
Division 33
Lloo Itom Unit price
.Type
Group 3.0 Construction
Scope of The Contractor will perform Plpo Qursling tasks as noted and In accordance with the details provided In the project contract dowunlonts or
Work as directed by lho Pnglneor.
Notes Change Order No. 4 is requested to add additional quantities to tour (4) bid items to relied quanl€Ues used In ilia field.
Awarded To To-Mox Construction LLC
Marlbet Torres
Reason QuanlllyAdjustmant
Code
Days 0
Changed
Attachments
Pending Pay item Street Rehab Project.xfsx
Change Order Summary
original Contract Sum
Net Cost by Previous Approved COs
Contract Sum fanfare Thio CO
Contract Sum Changed By This CO
Now Contract Sum
Ail Change Orders make up 614% of [tie Original Contract
Accounting and SUM
AcCoullE€ng Status
Item Id
6G9,861.80 Substantial Completion Date
12;600.00: Not Time Change By Provlous Cos 12 days
602,461,80 Substantial Completion before This CO
21,265.00 Tigre Changed By This CO 0 days
623,726.80 New Substantial Completion Dato
389
PC Number
430950
Ft -MA Number
Accounting Projact Code
WWC019
CustomAccounting l=lold 04
cuslornAocounling Field 05
Custom Accounting Field O0
Custom Accounting Field 07
Custom AcoountilIg Fle10 00
Line items
(tom Aeoount WBS1
Unit
Total
it Code Section
Description
Quantity UoM
Price
Amount
3.0 Construction
003 GG Contract 3
Flexible Pavement Structure Repair (4")
130.00 BY
66,00
8,450.00
006 GC Contract 6
Remove and Replace or Install New Std. Fiberglass Manhole, Up to 0' 2,00 EACH
6,346,00
10,690.00
Depth with All Joints & Connectl
011 GG Contract 11
obstruotton Rornoval by Excavation, All Sixes,
All Depths, Willi Peojoot 2,00 EACH
426.00
050.00
Manager's Approval
014 GC Contract 14
Pipe Bursting 6" Sewer to 0,626" CD HOPE
30.00 i.,F.
42.50
1,275.00
Total
21,206.00
Approval Pondlnn
Name or Role
1 Exleural-GC
2 Project Manager
3 City Engineer
4 Director
6 Admin
6 Assistant City Manager
7 City Clerk
Status
Approved
MarlbolTorras
25•Apr-2023 02;30 PM CST
Approved
Kevin Young
25-Apr-2023 03:31 PM CST
Approved
Amalle "Molly" Vlllarroat
20•Apr-2023 03:42 PM CST
Approved
Bart Barlkowlak
20•Apr-2023 03:56 PM CST
Pending
Created by; l(ovin You)tg on 24-Apr-2023 La8t Modilled by: Dara Woodruff on 01•Mey-2023
Grand Total: 21,265.00
Actions
Welling for pravlous approvals.
Walling for previous approvals.
Due: 6-May-2023
Contract - 001,003
00-Doo-2022 02:23 PM CST
001,003: change Order No. 3
Street Rohsb Salvor Una Pipe Bursting Project
1350 Lnngliatrt Lleaumont, Texas 77708
Project Number: WU0322-16
Grant[ Total: $4,600,00
For 001 Street Rehab Sower tine Plpe Bursting Project
Division 33
Line Item Untt price
Typo
Group 3.0 Conslructlon
Scopo of To add an addition bid Ilom for point repair and cast Iron pipe removal, sualing of manhole Inside and oulWdo of storm drain, and
Work replacemetlLof lite 6Inch plpo Mill 8.626 Inch HDPE from MN-234 to 3 fl. past conlllct box.
Notes
Awarded To To•Mox Consimellon LLC
Nindbel Torras
Roason Unforseon Slla Conditions
Code
Days 6
chatlged
Attachments kXTERNAL City of Beaurnont Strout Rehab Point Repair Quoto.pdf
Change Order summary
Original Contract Sutn 589,861,80IStthstantlat
Colnplotton Date
Not Cost by Previous Approved 00s 8,100.00lNotTime
Change By Previous COs G days
ContractsUnl l3ofore This CO 697,001,80:Substantial
Completion before This CO
t
Contract Sum Chaltgod BY This CO 4,500,00
I7into Changed By This CO 6 days
Now Contract Sum 602,461.80
� Now Substantial Completlon Pato
All Change Orders mako tip 2.14% of the QrlgInal Contract
Accounting and Status
Accntulting States
Humid
325
PO Nun€bor
Accounting Project Coda
Cuatom Accounting Flold 06
CuslomAocounllng Mold 07
Line Items
ltorn Aocount was/
fJ Codo soctlon Dosarlptlon
3,0 Construction
430050 I FGMA Nunthor
Vv1MC01fl CuatontAccomilingField 04
CustomAccountlog Flold 00
CustomAccountinq Flold 09
Unit Total
Quantity Uom Prtco Amount
017 GC Contract 17 Polnt Ropalr, Cast Iron Plpe removal A replacoment with 8.626" HOK 1.00 t.S 000.00 4,600.00
pipe, sealing of conflict box
.Total •� .—._._._..._. _.._�_._..�...._-�---•---�__�_ ___.�_�. - ——-----•--- 4,600.00
Grand Total: 4,600.00
Approval Approved
Name or Role
status
1
External -GC
Approved
Marlbel Tortes
05•Doc-2022 02.07 PM CST
2
ProJoctManagor
Approved
John Pippins
00.Doo-2022 00:60 AM CST
3
City Engineor
Approved
Amalla "Molly" Villarreal
00•Doc-2022 00:20 AM CST
4
Director
Approvod
Curt partkotvlak
06-Doo-2022 00:42 AM CST
5
Admin
Approved
Da€a Woodruff
06•Doc-2022 09:68 AM CST
APPROVED BY: A
1Cel11 th It%w] atns Dot
City Mnnager Al
�c
us
I]
BY;
Duo: 13•Doo-2022
Actions
GontyacL If 001,002
10-06-2022 08:44 AM CST
001,002: Change Order No. 2
Shoat Rohah Sower Lrna Pipe Musing Project
1350 Langham Beaumont, Taxes 77108
Project Nombor! WU0322.16
Grand 'I'nlal: $8,100.00
For WU0322-18 To-tdox Con Street Rehab Sewer Linn Mlin nursling Pro)ecl
tiivislon 33
Line Item Unit price
Typo
Group 3.0 Consiructlon
Scope of To add an addillonal bid Item for iho contractor to psrform lvm (9) needed point lopelrs to connect to the oxisUng 12' PVG sanitary sewer
Work line that ctosses through a 72` storm drain behvean MH791 and MHz11 an page 4 of the plan shoots. Six (6) additional calendar days
will be oddod to the contract for the completion of tho wark.
Notes
Awarded TO To-MoxConslrudlon,LLC
Ma dbet •Torres
Reason Unforaeon Site Conditions
Code
Days 6
Changed
Atlaotrmonis Street Reltab Project Mtf 701.241 (Moto.pdf
Change Order Summary
original ContraM Sum
669,661.801 Substantial Completion halo
Not Coal by Previous Approved
0.00 HatTlmo Change By previous 0 days
Gus
Cos
Contract Sum Boforo TW& CO
fis9,g61.eD Subslartlfal Completion beroro
Mils CO
Contract sum Changed By This
i
8,100.00;TImo Ohangod ByThls GO adays
Co
Now Ceniracl Sum
697,961.81)1 Now Substantial Completion
pale
A I Change Orders make up 1.371G of
the Odgl0al Contract
Accounting and Status
Accotinling stales
I
Item Id
302
i
vo Number
`FFMA Number
Accounting project Codo
MC019 Custom AccougGrty Field 04
Guatom Acootlnl111q Fioid 85
Custom Accounting Field 06
Cuslem Accounting Field 07
Cusloin Accounting Field 00
Une Items
Account W13SI Uplt Total
Itemil Code soctlon dascrlptlon Quantity UoM prlco Amount ,
3.0 conslructlon
016 GC 10 Polnl Ropalr 2.00 EACH 4,050.00 0,100,00
Contract
Total D,100.00
Grand Total: 8,100.00
Ap))roval Approved
Due: W.Oct-2022
Nam* oritolo
status Actions
1
Cxlomal-00
Approved
Madhol Torros
05.Oct-202205:07 PM CST
2
P(ojocl Manager
Approved
Sohn Pippins
07.Oct-2022 01:20 PM CST
3
Clty Englneor
Approved
Amelia'MoMyy' Villaatool
07.Oct-202205:27 PM CST
4
Dlroclor
Approved
Dart DarlkovAak
10.Oct-2022 00:42 AM CST
6
Admlo
Approved
Dare Woodwfl
10.Oct-2022 00:46 AM CST
Croalod by: Kovin Young on 05-Gc1.2022 Last Modlnod by: Darn Woodruff on 10.0cl-2022
APPROVED BY: ATTESTED BY:
] A"b�oj�
I&rl)..�-)-1 . '
Kenneth R. Williams Date Tina Broussard ate
City Manager City Clerk
(IItYOP WAUMONT
Dill
Jv#FEO, NJ�
pJPr O.rathp Plo:eel
County
,�fnhtbOretrUnf
on
Duuif�
nfsw*nl
cotilrfftl7Ymbfn
OIO#70.1W4}!!.}{
t>AnrR
CIyO#ls m"t
09n1n119fJ
ToFWCotalm9m,11.)
C.O. Noa
I
I1171Atuo aawilatalkIIuwwraipwii,7l4J[ILT%-IfIlaf%I1LPA3A.Im 7
Wall - Mull
ORIOIIALCOIRMOYA1WUIM , 1 11P.667.14
VET FROM PREVIOUS CI W IOE ORDERS:
YOTAE AUOUNt OF 11IIb 0I WIOE OROFM' .1. _..
PERCEIR' OP YIIII CIW 70C ORDER; 0.00FS
T01ALpP.1tCPl#rGWIOE0R0E71T�07,YF: A40
IiE1YfA77TM0iM10V7fif 1 6 08
00MRAOTTWE
011101i"Ootmorr1VE: #tO uUMHd i1
A001ROHAlWaRAOT1111EPfnPAtMOU5CUM ORDERS: Ou11MrtE1 +
AODIIIML0WITMOTTIMEPER YRISVI1102ORM: 0oh rldr�
RMSCOOO11TRAOT111,IE; fluf ff ffi
F
kdu Wrvm gkso"rpvp WI Da64WAWIU14vtU stirks 161 aM4dfm!*�p.1901hD71*ibis Or6Jt!opal{(ArMIcmwditmFNr1)harm"
rn!dt"U64In" *AN,Vd6t If"rv+" 10 putum Nr rnln hvAWJrt Nr oon4.d WrQ47aiVy 46141810hOMI)I CNNIOrL+rsrd Mj(4Aw4CMVb Ot4tn.
A<a;tir c� c#u7r4Mfa WfstilM rAglr+am iMlAirn Oahff fmtCttLeUq NnNr CAVOr 6+d1 r If jtf f frAf f n-iwvAf r,7rmgWj golf P34W #qu0rm41t0lhr C<AWA
lydtnuCtrOsda ruwtu u tylutattr r tlrmanuif cnwlsr PUD rlurilh{roptdlukf ttrf,'
!�i'TED nYt
7/2a(21A2
r
#ItVICY7Rn17Yt
cm tRwrttst
APYROMORYI
6�:� /> L-� a Y Zz
INA000if1 PATI
PRI.Awtowit"m
PWAR[OnYf
joempnosA girl Xti
WATIRMYRA Ots1017Jµtthacll
x1,5 , w zz_
a,umnvrrv�n OMP.
O COToROFPOP UaY7MRe e7ttIp4al00Y
1E IMS
A TennYt
P+ efl : O pAle
tJn<ulul
Contract # 001.004
17-May-2023 03:55 PM CST
001.004: Change Order No. 4
Street Rehab Sewer Line Pipe Bursting Project
1350 Langham Beaumont, Texas 77706
Project Number: WU0322-16
Grand Total: $21,265.00
For 001 Street Rehab Sewer Line Pipe Bursting Project
Division 33
Line Item Unit price
Type
Group 3.0 Construction
Scope of The Contractor will perform Pipe Bursting tasks as noted and in accordance with the details provided in the project contract documents or
Work as directed by the Engineer.
Notes Change Order No. 4 is requested to add additional quantities to four (4) bid items to reflect quantities used in the field.
Awarded To To-Mex Construction LLC
Maribel Torres
Reason Quantity Adjustment
Code
Days 0
Changed
Attachments
Pending Pay Item Street Rehab Project.xlsx
RES 23-132 St. Rehab Sewer Line PB C_04.pdf
Change Order Summary
Original Contract Sum
Net Cost by Previous Approved COs
Contract Sum Before This CO
Contract Sum Changed By This CO
New Contract Sum
All Change Orders make up 5.74% of the Original Contract
Accounting and Status
Accounting Status
589,861.80 Substantial Completion Date
12,600.00 Net Time Change By Previous COs 12 days
602,461.80 Substantial Completion before This CO
21,265.00 Time Changed By This CO 0 days
623,726.80 New Substantial Completion Date
Item Id 389
PO Number 430950 FEMA Number
Accounting Project Code WWC019 Custom Accounting Field 04
Custom Accounting Field 05 Custom Accounting Field 06
Custom Accounting Field 07 Custom Accounting Field 08
Line Items
Item
Account
WBS/
Unit
Total
#
Code
Section
Description
Quantity UoM
Price
Amount
3.0 Construction
003
GC Contract
3
Flexible Pavement Structure Repair (4")
130.00 SY
65.00
8,450.00
006
GC Contract
6
Remove and Replace or Install New Std. Fiberglass Manhole, Up to 8'
2.00 EACH
5,345.00
10,690.00
Depth with All Joints & Connecti
011
GC Contract
11
Obstruction Removal by Excavation, All Sizes, All Depths, With Project
2.00 EACH
425.00
850.00
Manager's Approval
014
GC Contract
14
Pipe Bursting 6" Sewer to 8.625" OD HDPE
30.00 L.F.
42.50
13275.00
Total
215265.00
Approval Approved
Name or Role
1 External -GC
2 Project Manager
3 City Engineer
4 Director
5 Admin
6 Assistant City Manager
Status
Approved
Maribel Torres
25-Apr-2023 02:30 PM CST
Approved
Kevin Young
25-Apr-2023 03:31 PM CST
Approved
Amalia "Molly" Villarreal
28-Apr-2023 03:42 PM CST
Approved
Bart Bartkowiak
28-Apr-2023 03:58 PM CST
Approved
Dara Woodruff
10-May-2023 08:52 AM CST
Approved
June Ellis
10-May-2023 10:50 AM CST
Grand Total: 21,265.00
Due: 17-May-2023
Actions
Name or Role Status Actions
7 City Clerk
Approved
Tina Broussard
10-May-2023 11:02 AM CST
Created by: Kevin Young on 24-Apr-2023 Last Modified by: Tina Broussard on 10-May-2023