HomeMy WebLinkAboutRES 23-044RESOLUTION NO. 23-044
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on June 14, 2022, the City Council of the City of Beaumont, Texas
passed Resolution No. 22-153 awarding a contract in the amount of $3,670,700-.00 to
King Solution Services, inc., of Houston,, Texas, for the City -Wide Pipe Bursting
Contract- Phase I Project; and,
WHEREAS, Change Order No. 1, with no dollar amount, is attached for your
review; and,
WHEREAS, Change Order No. 2, in the amount of $438,825,00, is requested for
the addition of 4,100 LF of pipe bursting of 15" to 16" OD HDPE pipe, approximately
1751F of pipe bursting 6" to 8_.625" OD HDPE pipe, approximately 1,100 LF of open
cut, and 17 manholes along S. 4th Street before the street can be rehabilitated. The
sewer lines and -manholes have reached the lifetime expectancy and are in need of
replacement. An additional sixty (60) days is requested for the completion of the work. If
approved the new contract amount will be $4,109,525.00;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, . _
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute 'Change
Order No. 2, in the amount of $438,825.00 for additional work described above, thereby
increasing the total contract amount to $4,109,525.00 for the City -Wide Pipe Bursting
Contract- Phase I Project; and,
BE IT FURTHER RESOLVED THAT the City -Wide Pipe Bursting Contract -
Phase I Project be and the same is hereby accepted.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 31st day of
January, 2023.
- Mayor Robin Mouton -
RESOLUTION NO.22-153
WHEREAS, the City of Beaumont solicited bids for furnishing all labor, materials,
and equipment for the City Wide Pipe Bursting Contract -Phase I Project; and,
WHEREAS, King Solution Services, LLC, of Houston, Texas, submitted a bid in
the amount of $3,670,700.00; and,
WHEREAS, the City Council is of the opinion that the bid submitted by King
Solution Services, LLC, of Houston, Texas, is the lowest responsible bidder providing
services at the best value to the City and should be accepted;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Council hereby approves the award of a contract to King Solution
Services, LLC, of Houston, Texas, in the amount of $3,670,700.00 for the City Wide
Pipe Bursting Contract -Phase 1 Project; and,
BE IT FURTHER RESOLVED THAT the Interim City Manager be and he is
hereby authorized to execute a contract with King Solution Services, LLC, of Houston,
Texas, for the purposes described herein.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 14th day of
June, 2022
.F F.hfLlC
- Mayor Robin
1/18/23, 3:41 PM
Contract # 001.002
18-Jan-2023 03:40 PM CST
Projectmates Contract
--------------
001.002: CO # 2: Map 13 Addition - 4th Street
CITY WIDE PIPE BURSTING CONTRACT - PHASE 1
1350 Langham Rd Beaumont, Texas 77707
Project Number: WU1022-02
i
Grand Total: $438,825.00
-..............._. .............._.. ............_ _-...._.._.._.._.....__._.:.
For 001 WU1022-02 City Wide Pipe Bursting Contract - Phase I
Division 33
i
Line Item Unit price
Type
Group 3.0 Construction
Scope of Addition of Map 13 on S. 4th Street to the plan set. Map 13 adds approximately 4100 LF of pipe bursting of 15' to 16" OD HDPE pipe,
Work approximately 175 LF of pipe bursting 6" to 8.625" OD HDPE pipe, approximately 1100 LF of open cut, and 17 manholes to S. 4th Street.
Notes Map 13 on S. 4th Street is being added to replace the sewer lines and manholes before the street can be rehabilitated . The sewer lines
and manholes are in need of repair and are recommended for replacement.
Awarded To King Solution Services LLC
Mario Jaimes
27738
Reason Owner Requested
Code
Days 60
Changed
Attachments
CO 2 Plan Set 4th St. Addition (Executed).pdf
i
i
------------- ----------- ---- .------ --- _---- ..-.._----------- --- --- _------ ............_......_...----_.........................-._..........._-- --------------- ---- ------- ---- .------- .------- ._...._--- ------ .---------- .-------
._.-------------- -..-_..........------------- ---_---.---------------
--.-:
Change Order Summary E
i.......... ... .I...... _... -
I Original Contract Sum 3,670,700.00 Substantial Completion Date
I Net Cost by Previous Approved COs 0.00 Net Time Change By Previous Cos 0 days j
_.........--- ---- — ---- ----------- -..._---------------- ...__.._.....------- ---------- ..__... - .._...... __...._...._...-- - - ---- ---------- ------ ---------..._------ ---- ....-.....------- --_.---- ----- --- ---................- •:
Contract Sum Before This CO 3,670,700.00 Substantial Completion before This CO i
Contract Sum Changed By This CO 438,825.001 Time Changed By This CO 60 days
New Contract Sum 4,109,525.001 New Substantial Completion Date
All Change Orders make up 11.95% of the Original Contract
Accounting and Status
-------------
Accounting Status
I
hftps://cityofbeaumont.projectmates.com/Projectmates/C Exhibit "N' aspx?enc=28878DO1 099DB758OF61 C4C8707E682578... 1/3
1/18/23, 3:41 PM
Projectmates Contract
Item Id
340
-- - -- - ----------
PO Number
- - - -- - ---- - ---
430946
-- - -- -- ---- ------ ----------
FEMA Number
Accounting Project Code
i
Custom Accounting Field 04
i Custom Accounting Field 05
Custom Accounting Field 06
...-._..._.... - -
Custom Accounting Field 07
i
_..._..............._...... -......._............._..._..------
Custom Accounting Field 08
.... ....... _.
1
I
i
Line Items
I
i
1 Item Account WBS/
Unit
Total
# Code Section
Description Quantity UoM
Price
Amount
3.0 Construction
005 GC Contract 351
Flexible Pavement Structure Repair (4") 600.00 SY
60.00
36,000.00
015 GC Contract 3301
Remove and Replace or Install New Std. Pre -Cast Concrete Manhole, 2.00 EACH
7,000.00
14,000.00
i
i._...-.............. -- _........... _. _. __.._
Less than 5' Depth, (With All Join
. -- -- ----- .... ._ . -----_.-- ----------- ----- - -- - --- --- - .. _..._... __. ._ . _... --- --- ---- -------
_. ------------ -
i 016 GC Contract 3301
Remove and Replace or Install New Std. Pre -Cast Concrete Manhole, 15.00 EACH
7,200.00
I
108,000.00
5' to 8' Depth (With All Joints &
i
` 019 GC Contract 4020
Pipe Bursting 6"-8" Sewer to 8.625" OD, All Depths 175.00 LF
35.00
6,125.00
022 GC Contract 4020
Pipe Bursting 15" Sewer to 16.0" OD, All Depths 4,100.00 LF
67.00
274,700.00
Total
438,825.00 i
Grand Total: 438,825.00
Approval Approved
Due: 25-Jan-2023
Name or Role
Status Actions i
1
External -GC
Approved
Allan Negrete
18-Jan-2023 02:26 PM CST
2
Project Manager
------------
Approved
John Pippins
I
18-Jan-2023 02:49 PM CST E
3
City Engineer
Approved
Amalia "Molly" Villarreal
18-Jan-2023 03:03 PM CST I
4
Director
Approved
Bart Bartkowiak i
18-Jan-2023 03:35 PM CST
—-------
5
.___ ._ ___.....,....____,.____ __._..___...___._
Admin
._.._.._...,_.._......__...__._..__...,._...____--.- .............._
Approved
Dara Woodruff
i
18-Jan-2023 03:41 PM CST
https://cityofbeaumont.projectmates.com/Projectmates/ContractMgmtlContractPrinterFriendly.aspx?enc=28878D01099DB7580F6l C4C8707E682578... 2/3
1/18/23, 3:41 PM Projectmates Contract
Created by: Kevin Young on 22-Dec-2022 Last Modified by: Dara Woodruff on 18-Jan-2023
APPROVED BY:
Kenneth R. Williams Date
City Manager
ATTESTED BY:
Tina Broussard
City Clerk
Date
https://cityofbeaumont.projectmates.com/Projectmates/ContractMgmtlContractPrinterFriendly.aspx?enc=28878D01099DB7580F61 C4C8707E682578..
Date:
Prgjocl:
Caynty,
plitdcl:
Contract Number.
ownir
Contractor.
No:;
CITY OF BEAUMONT
July 20, 2022
CIIyVilda Plpe Bursting Contract - Phaso 1
JNfewn
Beaumont
BID'NO. WU1022-02
City of Bii iimlihl
King Solution Servlcoe, LLC
1`
ORIGINAL CONTRACT AMOUNT.
S
S.87o,700.00
NET FROM PREVIOUS CHANGE ORDERS.
S
TOTAL AMOUNT OF THIS CHANGEORDER:
S
PERCENT OF THIS CHANGE ORDER:
0.00Y.
TOTAL PERCENT CHANGE ORDER TO DATE:
%0.00%
NEW CONTRACT AMOUNT.
S
3,670,70000
CONTRACTTIME
ORIGINAL CONTRACT TIME.
365 calandardays
ADDITIONAL CONTRACT TIME PER PREVIOUS CHANGE ORDERS:
O calendar days
ADDITIONAL CONTRACT TIME PERTHIS CHANGE ORDER:
0 calendar days
REVISED CONTRACT TIME:
365 calendar drys
CONDITION OF CHANGE:
'Conbsctor acknowledges and iprus Thal Ihs edjustmirits In contract price and eodtrael6mo s6polaled In Nla Change Order rspresents tull eompensaaaa lot W Iqueases
srid doereai4h tho coatof. and thetlme t+4u4ed to perform the snUro work under the contract arid" d jactly ofIndliepay Flom NH Clunpc order and ill prWous Change Ciders.
Acceptance of IAb tYshar con•ritutea an agu+minl between Omar and Corib+ctor IhB ltu Change Older roptisint6'en all Industie, mutually ayiaed upon sojustment to the ContiacL
and that ConVadorvAl m6 all rlyhu to pia ra cidm on Udi Chonpo Order odor did properly �xeculed7
ACCEPTED BY:
/VIA^
� 20 2022
KING BO 1101 RVICES;LLO-REP - DATE
PREPARED BY:
4OHN PIPPINS Ill. - DATE
WATEROTILU IEs SIONMANAOE1t
REVIEWED BY:
REMMEWE Y
- DATE
TDARTKOYAA, DATE
A ALIA L
CITY CNOINEER
DIRECTOR OF PUBLIC WORKS 6 TECHNOLOGY
- -
SERVICES
APPROVED BY.
ATTESTED Ell:
I r
Cx BOONES",
INTERIM CRYMANAGERA
;',•,
-7•as5-
RESOLUTION NO..23-045
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute the renewal -
of an annual Maintenance Agreement in the amount of $171,200.40 with Azteca
Systems, LLC, of Sandy, Utah, the sole source having exclusive rights to modify and
maintain the Cityworks software used by.several City departments.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551...
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 31st day of
January, 2023.
Af
C� ;�� �% i1/✓
Mayor Robin Mouton -
PnojeomateuConmsm -
Contract #OO1.0O2
1a-Jan-20000awoPwCST
onn'vvIDEnPEounoTIN000mTxAoT-PHAos(
1mmLmngxamRdBeaumont, Texua77ru7
Project Number: WU 1022-02
' --' --------'----
Grand Total: $438,825.00
For 001 WU1022-02 City Wide Pipe Bursting Contract - Phase I
' Division oo
-'----------------'---'---------`----'------------'----'--`
� Line Item Unit price
`�p
/ o
' omun u000nom/mmn
Scope of Addition of Map 1uona4thStreet mthe plan set. Map 1uadds approximatelyw00 LF of pipe bursting of 15"m16" OD*DPE pipe,
Work mppmmmathly 1nnu=nrpipe bursting u^maaus oo*opEpipe, approximately 11uou=mopen cut, and 17manholes mo.4mStreet.
� - .-. ._..-..... ......---_...- .-.-.. -_.....-.' - --......___-._' .........
..
-_
' Notes Map 1oonS.hStreet Is being added re
place th
e lines and manholes before the street can borehabilitated .The sewer lines
�
and manholes are mneed orrepair and are recommended for mplaonmem�
} --'----- --------' - ' --- ----------- --- --- - ----'-- -----------'------'-'---''
' Awarded To King Solution Services Luz
� MamoJaimou
27738
Reason Owner Requested
ouue
uuya oo
Changed
Attachments CO 2 Plan Set 4th St. Addition (Executed).pdf
--_ '- - .. -- -_ .---'-_'----.' --_-- .—_--.---._
___
Change Order Summary
Original Contract Sum 3,670,700.00 Substantial Completion Date
Not Cost by Previous Approved COs 0.00 Net Time Change By Previous COs 0 days
Contract Sum Before This CO 3,670,700.00 Substantial Completion before This CO
Contract Sum Changed By This CO 438,825.00 Time Changed By This CO 60 days
Now Contract Sum 4,109,525.00 New Substantial Completion Date
All Change Orders make up 11.951% of the Original Contract
Accounting and Status
Accounting Status
" 0eeDe7580Fe1 1/3
1/18/23o*141 Pm .
FnNeomatesoonurao
Item Id
340
PO Number
430946
FEMA Number
Accountino Project Code
Custom Accounting Field 04
Custom Accounting Field 05
Custom Accounting Field 06
I Custom Accounting Field 07
Custom Accounting Field 08
Line Items
'----
Item Account W13S/
Unit
Total
# Code Section
Description Quantity UoM
Price
Amount
3.0 Construction
015 GO Contract 3301
Remove and Replace or Instal(New Std. Pre -Cast Concrete Manhole, 2,00 EACH
7,000-00
14,000.00
Less than 5' Depth, (With Alf Join
016 GO Contract 3301
Remove and Replace or Install New Std. Pre -Cast Concrete Manhole,
51 to 8' Depth (With All Joints &
Total
438*825.00
Grand Total-,,
438,825.00
Approval Approved
oue 25-Jun-2023
Name or Role
Status Actions
I
External -GC
Approved
Allan Negrete
18-Jan-2023 02:26 PM CST
2
Project Manager
Approved
John Pippins
3
City Engineer
Approved
Amalia "Molly" Villarreal
18-Jan-2023 03:03 PM CST
4
Director
Approved
Bart Bartkowlak
18-Jan-2023 0135 PM CST
Dara Woodruff
18-Jan-2023 03:41 PM CST
1/18/23l 3:41 PM Projectmates Contract
Created by: Kevin Young on 22-Dec-2022 Last, Modified by: Dara Woodruff on 18-Jan-20,23
I Am VIUNJ -2- It W-A!, 9 H low] A I
Kenneth R. Williams
City Manager
r3
Date Tina Broussard Date
City Clerl<
hittps:llcityofbeaumont.projectmates.com/Projectmates/`ContractMgmtlContractPrinterFriendly.aispx?enc=28878DOI 099DB758OF61 C4C8707E682578..... 3/3