HomeMy WebLinkAboutRES 23-040RESOLUTION NO. 23-040
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
WHEREAS, on December 12, 2022, the City Council of the City of Beaumont,
Texas passed Resolution No. 22-339 awarding an emergency contract in the amount of
$126,950.00 to To-Mex Construction, LLC, of Houston, Texas, for the Calder Place from
Wheat Drive to Brentwood Drive Emergency Repair Project; and,
WHEREAS, Change Order No. 1, in the amount of $5,000.00, is attached for-:
your review; and,
WHEREAS, Change Order No. 2, in the amount of $58,200.00, is requested to
add additional work to directionally bore and replace approximately 150 linear feet of 8-
inch sanitary sewer line. The additional work is required.to correct:the grade of the line
that has droppedapproximately two (2) feet and has caused a reverse flow of the sewer
line. An additional forty (40) days are requested for the completion of the work. If
approved, the,new contract amount will be'$190,150.00;
NOW, THEREFORE, BE IT RESOLVED BY THE.
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are
hereby, in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 2, in the amount of $68,200.00 for additional work described above, thereby
increasing the total contract amount to $190,150.00 for the Calder Place from Wheat
Drive to Brentwood Drive Emergency Repair Project; and,
BE IT FURTHER RESOLVED THAT the Calder Place from Wheat Drive to
Brentwood Drive Emergency Repair Project be and the same is hereby accepted.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 31st day of
January, 2023
q4:4� zAam -
Mayor Robin Mouton -
RESOLUTION NO.22-339
BE IT RESOLVED BY THE CITY COUNCIL OF THE
-CITY OF BEAUMONT:
WHEREAS, on November 8, 2022, the City was made aware that a 1,350-foot
section of the six (6) inch sanitary sewer line in Calder Place from Wheat Drive to
Brentwood Drive has multiple failures with parts causing complete.back up of two (2)
streets; and,
NOW, THEREFORE, BE 1T RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute an
emergency contract with To-Mex: Construction, LLC, of Houston, Texas in the amount of
$126,950.00 to complete repairs on the sewer main. The contract is substantially in the
form attached hereto as Exhibit "A" and made a part hereof for all purposes.
The meeting at which this resolution.was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 12th
day of. December, 2022.Aw
_
Mayor Robin Mouton -
i� � "s
1/18123, 3:59 PM
Projectmates Contract
Contract # 001.002
18-Jan-2023 03:59 PM CST
001.002: Change Order No. 2
For 001 Calder Place Emergency Pipe Bursting
Division 33
Line Item Lump sum
Type
Group 3.0 Construction
CALDER PLACE EMERGENCY PiPE BURSTING
1350 Langham Rd Beaumont, Texas 77707
Project Number. PO - 432036
Grand Total: $58,200.00
Scope of To add additional work to directionally bore and replace approximately 150 LF section of 8-inch sanitary sewer line between manholes
Work 436 and 434 on the Calder Place Emergency Pipe Bursting Plan Sheets.
Notes This additional work is required to correct the grade of the line that has dropped approximately 2 VF and has caused a reverse flow of the
sewer line.
Awarded To To-Mex Construction LLC
Maribel Torres
Reason Unforseen Site Conditions
Code
Days 40
Changed
Attachments Calder Emergency Job CO 2 Quote.pdf
Calder Place Emergency Pipe Bursting Plans (Executed).pdf
Change Order Summary
Original Contract Sum
126,950.00 j Substantial Completion Date
Net Cost by Previous Approved Cos
5,000.00 I Net Time Change By Previous COs 7 days
Contract Sum Before This CO
131,950.00 I Substantial Completion before This CO
Contract Sum Changed By This CO
58,200.00 Time Changed By This CO 40 days
New Contract Sum
190,150.00 ! New Substantial Completion Date
All Change Orders make up 49.78% of the Original Contract
Accounting and Status
Accounting Status
httpsl/cityofbesumont.projectmates.com/Projectmates/ContractMgmtfContractPrinterFriendl ry_.aspx7enc=28B78D01099DB7580F6lC4C8707E682578... 1/2
Exhibit "A„
1118123, 3:59 PM Projectmates Contract
Item Id 343
PO Number 432036 i FEMANumber
Accounting Project Code Custom Accounting Field 04
Custom Accounting Field 05 '!Custom Accounting Field 06
Custom Accounting Field 07 .;Custom Accounting Field 08
Line Items
Item #
Account Code
WBSI Section
Description
Change Order No. 2
004
GC CONTRACT
004
Directionally bore and Install approximately 150 LF of 8.625" HDPE Sewer Line
005
GC CONTRACT
005
Point Repair Between MH 437-436
006
GC CONTRACT
006
Well Pointing I Dewatering System
007
GC CONTRACT
007
Install New Manhole - MH 794A
Total
Approval Approved
Name or Role
Status
1 External -GC
Approved
Maribel Torres
18-Jan-202311:16 AM CST
2 Project Manager
Approved
John Pippins
18-Jan-2023 01:24 PM CST
3 City Engineer
Approved
Amalie "Molly" Villarreal
18-Jan-2023 03:04 PM CST
4 Director
Approved
Bart Bartkowiak
18-Jan-2023 03:36 PM CST
5 Admin
Approved
Dare Woodruff
18-Jan-2023 03:59 PM CST
Created by: Kevin Young on 18-Jan-2023
Last Modified by: Dara Woodruff on 18-Jan-2023
Total Amount
33,000.00
4,200.00
12,000.00
9,000.00
583200.00
Grand Total: 58,200.00
Due: 25-Jan-2023
Actions
,PPROVED BY: ATTESTED BY:
;enneth R. Williams Date Tina Broussard Date
Ity Manager City Clerk
Contract # 001.001
18-Jan-2023 09:58 AM CST
001.001: CHANGE ORDER NO. 1
CALDER PLACE EMERGENCY PIPE BURSTING
1350 Langham Rd Beaumont, Texas 77707
Project Number: PO - 432036
Grand Total: $5,000.00
For 001 Calder Place Emergency Pipe Bursting
Division 33
Line Item Lump sum
Type
Group 3.0 Construction
Scope of To Mobilize and CCTV approximately 385 LF of sanitary sewer main between manholes 436 and 434 to determine where the elevation of
Work the sewer line begins to drop.
Notes
Awarded To To-Mex Construction LLC
Maribel Torres
Reason Owner Requested
Code
Days 7
Changed
Attachments
Quote for CCTV from MH436 - MH434.pdf
Change Order Summary
Original Contract Sum
Net Cost by Previous Approved COs
Contract Sum Before This CO
Contract Sum Changed By This CO
New Contract Sum
All Change Orders make up 3.94% of the Original Contract
Accounting and Status
126,950.00 I Substantial Completion Date
0.00 ji Net Time Change By Previous COs
126,950.00 I Substantial Completion before This CO
5,000.00 Time Changed By This CO
131,950.00 ; New Substantial Completion Date
0 days
7 days
Accounting Status
Item Id
PO Number
Accounting Project Code
Custom Accounting Field 05
Custom Accounting Field 07
341
432036 ; FEMANumber
!Custom Accounting Field 04
I
! Custom Accounting Field 06
i Custom Accounting Field 08 -
Line Items
Item # Account Code WBS1 Section Description
Contract Items
002 GC CONTRACT 002
003 GC CONTRACT 003
Total
Approval Approved
Name or Role
1 External -GC
2 Project Manager
3 City Engineer
4 Director
5 Admin
Change Order No.1 Mobilization
CCTV approximately 384 LF between MH436 to MH434
Status
Approved
Madbel Torres
18-Jan-2023 09:26 AM CST
Approved
Kevin Young.
18-Jan-2023 09:45 AM CST
Approved
Amalia "Molly" Villarreal
18-Jan-2023 09:61 AM CST
Approved
Bart Bartkowiak
18-Jan-2023 09:67 AM CST
Approved
Dara Woodruff
18-Jan-2023 09:58 AM CST
Total Amount
3,500.00
1,500.00
5,000.00
Grand Total: 5,000.00
Due: 25-Jan-2023
Actions
Created by: Kevin Young on 04-Jan-2023 Last Modified by: Dara Woodruff on. 18-Jan-2023.
APPROVED BY: STFD
--11 R, V I. (J"y I
3
Kenneth R. Williams Date Tina Broussard Date
City Manager City Clerk