HomeMy WebLinkAboutRES 22-282RESOLUTION NO. 22-282
BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF BEAUMONT:
WHEREAS, on December 15, 2020, by Resolution 20-279, City Council awards
a contract to BDS Contractors, LLC d/b/a MK Contractors, of Vidor, Texas in the
amount of $721,615.00, for the Primer Street Lift Station Repairs Contract Project; and,
WHEREAS, Change Order Nos. 1-4, in the amount of $165,201.00, as shown in
Exhibit "A," attached hereto; and,
WHEREAS, Change Order No. 5 is required in the amount of $10,148.00, to add
a final bid item for reimbursement for continuous cleaning and back washing of the dry -
pit pumps due to excessive solids buildup. A total of thirty (30) calendar days are
requested to be added to the contract time to reflect the additional time used to clear the
solids from the wet well. If approved, the addition would result in a final contract amount
of $896,964.00; and,
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are
hereby, in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 5, in the amount of $10,148.00 for additional work described above thereby
increasing the total contract amount to $896,964.00 for the Primer Lift Station Repairs
Contract Project; and,
BE IT FURTHER RESOLVED THAT the Primer Lift Station Repairs Contract
Project; be and the same is hereby accepted; and,
BE IT ALSO RESOLVED THAT the City Manager is hereby authorized to make
final payment in the amount of $22,840.34 to the Citywide Ditching Program Phase I.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 25th day of
October, 2022.
- Mayor Robin Mouton -
APPROVAL OF CONTRACT CHANGE
CHANGE ORDER No. Five (5) & Final
DATE: October 13, 2024
PROJECT: City of Beaumont, Texas
Lift Station & WWTP Repairs
Tropical Storm Harvey
Primer Street lift Station
Bid No. WU1021-01 / FEMA 048352
OWNER: City of Beaumont, Texas
801 Main Street
Beaumont, Texas 77704
CONTRACTOR: MK Constructors
i 2485 North Street
Vidor, Texas 77662
TO THE OWNER: Approval of the following contract change is requested.
REASON FOR CHANGE: To provide for continuous cleaning of the dry -pit pumps after the pump startup due to overwhelming solids
accumulation In the wet well. This Change Order Is not eligible for FEMA Reimbursement
ORIGINAL CONTRACT AMOUNT: $ 721,615.00
REVISED CONTRACT AMOUNT PER PREVIOUS CHANGE ORDERS $ 886.816.00
THIS CHANGE ORDER
to Description
13 Provide for continuous cleaning of the dry-plt pumps after pump startup due to $ 10,148.00
overwhelming solids accumulation In the wet well, ADD iLS @ $10,148.00/LS
TOTAL AMOUNT OF THIS CHANGE ORDER: $ 10,148,00
TOTAL REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER: $ 896,964.00
PERCENT OF THIS CHANGE ORDER 1.41%
TOTAL PERCENT CHANGE ORDER TO DATE 24.30%
CONTRACTTIME
Original Contract Time: 180 calendardays
Additional Contract Time per Previous Change Orders 379 calendar days
Additional Contract Time per this Change Orders 30 calendar days
Revised Contract Time 589 calendar days
CONDITION OF CHANGE:
"Contractor acknowledges and agrees_ that the adjustments In contract:prlce and contract time stipulated In this Change.0rder represents full
compensation for all Increases and decreases In the cost of, and the time required to perform the entire -work under the Contract arising
directly or indirectly from this Change Order and all previous Change Orders. Acceptance of this waiver constitutes an agreement between
Owner and Contractor that the Change Order represents an all Inclusive, mutually agreed upon adjustment to the Contract, and that
Contractor will waive all rlghts.to file a claim on this Change order after it Is properly exe
cuted."
Accepted by Reviewed by:
MK Constructors Amaila Villarreal, P.E. Bart eartkowiak
Contractor City Engineer Director of Public Works
and Technology Services
Date: �� ��S'��.�. Date:' 01 I —(� { lcoepa_ ' Dale:
Reco m d b / -y" Approved by: Attested by;
Schaumbur & Polk, Inc. _ Kenneth R. Williams Tina Broussard
Engineer %� j/:� City Manager City Clerk
Date: / , !� Date: Dale:
EXHIBIT "A"
APPROVAL OF CONTRACT CHANGE
CHANGE ORDER No. Four(4)
DATES April 11, 2022
PROJECT: City of Beaumont, Texas
Lift Station & WWTP Repairs
Tropical Storm Harvey
Primer Street Lift Station
Bid No. WU1021-01 / FEMA 1148352
OWNER: City of Beaumont, Texas
801 Main Street
Beaumont, Texas 77704
CONTRACTOR: MK Constructors
2485 North Street
Vidor, Texas 77662
TO THE OWNER: Approval of the following contract change Is requested.
REASON FOR CHANGE: To provide additional contract time to allow for the delays in matedal/equipment delivery due to supply chain
complications as a result of the C.OVID-19 pandemic:
ORIGINAL C014TRACT AMOUNT:
S 711,615,00
REVISED CONTRACT AMOUNT PER PREVIOUS CHANGE ORDERS
S 886,816.00
THIS CHANGE ORDER
TOTAL AMOUNT OF THIS CHANGE ORDER:
$ -
TOTAL REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER:
S 886.816.00
PERCENT OF THIS CHANGE ORDER
- 0.00%
TOTAL PERCENT CHANGE ORDER TO DATE
22.89%
CONTRACTTIME
Original Contract Time:
180 calendar days
Additional ContractTime per Previous Change Orders
152 calendar days
Additional Contract Time par this Change Orders
227 calendar days
Revised Contract Time
559 calendar days
CONDITION OF CHANGE:
"Contractor acknowledges and agrees that the adjustments In contract price and contract time stipulated In this Change Order represents full
compensation for all Increases and decreases In the cost or, and the time required to perform the entire work under the Contract arising
directly or Indirectly from this Change Order and all previous Change Orders. Acceptance of this waiver constitutes an agreement between
Owner and Contractor that the Change Order represents an all Inclusive, mutually agreed upon adjustment to the Contract, and that
Contractor will waive all rights to f Ile a claim on this Change Order after it (s properly executed."
Accepted by �q.R•ev_iew\ed by: a
A , R le W y;
K Constructors Amalla Villarreal, P.E. B 8artkowi
Contractor City Engineer Director of Public Works
!? `�/ _^ and Technology Services
Dateq ' L2 Date: I D�C�(�� Date: /u-�i�i
Reco e y . Approved by: A sted by: "
V v /2--fitI
AAA
Schaumburg rPolk, Inc. Chris Boone rfa rous and
Engineer Interim City Manage ry % CityClerk
Date: / ?' Date: LG. Date: •
APPROVAL OF CONTRACT CHANGE
CHANGE ORDERNo. Three (a)
DATE: January20, 2022
PROJECT: • Cltyef Beaumont, Texas
Lift Station & VVWTP Repairs
tropicalStortn Harvey
Primer Street Lift Station
Did No; WU1021•01 / FEMA 114052
OWNER: City of Beaumont, Texas
801 Main Street
Beaumont, Texas 77704
CONTRACTOR: MIN Constructors
2405 North Street
Vldor, Texas 77662
TO THE OWNER: Approval of the following contractchange Is requested.
Reason for Change: To ft rnIsh all labor, materials and equipment to Install one (1)18"x12" tapping sleeve and valve with additional fittings
for bypass discharge (12" tap Included), temporary relocation of ongoing bypass discharge, additional shoring for the existing manhole, Water
line and 'ditch for the valves Installation, road restoration and traffic control for road closure.
ORIGINAL CONTRACT AMOUNT: S 721.615.00
REVISED CONTRACTAMOUNT.PER PREVIOUS CHANGE ORDERS 3 827.591.00
THIS CHANGE ORDER
Item Description
12 Furnish all labor, materials and equipment to Install one (1)18" x12" tapping sleeve and valve with $ 59,225.00
additional fittings for bypass discharge (12" tap Included), temporary relocation of ongoing bypass
discharge, additional shoring for the existing manhole, water line and ditch for the valves Installation,
road restoration and traffic control for road closure. ADD $59,225,00/LUMP SUM
TOTALAMOUNT OFTHIS CHANGE ORDER: $ 59,225.00
TOTAL REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER: 886,616.00
PERCENT OF THIS CHANGE ORDER 8.21%
TOTAL PERCENT CHANGE ORDER TO DATE 22.89%
CONTRACTTIME
OriginalContractTlme: 180 calendar days
Additional Contract Time per Previous Change Orders 112 calendat days
Additional Contract Time per this Change Orders 40 calendar days.
Revised Contract Time 332 calendar days
CONDITION OF CHANGE;
"Contractor acknowledges and agrees that the adjustments.ln contract price and contract time stipulated In this Change Order:represents full
compensatlop for all Increases and decreases In the cost of, and the time required to perform the entire work under the Contract arising
directly or Indirectly from this Change. Order and all ,prevlous Change Orders. Acceptance of this waiver constitutes an egreement between
Owner and Contractor that the Change order represents an all Inclusive, mutually agreed upondjustment to the Contract, and that
Contractor will waive allAghts to file a claim on this Change Order after it Is properly executed."
Accepted by; Reviewed by: Revle by:
MI( Constructors Amalla Villarreal, P.E. D Ba tkowlak
Contractor City Engineer Director of Public Works
rr and Technology services
Date �� Date: :J a 0 Date: 12�L
Approved by: j
Kyle Hayes r`
City Manager J
Date: `� Y• 2 1
Att ted by: U�104
Tina Broussard U
city Clerk 'J
Date: CQ . —( a a,
APPROVALOF CONTRACT CHANGE
CHANGE ORDER No, Two (2)
DATE: December 1, 2021
FROM ICTt city of Beaumont, Texas
Lift Station & WWTP Repairs
Tropical Storm Harvey
PrImerWeet LiftStatlon
Old No, W61621•01 I FEMA 1148352
OWNER, City of Beaumont, Texas
801 Meln Street
Beaumont, Texas 77704
CONTRACTOR, MR Constructors
2485 North Street
Vidoq Texas 77662
TOTHE OWNER, Approval,of the following contractchange.ls requested:
Reason for Change: -To furnish all labor, materials and equlpmentto Install a 20" AVTvalve on the 20" force main to Isolate the force main
from the drywell In order to remove and replace the existing, valves, fittings and piping.
ORIGINAL CONTRACT AMOUNT. 721,615.00
REVISED CONTRACT AMOUNT PER CHANGE ORDERNo.1 S 739,971.00
THIS CHANGE ORDER
to Desc tlo
11 Furnish all labor; materials and equipment to install a 20" AWvalve on the 20" force main to Isolate the $ 87,620A0
force main from the drywall In order to remove and replace the existing valves, fittings and piping,. ADD
$87,620,OOILS
TOTAL AMOUNT OF THIS CHANGE ORDERI $ 87,620.0.0
TOTAL, REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 827,591.00
PERCENT OF THIS CHANGE ORDER 12,14%
TOTAL PERCENT CHANGE ORDER TO DATE 1 41,69Ya
CONTRACT TIME
Original ContraetTime: 180 calendardays
:Additional ContractTIme per Previous Change Orders 28 calendar days ,
Additional ContractTlme per this Change Orders 84 calendardays
Revised Contract Time 292 calendar days
CONDITION OF CHANGES
"contractor acknowledges and agrees that the adjustments In contract price and contract time stipulated In this change Order represents full
compensation for all Increases and decreases In the cost of, and the time required to perform. the entire work under the Contract arising
directly or Indirectly from'this change older and -all previous Change Orders. Acceptance of this waiver constitutes an agreement between `
Owner and Contractor .titet.the Change Order represents an all Inclusive, mutually agreed upon adjustment to the Contract, and that
contractor will waive all rights to file a claim on this change order after It Is properly executed."
Acce ted b Reviewed by: RevZz -
MR Constructors Amalla Villarreal, P.E. M gartkow)a vm�
contractor City Engineer Director of Public Works
l and Technology Services)
Datei Dates 1_ Dalai
co man Approved by: tested. by: RRAll I
&.s/
Schaumbur7/�
k, Inc. Kyle Hayes Ina Broussard QI
Englneer City Manager j G Cityclerk ( II ..a
Date, . �/ Dates l r O a Dale, l tg •O • � �tl� �
APPROVAL OF CONTRACT CHANGE
CHANGE ORDER No, One (11
DATE: October 15, 2021
PROJECT: City of Beaumont, Texas
Lift Station &.WWTP Repalrs
Tropical Storm Harvey
PrlmerStreet LlftStation
old No. WU1021.01 / FEMA 1148352
OWNER: City of Beaumont, Texas
601 Main Street
Beaumont, Texes77704
CONTRACTOR: MK Constructors
2485 North Street
Vldor, Texas 77662
TO THE OWNER: Approval of the following contract change Is requested.
Reason for Change: To remove and replace the existing deteriorated ductile Iron discharge piping and fittings for the submersible pump In
the secondary wet well. This change order Is not ellglbla for FEMA Reimbursement
ORIGINAL CONTRACT AMOUNTI
$ 721,615.00
THIS CHANGE ORDER
Lem Description
9 Fumish all labor, materials and equipment to remove and replace the existing e" discharge piping and $
fittings for the submersible pump In the secondary wet well, Including base elbow, ductile Iron piping,
,coupling, and 90 degree hand; ADD $18,356.00/lump sum
TOTAL AMOUNT OF THIS CHANGE ORDER:
TOTAL REVISED CONTRACTAMOUNT INCLUDING THIS CHANGE ORDERI
18,956.00
$ 18,856.00
$ 739,972,00
CONTRACT TIME
Original ContrectTime: 180 calendardays
Time requested for material delivery end Installation of the new 8" discharge piping and base elbow, 28 calendar days
Revised contract Time per this change order 20B calendardeys
CONDITION OF CHANGE:
"Contractor acknowledges and agrees that the adjustments In contract price end contract time stipulated In this Change order represents full
compensation for all Increases and decreases In the cost of, and the time required to perform the entire work under the contract arlsing
.directly or Indirectly from this Change order and all previous Change Orders. Acceptance of this waiver constitutes an agreement between
owner and contractor that the Change Order represents an all Inclusive, mutually agreed upon adjustment to the Contract, and that
V—f— nr Will wniva all rlahta to flla a rinlm nn this Chanaa Ordar after it Is nrnnariv executed."
Acc Ced by: Revieweed by:
r \ l ww �14A47►� �rV`1`�iM1/►lL7LW�l
MK Constructors Amalia Villareal, P.E.
Contractor City Engineer
Date!&&t � Date:
R omm nde y:
Scilaurr) erg &Polk; Inc,
Enginee
Date:
Approved by: L f
Kyle Hayes t
city Manager /) I
Date: / / 1 Z
2iy�A
:
eartkowlak
Director of Public Works
and Technology Services
Datel b-20 ` 1 0 i
byl - n % . .
City Clerk J
Date: ' ( / .1 - ;?
I
CHANGE ORDER No, Five (5) & Final
•b:
PROJECTi City of Beaumont, Texas
Lift Station & WW,TP Repairs
Tropical Storm Harvey
Primer Street Lift Station
Bid No, WU'1021-0, / FEMA 11403S2
oW Pnr City of Beaumont, Texas
001 Main Street
Beaumont, Texas 77,704
CONTRACTOR MK Constructors
2485 North Street
V"Idor, Texas 7766l2
TO THE OWN'EM Approval of the following contrast change Is requested,
ROASON FOR CHANGE To provide for continuous cleaning of the dry-plt pumps after the pump startup due to overwhelming, solids
e=1rrru1e1:10rr In the wet well, This Change Bader Is not eligible for PEMA Reimbursement
ORIGINAL CONTRACT AMOUNT,
RCVISC CONTRACT AMOUNT PER PREVIOUS CHANGE ORDERS
THIS CHANGE ODD ,
»
r e .escr
S Provide for continuous cleaning of the dry-plt pumps after pump startup due to
10, »» 8o0
overwhelming solids accumulation In the wet well, AbC ILS @ $101148,00, LS
» TOTAL. AMOUNT OP THIS CHANGE ORDEM
$ 10114l8�oC
TOTAL RIEVI ED C'ONT ACT' AMOI UI 'T INCLUDING THIS CHANGE CADP t
896,964.00
PERCENT OF THIS CHANGE ORDER
1,41
TOTAL PERCENT CHANGE ORDER TO DATE
24,90
CONTRACT TIMIE
c rIgInal Contract Times#
180 calendar clays
Additional Contract Time per Previous Change Orders
379 calendar days
Additional Contract Time per this Change orders
30 calendar days
Revised Contract Time
509 calendar days
Reco -0i d b% " Aj .01 r od hv
V
Schaumbluml Polko Inc, Kenneth
Engineer r-j Cit MID
y njXr /'l I
Daliro M O
este by;
01AU4A UQ4W
pow 9=
er� Broussard
City Cler c
Dolor
i