HomeMy WebLinkAboutRES 22-256RESOLUTION NO.22-256
BE 1T RESOLVED BY THE CITY COUNCIL OF THE
CITY OF BEAUMONT:
WHEREAS, on December 14, 2021, the City Council passed Resolution No. 21-
336 awarding a contract in the amount of $370,000.00 to Pro -Pipe, Inc., of Irvine,
California, for the Sewer Evaluation Work Order Contract — Phase IV (Rebid) Project
and,
WHEREAS, the City Manager executed Change Order Nos. 1-4, in the amount of
$19,185.00, to adjust the estimated quantities to reflect the actual quantities used in the
completion of the project, thereby increasing the contract amount to $389,185.00;
and,
WHEREAS, Change Order No. 5, in the amount of $30,072.25, is required to add
seven (7) additional items to clean and televise storm sewer lines and one (1) additional
item to clean and televise a 26-inch sanitary sewer pipe that are included on Work order
No. 3.; no additional days will be added to the contract for additional work. If approved,
Change Order No. 5 would result in a new contract amount of $419,257.25 and,
WHEREAS, the project has been inspected by the Engineering Division and
found to be complete in accordance with the provisions and terms set forth in the
contract;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 5, in the amount of $30,072.25, to add seven (7) additional items to clean and
televise storm sewer lines and one (1) additional item to clean and televise a 26-inch
sanitary sewer pipe that are included on Work order No. 3.; no additional days will be
added to the contract for additional work. Change Order No. 5 would result in a new
contract amount of $419,257.25.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 11th day of
October, 2022.
Mayor Robin Mouton
Contract - 001.005
04-Oct-2022 11:48 AM CST
SEWER EVALUATION WORK ORDER CONTRACT - PHASE IV (REBID)
1350 Langham Rd Beaumont, Texas 77707
Project Number: WU1022-01
001.005: Change Order No. 5
Grand Total: $30,072.25
For 001 REBID - Sewer Evaluation Work Order Contract - Phase IV
Division 33
Line stern Unit price
Type
Group 3.0 Construction
Scope of Change Order No.5 is to add tile Work Order#3 Plans and to add seven (7) additional items to Clean and CCTV Storm Sewer and one
Work (1) additional Item to Clean and CCTV 26-inch Sanitary Sewer Pipe.
Notes
Awarded To Pro -Pipe, Inc.
Ryan Gaskle
28669
Reason Owner Requested
Code
Days 0
Changed
Attachments
Sewer Eval Phase IV WO 3 (Executed).pdf
Pro -Pipe Quote for 26-inch Sanitary Sewer Clean & CCTV_09... 022.pdf
Pro -Pipe Quote for Storm Sewer Addition_08,31.2022.pdf
Change Order Summary
Original Contract Sum 370,000.00
Net Cost by Previous Approved COs 19,185,00
Contract Sum Before This CO 389,185.00
Contract Sum Changed By This CO 30,072,25
New Contract Sum 419,257.25
All Change Orders make up 13.31% of the Original Contract
Accounting and Status
Substantial Completion Date 14-Feb-2023
Net Thne Change By Previous Cos 5 days
Substantial Completion before This CO 19-Feb-2023
Time Changed By This CO 0 days
New Substantial Completion Date 19-Feb-2023
EXHIBIT "A°
Accounting Status
Item id
298 i
PO Number
422428 FEMA Number
Accounting Project
Code
WWC019 Custom Accounting Field 04
Custom Accounting Field 05
Custom Accounting Field 06
Custom Accounting Field 07
Custom Accounting Field 08
Line Items
Item Account
Wasi
Unit
Total
# Code
Section
Description
quantity
UoM
Price
Amount
3.0 Construction
015 GC Contract
2558
CCTV Inspection and Cleaning - 12" Storm Sewer Main (WO #3 -
2,225.00
LF
2.54
5,651.50
Maps 1 & 2)
016 GC Contract
2558
CCTV Inspection and Cleaning - 15" Storm Sewer Main (WO 43 - Map
525.00
LF
5.94
3,118.50
1)
017 GC Contract
2558
CCTV Inspection and Cleaning - 18" Storm Sewer Main (WO #3 - Map
375.00
LF
8.59
3,221.25
1)
018 GG Contract
2558
CCTV Inspection and Cleaning -18" Storm Sewer Main (WO #3 - Map
1,950.00
LF
4.14
8,073.00
2)
019 GC Contract
2558
CCTV Inspection and Cleaning - 27" Storm Sewer Main (WO #3 - Map
250.00
LF
12.89
3,222.50
2)
020 GC Contract
2558
Lateral Launch Inspection - Storm Sewer (WO 43 - Map 1)
350.00
LF
6.53
2,285.50
021 GC Contract
2558
Lateral Launch Inspection - Storm Sewer (WO #3 - Map 2)
1,000.00
LF
2.25
2,250,00
022 GC Contract
2558
Cleaning and CCTV of 26-inch Sanitary Sewer
600.00
LF
4,50
2,250.00
Total
30,072.26
Grand Total: 30,072,26
Approval Approved
Due. 6-Oct-2022
Name or Role
Status Actions
1 External -GC
Approved
Ryan Gaskie
28-Sep-2022 02:24 PM CST
2 Project Manager
Approved
Jahn Pippins
28-Sep-2022 05:26 PM CST
3 City Engineer
Approved
Amalia "Molly" Villarreal
29-Sep-2022 09:08 AM CST
Name or Role Status
a Director Approved
Bart Bartkowiak
29-Sep-2022 09:10 AM CST
5 Admin Approved
Dara Woodruff
29-Sep-2022 09:29 AM CST
APPROVED BY: ATTESTED BY:
Actions
Kenneth R. Williams Date Tina Broussard Date
City Manager City Clerk
Contract - 001.005
04-Oct-2022 11:48 AM CST
001.005: Change order No. 5
SEWER EVALUATION WORK ORDER CONTRACT - PHASE IV (REBID)
1350 Langharn Rd Beaumont, Texas 77707
Project Number: WU 1022-01
Grand Total: $30,072.25
For 001 REBID - Sewer Evaluation Work Order Contract - Phase IV
Division 33
Line item Unit price
Type
Group 3.0 Construction
Scope of Change order No.5 is to add the Work order #3 Plans and to add seven (7) additional items to Clean and CCTV Storm Sewer and one
Work (1) additional item to Clean and CCTV 26-inch Sanitary Sewer Pipe.
Notes
Awarded To Pro -Pipe, Inc.
Ryan Gaskie
28669
Reason Owner Requested
Code
Days 0
Changed
Attachments
Sewer Eval Phase IV_WO 3 (Executed).pdf
Pro -Pipe Quote for 26-inch Sanitary Sewer Clean & CCTV 09.,.022.pdf
Pro -Pipe Quote for Storm Sewer Addition-08.31.2022.pdf
Change order Summary
Original Contract Sum 370,000.00 Substantial Completion Date 14--Feb-2023
Net Cost by Previous Approved Cos 19,185.00 Net Time Change By Previous Cos 5 days
Contract Sum Before This CO 389,185,00 Substantial Completion before This Co 19TFeb-2023
Contract Sum Changed By This CO 30,072.25 Time Changed By This CO 0 days
New Contract Sum 419,257.25 New Substantial Completion Date 19--Feb--2023
All Change orders make up 13.31% of the original Contract
Accounting and Status
Accounting Status
Item ld
PO Number
Accounting Project Code
Custom Accounting Field 05
Custom Accounting Field 07
Line items
Item Account WBS1
# Code Section Description
3.0 Construction
298
422428 FEMA Number
WWC019 Custom Accounting Field 04
Custom Accounting Field 06
Custom Accounting Field 08
Unit Total
Quantity UoM Price Amount
015
GC Contract
2558
CCTV Inspection and Cleaning - 12" Storm Sewer Main (W4 #3 -
2,225.00
LF
2.54
5,651.50
Maps 1 & 2)
016
GC Contract
2558
CCTV Inspection and Cleaning - 15" Storm Sewer Main (WC #3 - Map
525.00
LF
5.94
3,118.50
1)
017
GC Contract
2558
CCTV Inspection and Cleaning - 18" Storm Sewer Main (WC #3 - Map
375.00
LF
8.59
3,221.25
1)
018
GC Contract
2558
CCTV Inspection and Cleaning - 18" Storm Sewer Main (WC #3 -- Map
1,950.00
LF
4.14
8,073.00
2)
019
GC Contract
2558
CCTV Inspection and Cleaning - 27" Storm Sewer Main (WO #3 - Map
250.00
LF
12.89
3,222.50
2)
020
GC Contract
2558
Lateral Launch Inspection - Storm Sewer (WC #3 - Map 1)
350.00
LF
6.53
2,285.50
021
GC Contract
2558
Lateral Launch Inspection - Storm Sewer (WO #3 -- Map 2)
1,000.00
LF
2.25
2,250.00
022
GC Contract
2558
Cleaning and CCTV of 26-inch Sanitary Sewer
500.00
LF
4.50
2,250.00
Total
30,072.25
Grand Total: 30,072.25
Approval Approved
Due: 6TGct--2022
Name or Role Status Actions
1 External -GC Approved
Ryan Gaskie
28-Sep-2022 02:24 PM CST
2 Project Manager Approved
John Pippins
28-Sep-2022 05:26 PM CST
3 City Engineer Approved
Amalia 'Molly" Villarreal
29-Sep-2022 09:08 AM CST
Name or Role Status Actions
4 Director Approved
Bart Bartkowiak
29-Sep-2022 O9:10 AM CST