HomeMy WebLinkAboutRES 22-257RESOLUTION NO. 22-257
WHEREAS, on March 9, 2021 the City Council of the City of Beaumont, Texas
passed Resolution No. 21-056 awarding a contract in the amount of $671,493.01 to
Placo, Ltd., of Lumberton, Texas, for the Lift Station & WWTP Repairs Tropical Storm
Harvey Group 2 Lift Stations Project; and,
WHEREAS, on September 22, 2021, the City Council of the City of Beaumont,
Texas passed Resolution No. 21 -217 authorizing the City Manager to execute Change
Order No. 1, in the amount of $29,816.39, to increase the size of the flood barrier at
Tyler Street Lift Station and increase the size of the electrical platforms at the Bennett
Lift Station and Stonetown Lift Station to accommodate the larger electrical equipment
required for the addition of the proposed Variable Frequency Drive (VFD) units to be
added to the pump controls, thereby increasing the total contract amount to
$701,309.40; and,
WHEREAS, on March 22, 2022, the City Council of the City of Beaumont, Texas
passed Resolution No. 22-091 authorizing the City Manager to execute Change Order
No. 2, in the amount of $69,180.90, to remove and replace four (4) sets of pump guide
rails and a pump base replacement at the Bennett Lift Station, thereby increasing the
total contract amount to $770,490.30; and,
WHEREAS, on April 26, 2022, the City Council of the City of Beaumont, Texas
passed Resolution No. 22-116 authorizing the City Manager to execute Change Order
No. 3, in the amount of $19,481,70, to accommodate changes caused by larger pump
power leads and furnish and install a new weatherhead at the Bennett Lift Station; and,
furnish and install larger pump cable conduits and weatherhead at the Stonetown Lift
Station, thereby increasing the total contract amount to $789,972.00; and,
WHEREAS, Change Order No. 4, in the amount of ($50,000.00), is required to
adjust the estimated quantities in the contract to reflect the actual quantities used in the
completion of the project. A total of seventy-eight (78) calendar days are required to be
added to the contract time to reflect the actual contract time used. The calendar days
were added to account for inclement weather days and additional time processing
Change Order Nos. 2-3. Thereby reducing the total contract amount to $739,972.00;
and,
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 4, in the amount of ($50,000.00) to adjust the estimated quantities in the
contract, thereby reducing the total contract amount to $739,972.00 for the Lift Station &
WWTP Repairs Tropical Storm Harvey Group 2 Lift Stations Project.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 11th day of
October, 2022.
- Mayor Robin Mouton -
APPROVAL OF CONTRACT CHANGE
CHANGE ORDER No, Four (4) & FlnO
DATE,. August 29, 2022
PROTECT: City of Beaumont, Texas
Lift Station & WWTP Repairs
Tropical storm Harvey
Group 2 Lift Stations
Old Na. WU0121-11 / FEMA f113512, 13477,13510
OWNER: City of Beaumont, Texas
801 Main Street
Beaumont, Texas 77704
CONTRACTOR: Place, Ltd
11939 Leatherwood Drive
Lumberton, Texas 77657
TO THE OWNEn: Approval of the following contract change Is requested.
Reason for Change; To adjust final quantities and contract time
ORIGINAL CONTRACT AMOUNTi 6 14 3.01
REVISER CONTRACT AMOUNT PER PREVIOUS CHANGE ORDERS;
789,972,00
THIS CHANGE ORDER
ev Rem DescrJotion
5 Contln$ency. METE the unsused Contingency, $50,0moo/is
$ (50,90%OD)
TOTAL AM OUNT Of THIS CHANGE OR DER;
$ (50,000,00)
TOTAL REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER!
S 739.97?.Bo
PERCENTOFTHIS CHANGE ORDER
-7.45%
TOTAL PERCENT CHANGE ORDER TO RATE
10.20%
CONTRACTTIME
Original ContractTlme:
1E0 calendar days
Addltlona! Contract Time per Previous Change Orders
163 calendar days
THIS CHANGE ORDER
Additional Contract Time requested this Change order
78 calendar days
Revised Contract Time
421 calendar days
CONDITION OF CHANGE;
"Contractor acknoveledges and agrees that the adjustments In contract price and contract time stipulated In this Change Order represents full
compensation for all Increases and decreases In the cost of, and the time requlred to perform the entire work under the Contract arising directly
or indirectly from this Change order and all previous Change Orders, Acceptance of this walver constitutes an agreement between Owner and
Contractor that the Change Order represents an all Inclusive, mutually agreed upon adjustment to the Contract, and that Contractor will waive all
rights to file a eialm on this Change Order after R Is properly executed,"
Accep ed byt Reviewed by: Re
Pla , tt 1 AmaUa villarreai, P.E, v a rtkovrl
Co ctor City Engineer Director of public Works
{61�y and Tec olog^!y Services
Date! f�"""d Date: { pste; —
Re ' Approved by:
Attested by:
i
M
Schaumburg Polk, Inc, Kenneth R. Williams
Tina Broussard
y CityManagor
Engineer L16
pate: Z}� pater
City0ork
Date:
APPROVAL, OF CONTRACT CHANGE
CHANGE ORDER No. Four (4) & Final
DATE: August 29, 22
PROJECT: City of Beaumont, Texas
Lift Station & W'WTP Repairs
Tropical Storm Harvey
Group 2 Lift Stations
Bid No. WU0121-11 / FEMA 1113512, 13477, 13510
OWNER: City of Beaumont, Texas
801 Main Street
Beaumont, Texas 77704
CONTRACTOR: Placo, Ltd
11939 Leatherwood Drive
Lumberton, Texas 77657
TO THE OWNER: Approval of the following contract change is requested.
Reason for Change: To adjust final quantities and contract time
ORIGINAL CONTRACT AMOUNT:
67'1,493.01
REVISED CONTRACT AMOUNT PER PREVIOUS CHANGE ORDERS:
. ...... .... . 789j972-00
THIS CHANGE ORDER
New Itemspflon
Qescri_
5 Contingency. DELETE the unsused Contingency, $50,000.00/ls
(50$000,00)
TOTAL AMOUNT OF THIS CHANGE ORDER:
(50r000.00)
TOTAL REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER:
739,972.00
PERCENT 01F THIS CHANGE ORDER
-7.45%
TOTAL PERCENT CHANGE ORDER TO DATE
10.20%
CONTRACT TIME
Original Contract Time:
180 calendar days,
Additional Contract'Tlme per Previous Change Orders
163 calendar days
THIS CHANGE ORDER
Additional Contract Time requested this Change Order
78 calendar days
Revised Contract Time
421 calendar days
Engineer Ir e") City Manager City Clerk