Loading...
HomeMy WebLinkAboutRES 22-046RESOLUTION NO. 22-046 WHEREAS, on February 9, 2021, the City Council of the City of Beaumont, Texas passed Resolution No. 21-033 awarding a contract in the amount of $953,415.45 to Solid Bridge Construction, LLC, of Huntsville, Texas, for the Cattail Marsh Wetlands Repair Project; and, WHEREAS, on July 13, 2021, the City Council of the City of Beaumont, Texas passed Resolution No. 21-158 authorizing the City Manager to execute Change Order No. 1, in the amount of ($79,338.36), to account for two (2) additional damaged locations; and, to allow for an alternate repair to two (2) areas where the interior slop of the levee is still intact and the repairs will not be as extensive, thereby decreasing the total contract amount to $874,077.09; and, WHEREAS, on August 24, 2021, the City Council of the City of Beaumont, Texas passed Resolution No. 21-200 authorizing the City Manager to execute Change Order No. 2, in the amount of $21,899.93, to provide an alternate repair for three (3) locations where the existing levee road is in good condition, thereby increasing the total contract amount to $895,977.02; and, WHEREAS, a Miscellaneous Improvements allowance, in the amount of $100,000.00, was included in the above noted contract; and, WHEREAS, on October 12, 2021, the City Council of the City of Beaumont, Texas passed Resolution No. 21-248 authorizing the City Manager to execute Change Order No. 3, in the amount of $36,000.00, to provide for additional limestone base material to be placed on the existing levee roads within Cattail Marsh, thereby decreasing the total Miscellaneous Improvements allowance to $64,000.00 and having no effect on the total contract amount of $895,977.02; WHEREAS, on December 7, 2021, the City Council of the City of Beaumont, Texas passed Resolution No. 21-319 authorizing the City Manager to execute Change Order No. 4, in the amount of $49,895.00, for additional repairs of a damaged location on the interior side slope of the Cell 3 north levee, thereby decreasing the total Miscellaneous Improvements allowance to $14,105.00 and having no effect on the total contract amount of $895,977.02; and, WHEREAS, Change Order No. 5, in the amount of ($14,105.00) is required to adjust the estimated quantities in the contract to reflect the actual quantities used in the completion of the project, thereby decreasing the total contract amount to $881,872.02; and, WHEREAS, the project has been inspected by the Engineering Division and found to be complete in accordance with the provisions and terms set forth in the contract; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the statements and findings set out in the preamble to this resolution are hereby, in all things, approved and adopted; and, THAT the City Manager be and he is hereby authorized to execute Change Order No. 5, in the amount of ($14,105.00), to adjust the estimated quantities in the contract to reflect the actual quantities used in the completion of the project, thereby decreasing the total contract amount to $881,872.02; and, BE IT FURTHER RESOLVED THAT the Cattail Marsh Wetlands Repair Project be and the same is hereby accepted; and, BE IT ALSO RESOLVED THAT the City Manager is authorized to make final payment in the amount of $44,093.60 to Solid Bridge Construction, LLC, of Huntsville, Texas. The meeting at which this resolution was approved was in all things conducted in strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter 551. PASSED BY THE CITY COUNCIL of the City of Beaumont this the 8th day of February, 2022. - Mayor Robin Mouton - CHANGE ORDER NO. Five (5) & FINAL DATE:. January 11, 20,22 PROJECT: City of Beaumont, Texas Cattail Marsh Wetlands Repair BidNo. PW1021-06 / FEMA Project 413339 & 039195 OWNER*- City of Beaumont, Texas 801 Main Street Beaumont, Texas 77704 CONTRACTOR: Solid Bridge Construction, LLC 1204 Sam Houston Avenue, Sulte 1 Huntsville, TX 77340 TO THE. OWNER,* Approval of the following contract change is requested. Reason for Change: To adjust final' q,uantity/amo,unt for Bid Item No. 26. ORIGINAL CONTRACT AMOUNT: REVISED CONTRACT AMOUNT PER CHANGE ORDER No. 1, No. 2, No. 3 & No. 4: THIS CHIANGE ORDER Item Dtsc i tion� 26 Miscellaneous Improvements - Reduce the allowance by $14$105.00 to close-out contract. Remaining allowance = $14,105,00 - $14,105.00 = $0.00 TOTAL AMOUNT OF THIS CHANGE ORDER: TOTAL REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER: CO, N TRACT TIME Original Contract Time: Revised Contract Time per Change Order No. 1, No. 2, No. 3 and No. 4 Additional Contract Time for change order Revised Contract Time per this Change Order �95 977.02 $ (1.4,1O5,0®j $ (141105.00) 881,872.02 120 working days 231 working days 0 working days 231 working days CONDITION OF CHIANGlE., "Contractor acknowledges and agrees that the adjustments in contract price and contract time stipulated in this Change Order represents Bull compensation for all increases and decreases in the cost of, and the time required to perform the entire work under the Contract arising directly or indirectly from this Change Order and all pirevilou's Change Orders. Acceptance of this waiver constitutes an agreement between Owner and Contractor that the Change Order represents an all inclusive, mutually agreed upon adjustment to the Contract, and that Contractor will wailve all rights to file a claim! on this Change Order after it is properly executed." Accept , Tb y: 10C t t i �_l MIJBricliklr', ruction, LLC Contractor Date: 6XV Ile o, mended by: Approved by: Tcm Peal: ny. Kyle Hayes e e City Manager Date: Date: z "L Page 1 of 1 M1101 11Rtern by: r, , A- �. I Tina Broussard City Cler 01 . ar Date: