HomeMy WebLinkAboutRES 22-038RESOLUTION NO. 22-038
WHEREAS, on February 25, 2020, the City Council of the City of Beaumont,
Texas passed Resolution No. 20-041 awarding a contract in the amount of
$1,975,777.68 to Allco, LLC, of Beaumont, Texas, for the Wastewater Treatment Plant
Trickling Filters Rehabilitation Project; and,
WHEREAS, on June 2, 2020, the City Council of the City of Beaumont, Texas
passed Resolution No. 20-110 authorizing the City Manager to execute Change Order
No. 1, in the amount of ($47,843.32), to delete the rehabilitation of the existing
distribution tubes and truss arms on the Primary Trickling Filters; delete the
rehabilitation of the existing truss arms on the Secondary Trickling Filters; provide new
hot -dip galvanized steel distribution tubes on the Secondary Trickling Filters in lieu of
new stainless steel tubes; and, rehabilitate the interior and exterior surfaces of the
center columns on each of the Primary Trickling Filters and each of the Secondary
Trickling Filters, thereby decreasing the contract amount to $1,927,934.36; and,
WHEREAS, on August 21, 2020, the City Manager executed Change Order No.
2, in the amount of $0.00, to provide for the removal and replacement of six (6) of
thirteen (13) gusset plates on the Primary Trickling Filer No. 2 center column, thereby
having no effect in the total contract amount of $1,927,934.36; and,
WHEREAS, on November 6, 2020, the City Manager executed Change Order
No. 3, in the amount of $0.00, to provide for the removal and replacement of eight (8) of
twelve (12) gusset plates on the Primary. Trickling Filter No. 3 center column, thereby
having no effect in the total contract amount of $1,927,934.36; and,
WHEREAS, on January 20, 2021, the City Manager executed Change Order No.
4, in the amount of $0.00, to provide for a time extension due to time spent waiting for
answers from the trickling filter manufacturer on repair of the south primary center
column gussets, Covid-19 quarantine of workers, and Hurricane Laura, thereby having
no effect in the total contract amount of $1,927,934.36; and,
WHEREAS, on March 10, 2021, the City Manager executed Change Order No.
4, in the amount of $0.00, to provide for the removal and replacement of four (4) of eight
(8) gusset plates on the South Secondary Trickling Filter center column, thereby having
no effect in the total contract amount of $1,927,934.36; and,
WHEREAS, Change Order No. 6, in the amount of ($38,423.00), is required to
adjust the estimated quantities in the contract to reflect the actual quantities used in the
completion of the project, thereby decreasing the total contact amount to $1,889,511.36;
and,
WHEREAS, the project has been inspected by the Water Utilities Engineering
Division and found to be complete in accordance with the provisions and terms set forth
in the contract;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 6, in the amount of ($38,423.00), to adjust the estimated quantities in the
contract to reflect the actual quantities used in the completion of the project, thereby
decreasing the total contact amount to $1,889,511.36; and,
BE IT FURTHER RESOLVED THAT the Wastewater Treatment Plant Trickling
Filters Rehabilitation Project be and the same is hereby accepted; and;
BE IT ALSO RESOLVED THAT the City Manager is authorized to make final
payment in the amount of $94,475.59 to Allco, LLC, of Beaumont, Texas.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 1st day of
February, 2022.
ay�t-� Aa4��2.
- Mayor Robin Mouton -
APPROVAL OF CONTRACT CHANGE
CHANGE ORDER No. SIX (6) & FINAL
DATE; November �{„2021
PROJECT, City of Beaumont, Texas
Wastewater Treatment Plant:
Trickling Fllters Rehabliltatlon - WU0819-21
OWNERi City of Beaumont, Texas
801 Main Street
Beaumont, Texas 77704
CONTRACTOR: Allco, LLC
PO Box 3684
Beaumont, Texas 77707
TO THE OWNER: Approval of the following contract change Is requested.
Reason for Change: To adjust final pay Items to adjust contract time due to weather (rain), and unforeseen delays
ORIGINAL CONTRACT AMOUNT;
$ 1,975,777.68.
I1EVISED CONTRACT AMOUNT PER CHANGE ORDER NO, 5
$ 1,927,934.36
THIS CHANGE ORDER
112M Description
5 VEGETATIVE WATERING - DELETE Vegetative Wotering - $5,100.00 /lump sum
$ (5,100.00)
6 CONTINGENCY ALLOWANCE - DELETE remalning Contingency Allowance - $33,323.00 J lump sum
$ (33j323.00)
TOTAL AMOUNT OF THIS CHANGE ORDER N0. 6
$ (35s423,00)
TOTAL REVISED CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
1,889,511.36
CONTRACT TIM9-
Orlginal Contract Time.
180 calendar days
Additional Time per Change Order No. 2, No. 3, No, 4 and No. 5
52 calendar days
AdditionalTime Requeated t s C a Order
Contract Time suspended , waiting on secondary trickling filters to be delivered
47 calendar days
Delay for 195 Ton crane delivery
10 calendar days
Delay for painters to re-mobillxe on -site to paint South Secondary Filter
14 calendar days
Delay for painters to re•mobllize on -site to paint North Secondary Filter
14 calendar days
Additional time to repair clips on South Secondary Filter arms
14 calendar days
Additional time to repair clips on North Secondary Filter arras
14 calendar days
Delay for waiting on City to turn off filters
10 calendar days
Time Extension Request for Weather Delays
47 calendar days
170 calendar clays
Final Contract Tlme ParThis Chango Order No, 6
402 calendar days
s
Page 1 of 2
CHANGE ORDER No. SIX (6) & FINAL.
DATE,- Navarnber 2 0 2021
CONDITION OF CHANGE;
"Contractor acknowledges and agrees that the adjustments In contract price and contract tlrna stipulated In tlals Chon e order represents
cannpensatlon for all Increases and decreases In the cost of, and the time required to perform tale entire work under the Contract arlsing directly or
Indirectly from this Change. Order and all previous Change Orders. Acceptance of this waiver constitutes an agreement between owner and Contractor
that the Chong'e Order represents an all Inclusive, mutually agreed upon adjustment to the Contract, and that Contractor will valve all rights to file a
cialm on this Change order after It Is properly executed."
Accepted by
Contractor
Reviewed by;
, rnalla Villareal, P.E.
City Engineer
Date
Approved by.,
Kyle Mayes
City Wnicer
nataw
Director
Technologyand