HomeMy WebLinkAboutRES 21-200RESOLUTION NO. 21-200
WHEREAS, on February 9, 2021, the City Council of the City of Beaumont,
Texas passed Resolution No. 21-033 awarding a contract in the amount of $953,415.45
to Solid Bridge Construction, LLC, of Huntsville, Texas, for the Cattail Marsh Wetlands
Repair Project, and,
WHEREAS, on July 13, 2021, the City Council of the City of Beaumont, Texas
passed Resolution No. 21-158 authorizing the City Manager to execute Change Order
No. 1, in the amount of ($79,338.36), to account for two (2) additional damaged
locations; and, to allow for an alternate repair to two (2) areas where the interior slop of
the levee is still intact and the repairs will not be as extensive, thereby decreasing the
total contract amount to $874,077.09, and,
WHEREAS, Change Order No. 2, in the amount of $21,899.93, is necessary to
provide an alternate repair for three (3) locations where the existing levee road is in
good condition, thereby increasing the total contract amount to $895,977.02;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 2, in the amount of $21,899.93 for the additional work described above,
thereby increasing the total contract amount to $895,977.02 for the Cattail Marsh
Wetlands Repair Project.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 24th day of
August, 2021.