Loading...
HomeMy WebLinkAboutRES 21-199RESOLUTION NO. 21-199 WHEREAS, on March 16, 2021, the City Council of the City of Beaumont, Texas passed Resolution No. 21-066 awarding a contract in the amount of $549,490.00 to Shaver Construction & Contracting Services, LLC, d/b/a Silverback Services, of Jasper, Texas, for the Beaumont Water Treatment Plant 72-Inch Emergency Repair Project, and, WHEREAS, on June 9, 2021, the City Manager executed Change Order No. 1, in the amount of $3,700.00, to increase the size of the coring tool needed to gain access through the chemical vault floor due to unforeseen field conditions, thereby increasing the total contract amount to $553,190.00; and, WHEREAS, on June 16, 2021, the City Manager executed Change Order No. 2, in the amount of $6,165.00, for hydro excavation work to reveal the location of the existing 72" pipeline due to unforeseen field conditions, thereby increasing the total contract amount to $559,355.00, and, WHEREAS, on June 25, 2021, the City Manager executed Change Order No. 3, in the amount of $6,400.00, to obtain an engineered bulkhead design that will be sealed and stamped by a professional engineer registered with the State of Texas, thereby increasing the total contract amount to $565,755.00; and, WHEREAS, on July 20, 2021, the City Council of the City of Beaumont, Texas passed Resolution No. 21-169 authorizing the City Manager to execute Change Order No. 4, in the amount of $30,585.00, to fabricate and install an engineered bulkhead, thereby increasing the total contract amount to $596,340.00; and, WHEREAS, Change Order No. 5, in the amount of $24,937.00, is necessary due to unforeseen site conditions which developed during construction, thereby increasing the total contract amount to $621,277.00, NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the statements and findings set out in the preamble to this resolution are hereby, in all things, approved and adopted, and, THAT the City Manager be and he is hereby authorized to execute Change Order No. 5, in the amount of $24,937.00, for additional work described above, thereby increasing the total contract amount to $621,277.00 for the Beaumont Water Treatment Plant 72-Inch Emergency Repair Project. The meeting at which this resolution was approved was in all things conducted in strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter 551 PASSED BY THE CITY COUNCIL of the City of Beaumont this the 24th day of August, 2021. �l -Mayor Robin Mouton - � 6