HomeMy WebLinkAboutRES 21-011RESOLUTION NO. 21-011
WHEREAS, on March 19, 2019, the City Council of the City of Beaumont, Texas
passed Resolution No. 19-063 awarding a contract in the amount of $974,960.00 to
Allco, LLC, of Beaumont, Texas, for the Sewer Plant Pump Replacement and Renewal
Project; and,
WHEREAS, on August 20, 2019, the City Council of the City of Beaumont
passed Resolution No. 19-174, Change Order Nos. 1-3, in the amount of $138,000.00,
were required to provide the replacement of one (1) additional high flow pump and one
(1) motor due to the condition of the existing unit; and, an additional thirty (30) days for
the installation, thereby increasing the total contract amount to $1,112,960.00; and,
WHEREAS, Change Order No. 4, in the amount of $12,603.00, is requested to
address the existing four (4) pump pedestals on the project which was discovered
during the construction that the existing pedestals needed additional support which will
effectively secure the work already completed on the pump replacement; and, an
additional fourteen (14) calendar days will be added to complete the work;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 4, in the amount of $12,603.00 for additional work described above, thereby
increasing the total contract amount to $1,125,563.00 for the Sewer Plant Pump
Replacement and Renewal Project; and,
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 26th day of
January, 2021.