HomeMy WebLinkAboutRES 20-170RESOLUTION NO. 20-170
WHEREAS, on June 2, 2020, the City Council of the City of Beaumont, Texas
passed Resolution No. 20-114 awarding a contract in the amount of $93,450.00 to
Brystar Contracting, Inc., of Beaumont, Texas, for the Cartwright Avenue & Goliad
Street Storm Drainage Repair Project; and,
WHEREAS, Change Order No. 1, in the amount of $15;790.00, is required to
adjust the estimated quantities to reflect the actual quantities used in the completion of
the project, thereby increasing the total contract amount to $109,240.00; and,
WHEREAS, the project has been inspected by the Engineering Division and
found to be complete in accordance with the provisions and terms set forth in the
contract;
NOW, THEREFORE, BE IT RESOLVED BY THE
J
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 1, in the amount of $15,790.00, to address the items described above,
thereby increasing the total contract amount to $109,240.00 for the Cartwright Avenue &
Goliad Street Storm Drainage Repair Project;,and,
BE IT FURTHER RESOLVED THAT the Cartwright Avenue & Goliad Street
Storm Drainage Repair Project be and the same is hereby accepted; and,
BE IT ALSO RESOLVED THAT the City Manager is hereby authorized to make
final payment in the amount of $21,412.50 to Brystar Contracting, Inc., of Beaumont,
Texas.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 18th day of
August, 2020.