HomeMy WebLinkAboutRES 19-285RESOLUTION NO. 19-285
WHEREAS, on August 21, 2018, the City Council of the City of Beaumont, Texas
passed Resolution No. 18-203 awarding a contract in the amount of $1,204,807,00 to T
Construction, LLC, of Houston, Texas, for the Amelia Area and Sherwood Drive Pipe
Bursting — Phase II Project; and,
WHEREAS, Change Order No. 1, in the amount of ($158,159.40), is required to
adjust the estimated quantities to reflect the actual quantities used in the completion of
the project, thereby decreasing the total contract amount to $1,046,617.60; and,
WHEREAS, the project has been inspected by the Water Utilities Division and
found to be complete in accordance with the provisions and terms set forth in the
contract;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 1, in the amount of ($158,159.40), for additional work described above,
thereby decreasing the total contract amount to $1,046,647.60 for the Amelia Area and
Sherwood Drive Pipe Bursting — Phase II Project; and,
BE IT FURTHER RESOLVED THAT the Amelia Area and Sherwood Drive Pipe
Bursting — Phase II Project be and the same is hereby accepted; and,
BE IT ALSO RESOLVED THAT the City Manager is hereby authorized to make
final payment in the amount of $52,332.38 to T Construction, LLC, of Houston, Texas.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 10th day of
December, 2019.