HomeMy WebLinkAboutRES 75 245R E S O L U T I O N WHEREAS, the City of Beaumont and Trotti & Thomson executed a certain contract on the 16 day of April, 1974, for the construction of Washington Boulevard, CIP Project No. 11 -ST -03, at a total contract price of $723,915.50; and, WHEREAS, the work was completed in 138 of the 200 days allowed time, which is 630 of the allowed time; and, WHEREAS, the actual cost of the work was $721,289.29; and, WHEREAS, the City Engineer has inspected the work and has recom- mended its acceptance and final payment in the amount of $91,123.49 to be made to the contractor based on actual work performed; NOW, THEREFORE,'BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the City of Beaumont hereby accepts the completion of the afore- mentioned contract in all particulars and does further authorize the final payment of $91,123.49 to the said contractor. PASSED BY THE CITY COUNCIL of the City of Beaumont this the �_ day of 1975.