HomeMy WebLinkAboutRES 75 140RE S'O LUT I ON
WHEREAS, the City of Beaumont, a municipal corporation of the
State of Texas, has made application to the Texas Water Quality Board
and the Environmental Protection Agency for a federal grant pursuant
to the Federal Water Pollution Control Act Amendments of 1972, Public
Law 92-500, and the rules and regulations thereto;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the application for which federal grant assistance has been reques-
ted pursuant to the Federal Water Pollution Control Act Amendments of
1972, Public Law 92-500, will be constructed to completion in accordance
with the laws, rules and regulations and with the following approximate
project schedule:
Project Schedule Item Date of Action
General
Availability of Financing Funds for Applicants
Share of the Project Costs: Step 1 July, 1975
Step 2 July, 1976
Step 3 July, 1977
Availability of the Site(s) for the Project
Facilities Now Available
Step 1
Infiltration/Inflow Analysis Initiated August, 1975
Completed February, 1976
Submitted to State (TWQB) April, 1976
Preliminary Infiltration/Inflow
Evaluation Survey Study Plan (If Needed)
Initiated December, 1975
Completed March, 1976
Report Completed April, 1976
Submitted to State (TWQB) April, 1976
Infiltration/Inflow Evaluation Survey (If Needed)
Initiated July, 1976
Completed April, 1977
Report Completed June, 1977
Submitted to State (TWQB) July, 1977
Environmental Assessment
Initiated August, 1975
Completed* March, 1976
Public Hearing Advertised* April, 1976
Public Hearing CondlictPd* Mn -%r 1 Q 71;
Project Schedule Item Date of Action
Environmental Assessment
Finalized* June, 1976
Submitted to State (TWQB)* July, 1976
The Regional Planning Agency Comments
Approvals Completed* June, 1976
Submitted to State (TWQB)* July, 1976
Facility Plan (Including Final Engineering Report/
Feasibility Report)
Initiated* August, 1975
Completed* March, -1976
Report Completed* April, 1976
Public Hearing* May, 1976
Submitted to State (TWQB)* July, 1976
*Add 15 Months if Sewer Survey is Needed
Step 2 ,
Final Plans and Specifications
Initiated October, 1976
Completed July, 1977
Submitted to State (TWQB) September, 1977
Step 3
Advertise for Construction Bids within the days
indicated after authorization to advertise
for bids has been issued 15 days
Submit Bid Opening Documents within the days
indicated after the bid.opening date 15 days
Award Construction Contract within the days
indicated after authorization to award
the contract has been issued 15 days
Initiation of Construction within the days
indicated after the award of the contract 30 days
Complete Construction within the days indicated
after initiation of construction 1,100 days
and,
BE IT FURTHER RESOLVED that the above-named applicant under-
stands that the above project schedule must be approved by the Texas
Water Quality Board and the Environmental Protection Agency, and that
once a project schedule has been approved, no changes will be_ autho-
rized without first receiving approval of the change from the Texas,
Water Quality Board and the Environmental Protection Agency.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the
O
day of , 19 75 .