HomeMy WebLinkAboutRES 19-084RESOLUTION NO. 19-084
WHEREAS, on April 25, 2017, the City Council of the City of Beaumont, Texas,
passed Resolution No. 17-083 awarding a contract in the amount of $15,984,397.88 to
Allco, L.L.C., of Beaumont, Texas, for the Washington Boulevard Pavement Widening
Phase II (Corporate Drive to Amarillo Street) Project; and,
WHEREAS, on August 3, 2017, the City Manager executed Change Order No. 1,
in the amount of $9,920.00, to, adjust the estimated quantities to reflect the actual
quantities used in the completion of the project, thereby increasing the contract amount
to $15,994,317.88; and,
WHEREAS, on February 6, 2018, the City Council of the City of Beaumont,
Texas, passed Resolution No. 18-032 authorizing the City Manager to execute Change
Order No. 2, in the amount of $103,893.00, to accommodate design changes necessary
to address unforeseen conflicts with the underground utilities and additional curb and
driveway improvements required on Executive Boulevard and Corporate Drive, thereby
increasing the contract amount to $16,098,210.88; and,
WHEREAS, on May 14, 2018, the City Manager executed Change Order No. 3,
in the amount of $7,714.55, to adjust the estimated quantities to reflect the actual
quantities used in the completion of the project, thereby increasing the contract amount
to $16,105,925.43; and,
WHEREAS, on June 5, 2018, the City Council of the City of Beaumont, Texas,
passed Resolution No. 18-123 authorizing the City Manager to execute Change Order
No. 4, in the amount of $16,032.91 to adjust the pipe quantity and size which was not
allotted for in the original design and the addition of fourteen (14) calendar days,
thereby increasing the contract amount to $16,121,958.34; and,
WHEREAS, on July 17, 2018 the City Council of the City of Beaumont, Texas,
passed Resolution No. 18-157 authorizing the City Manager to execute Change Order
No. 5, in the amount of $33,303.00, to adjust bid items and quantities in the contract to
accommodate revisions to the storm sewer system; relocate a 16" waterline; and,
twenty-two (22) calendar days will be added to the contract for the work, thereby
increasing the contract amount to $16,155,261.34; and,
WHEREAS, on October 16, 2018 the City Council of the City of Beaumont,
Texas, passed Resolution No. 18-255 authorizing the City Manager to execute Change
Order No. 6, in the amount of $215,144.90, to adjust the bid items and quantities in the
contract to accommodate for additional sewer work; ground boxes for fiber optics and
traffic signals; and, sixty (60) calendar days will be added to the contract for the work,
thereby increasing the contract amount to $16,370,406.24; and,
WHEREAS, Change Order No. 7, in the amount of $128,658.75, is necessary to
adjust the bid items and quantities in the contract for additional waterline, surface inlets
for storm sewer, and foundations for traffic ground cabinets; traffic signal poles that
meet the height requirements needed to fit in the field; and, ten (10) calendar days will
be added to the contract for the work, thereby increasing the contract amount to
$16,499,064.99;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 7 for additional work described above, thereby increasing the contract
amount by $128,658.75 for a total contract amount of $16,499,064.99 for the
Washington Boulevard Pavement Widening Phase II (Corporate Drive to Amarillo
Street) Project., with sixty calendar days added to the contract for the work.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 9th day of
April, 2019.
hip
V of - Ma r Becky Ames -
0�
4g
.o
law