HomeMy WebLinkAboutRES 19-015RESOLUTION NO. 19-015
WHEREAS, on November 21, 2017, the City Council of the City of Beaumont,
Texas passed Resolution No. 17-248 awarding a contract in the amount of $726,162.75
to ALLCO, Inc., of Beaumont, Texas, for the Keith Road 16" Water Line (from Phelan
Boulevard to Dishman Road) Project; and,
WHEREAS, Change Order No. 1, in the amount of $30,945.25, is required to
adjust the estimated quantities to reflect the actual quantities used in the completion of
the project, and the addition of ninety-three (93) calendar days which were needed, due
to weather and utility coordination delays during construction, thereby increasing the
total contract amount to $757,108.00; and,
WHEREAS, the project has been inspected by the Water Utilities Division and
found to be complete in accordance with the provisions and terms set forth in the
contract;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 1, in the amount of $30,945.25, for additional work described above, thereby
increasing the total contract amount to $757,108.00 for the Keith Road 16" Water Line
(from Phelan Boulevard to Dishman Road) Project; and,
BE IT FURTHER RESOLVED THAT the Keith Road 16" Water Line (from Phelan
Boulevard to Dishman Road) Project be and the same is hereby accepted; and,
BE IT ALSO RESOLVED THAT the City Manager is hereby authorized to make
final payment in the amount of $37,855.40 to ALLCO, Inc., of Beaumont, Texas.
The meeting at which this resolution was approved was in all things conducted in
strict compliance with the Texas Open Meetings Act, Texas Government Code, Chapter
551.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 15th day of
January, 2019.
I�M§
yor Becky