WHEREAS, on September 27, 2016, the City Council of the City of Beaumont,
Texas, passed Resolution No. 16-188 awarding a contract in the amount of
$7,409,783.00 to McInnis Construction, Inc., of Silsbee, Texas, for the new Beaumont
Fire Station No. 1 Project; and,
WHEREAS, a contingency allowance in the amount of $100,000.00 was included
in the above noted contract; and,
WHEREAS, on December 22, 2016, the City Manager executed Change Order
No. 1, in the amount of $1,800.00, to remove approximately seventeen (17) concrete
footings which were encountered in the current area of excavation; and, to haul off and
backfill with compacted select fill, thereby decreasing the contingency allowance to
$98,200.00 and having no affect on the total contract amount of $7,409,783.00; and,
WHEREAS, Change Order No. 2, in the amount of $33,180.00 is required to
remove approximately 19,626 square feet of unstable subgrade soil located in the
building foundation area, thereby decreasing the contingency allowance to $65,020.00
and having no affect on the total contract amount of $7,409,783.00;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT-
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 1 for additional work described above, thereby decreasing the contingency
allowance by $33,180.00 for a total contingency allowance of $65,020.00 and having no
affect on the total contract amount of $7,409,783.00 for the new Fire Station No. 1
Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 10th day of
January, 2017