HomeMy WebLinkAboutRES 16-240RESOLUTION NO. 16-240
WHEREAS, on March 25, 2014, the City Council of the City of Beaumont, Texas,
passed Resolution No. 14-067 awarding a contract in the amount of $16,478,838.95 to
Brystar Contracting, Inc., of Beaumont, Texas, for the Washington Boulevard Pavement
and Drainage Improvement Project — Phase I (Amarillo to Martin Luther King Parkway),
and,
WHEREAS, on March 17, 2015, the City Council of the City of Beaumont, Texas,
passed Resolution No. 15-051 authorizing Change Order No. 1, in the amount of
($99,838.41), for minor design changes to better accommodate field conditions, thereby
decreasing the contract amount to $16,379,000.54; and,
WHEREAS, on November 17, 2015, the City Council of the City of Beaumont,
Texas, passed Resolution No. 15-255 authorizing Change Order No. 2, in the amount of
$85,093.00, to replace the existing piping system and fittings that connect the elevated
water storage tank on Harriot Street to the City water distribution system, thereby
increasing the total contract amount to $16,464,093.54; and,
WHEREAS, on January 11, 2016, the City Manager executed Change Order No.
3 in the amount of ($8,634.64) for replacement of the roadway pavement markings that
were not required with pavement markings that are required for installation to meet
current State and Highway Standard Pavement Markings, thereby decreasing the total
contract amount to $16,455,458.90; and,
WHEREAS, on June 14, 2016, the City Council of the City of Beaumont, Texas,
passed Resolution No. 16-106 authorizing Change Order No. 4, in the amount of
$14,622.00, for additional changes to construct a concrete structure to retain and
preserve the existing right-of-way landscape improvements and adjust existing sanitary
sewer manhole tops to match the proposed road pavement grade, thereby increasing
the contract amount to $16,470,080.90; and,
WHEREAS, Change Order No. 5, in the amount of $77,392.60, is required for
additional changes to install a 10" steel casing by bore under the Union Pacific Railroad
tracks right-of-way; install a 2" conduit for the City's fiber optic communications and
traffic signal lights controller lines; and, the fabrication and installation of new street
signs in accordance to City Standards along Washington Boulevard (Amarillo Street to
Martin Luther King Parkway), thereby increasing the contract amount to
$16,547,473.50;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT-
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 5 for additional work described above, thereby increasing the contract
amount by $77,392.60 for a total contract amount of $16,547,473.50 for the Washington
Boulevard Pavement and Drainage Improvement Project — Phase I (Amarillo to Martin
Luther King Parkway).
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 22nd day of
November, 2016.