HomeMy WebLinkAboutRES 16-106RESOLUTION NO. 16-106
WHEREAS, on March 25, 2014, the City Council of the City of Beaumont, Texas,
passed Resolution No. 14-067 awarding a contract in the amount of $16,478,838.95 to
Brystar Contracting, Inc., of Beaumont, Texas, for the Washington Boulevard Pavement
and Drainage Improvement Project — Phase I (Amarillo to Martin Luther King Parkway);
and,
WHEREAS, on March 17, 2015, the City Council of the City of Beaumont, Texas,
passed Resolution No. 15-051 authorizing Change Order No. 1, in the amount of
($99,838.41), for minor design changes to better accommodate field conditions, thereby
decreasing the contract amount to $16,379,000.54; and,
WHEREAS, on November 17, 2015, the City Council of the City of Beaumont,
Texas, passed Resolution No. 15-255 authorizing Change Order No. 2, in the amount of
$85,093.00, to replace the existing piping system and fittings that connect the elevated
water storage tank on Harriot Street to the City water distribution system, thereby
increasing the total contract amount to $16,464,093.54; and,
WHEREAS, on January 11, 2016, the City Manager executed Change Order No.
3 in the amount of ($8,634.64) for replacement of the roadway pavement markings that
were not required with pavement markings that are required for installation to meet
current State and Highway Standard Pavement Markings, thereby decreasing the total
contract amount to $16,455,458.90; and,
WHEREAS, Change Order No. 4, in the amount of $14,622.00, is necessary for
additional changes to construct a concrete structure to retain and preserve the existing
ay landscape improvements and adjust existing sanitary sewer manhole tops
to match the proposed road pavement grade, thereby increasing the contract amount to
$16,470,080.90;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 4 for additional work described above, thereby increasing the contract
amount by $14,622.00 for a total contract amount of $16,470,080.90 for the Washington
Boulevard Pavement and Drainage Improvement Project — Phase I (Amarillo to Martin
Luther King Parkway).
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 14th day of
June, 2016.