WHEREAS, on July 26, 2012, the Texas Department of Transportation (TxDOT)
entered into an agreement with Tradeco Infrastructura, Inc. in the amount of
$11,284,746.71 for the Concord Road Project; and,
WHEREAS, on July 9, 2013, the City Council of the City of Beaumont, Texas,
passed Resolution No. 13-147 approving Change Order No. 1, in the amount of
$88,965.21, including $12,085.19 for Engineering and Contingency charges, for
modifications to the water, sanitary sewer, storm sewer, and conduit lines for the
project; and,
WHEREAS, on December 15, 2015, the City Council of the City of Beaumont,
Texas, passed Resolution No. 15-295 approving Change Order Nos. 2, 3, 4 and 5, in
the total amount of $37,798.99, including $5,134.81 for Engineering and Contingency
charges, for the removal of water oak trees along SH 105; temporary drainage on SH
105 to aid the installation of water and sanitary sewer improvements; adjustment of
sanitary manholes to match final paving; and, removal of three (3) existing sanitary
manholes, respectively, thereby increasing the contract amount to $11,411,510.91; and,
WHEREAS, on March 4, 2016, the City Manager executed Change Order No. 6
in the amount of (-$6,695.34) for alterations to the sanitary pipe from SDR -17 to SDR -
26, thereby decreasing the contract amount to $11,404,815.57; and,
WHEREAS, on March 24, 2016, the City Manager executed Change order No. 7
in the amount of $6,614.94, including $898.61 for Engineering and Contingency
charges, for realignment of 8" PVC waterline to avoid conflict with existing utilities at
Concord Road and Garner Street, thereby increasing the contract amount to
$11,411,430.51; and,
WHEREAS, on February 9, 2016, the City Manager executed Change Order No.
8 in the amount of $0.00 to provide 87 additional working days to the contract, thereby
having no affect on the contract amount of $11,411,430.51; and,
WHEREAS, on March 8, 2016, the City Manager executed Change Order No. 9
in the amount of (-$36,248.64) for adjustments to the unit price for concrete sidewalks,
thereby decreasing the contract amount to $11,375,181.87; and,
WHEREAS, Change Order No. 10, in the amount of $55,461.32, including
$7,534.15 for Engineering and Contingency charges, is necessary to revise quantities
for items relating to the realignment of sanitary sewer lines from Dowlen Road to Garner
Road to avoid conflict with established utilities, thereby increasing the contract amount
to $11,430,643.19;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No.10 for additional work described above, thereby increasing the contract
amount by $55,461.32 for a total contract amount of $11,430,643.19 for the Concord
Road Project.