HomeMy WebLinkAboutRES 15-256RESOLUTION NO. 15-256
WHEREAS, on March 17, 2015, the City Council of the City of Beaumont, Texas,
passed Resolution No. 15-048 awarding a contract in the amount of $342,414.02 to LD
Construction, of Beaumont, Texas, for the Delaware Street Asphalt Resurfacing Project
— Phase II; and,
WHEREAS, Change Order No. 1, in the amount of $53,172.29, is required to
adjust the estimated quantities to reflect the actual quantities used in the completion of
the project, thereby increasing the total contract amount to $395,586.31; and,
WHEREAS, the project has been inspected by the Engineering Division and
found to be complete in accordance with the provisions and terms set forth in the
contract;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change
Order No. 1 adjusting quantities used to complete the project as described above,
thereby increasing the contract amount by $53,172.29 for a revised total contract
amount of $395,586.31; and,
BE IT FURTHER RESOLVED THAT the Delaware Street Asphalt Resurfacing
Project — Phase II be and the same is hereby accepted; and,
BE IT ALSO RESOLVED THAT the City Manager is hereby authorized to make
final payment in the amount of $91,163.07 to LD Construction, of Beaumont, Texas.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 17th day of