HomeMy WebLinkAboutRES 15-208RESOLUTION NO. 15-208
WHEREAS, on August 6, 2015, eight (8) bids were received for the Fire Station
No. 1 Project; and,
and,
WHEREAS, all bids exceeded the estimated construction cost of $5,794,000;
WHEREAS, it is the recommendation of Architectural Alliance, Inc, the
Architectural Consultant, that modifications be made to the construction documents and
the project be rebid at a later date; and,
WHEREAS, the City Council finds it is not in the public interest to accept the bids
for the First Station No. 1 Project and that same should be rejected;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby,
in all things, approved and adopted; and,
THAT the City Council does hereby reject the bids for the Fire Station No. 1
Project';
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 29th day of
September, 2015.
IBM+ii /,�►/ ,