HomeMy WebLinkAboutRES 14-261RESOLUTION NO.14 -261
WHEREAS, on May 6, 2008, the City Council of the City of Beaumont, Texas,
passed Resolution No. 08 -137 awarding a contract in the amount of $8,041,191.50 to
Allco, Ltd., of Beaumont, Texas, for the proposed Surface Water Treatment Plant
Improvements Phase I Project; and,
WHEREAS, on December 23, 2008, the City Council of the City of Beaumont,
Texas passed Resolution No. 08 -351 authorizing Change Order No. 1, in the amount of
$239,066.95, to furnish labor, equipment and material to install a new alum tank, the
removal and disposal of deteriorated existing precast pipe supports, and furnish labor,
equipment and material to install stainless steel pipe supports for each of the three (3)
pulsators, thereby increasing the contract amount to $8,280,258.45; and,
WHEREAS, on February 10, 2009, the City Council of the City of Beaumont, Texas
passed Resolution No. 09 -040 authorizing Change Order No. 2, in the amount of
$26,195.75, to increase the pulsator concrete and crack repairs in excess of bid quantities
in Pulsator #2, including labor and materials, thereby increasing the contract amount to
$8,306,454.20; and,
WHEREAS, on July 14, 2009, the City Council of the City of Beaumont, Texas
passed Resolution No. 09 -209 authorizing Change Order No. 3, in the amount of
$209,871.72, to demolish electric manhole duct banks, change PVC conduit to Rigid
Galvanized Steel conduit at Electric Building, remove abandoned 24 -inch pipeline, install
handrails at Pulsator raw water channel, provide emergency powerforSCADA transmitter,
replace (2) 48 -inch flow meters with (2) 36 -inch flow meters with adaptors for accuracy,
upgrade all windows and doors in Chemical Building to Hurricane rated, install new duct
bank from electric manhole to switch rack, place PatchCrete wainscoat over exposed
concrete block at Chemical Building, install Chemical Building roof drain line to existing
catch basin, replace existing 4x4 wooden chlorine ton container runners with 40 lb. steel
rail, sample pump modifications to submersible pumps in lieu of centrifugal pumps, repair
leakage and concrete damage to the walls of the existing Mixed Water Channel, including
repair of through -the -wall cracks with Combiflex, epoxy injection of 562 linear feet of cracks
and sandblasting and coating of the exterior of the channel at Pulsators 1, 2, and 3,
replace trolley hoist for Chemical Building, install electric manhole EMH -7, paint the
external Vacuum Chamber structures for Pulsators 1, 2, and 3, and additional 900 linear
feet of 4 -inch electrical PVC electrical installation to Administration Building from electrical
switchgear manhole, thereby increasing the contract amount to $8,516,325.92; and,
WHEREAS, on January 19, 2010, the City Council of the City of Beaumont, Texas
passed Resolution No. 10 -012 authorizing Change Order No. 4, in the amount of
$200,207.75, to furnish and install stairs and platforms for the new generators, weld
monorail joints in the Chlorine Building, provide concrete paving around the Electrical
Building, clean and re -caulk joints on the 5 MG clearwell cap, install ladders and step
platforms in the meter vault, install a 6 -inch liner wall at the mixed water channel, replace
(2) magna drives at the backwash pumps, install a 3 -inch PVC chlorine solution line from
Chemical Building to the Filter Building, add PVC expansion joints on wash lines in the
Pulsator Basins, pulsator concrete and crack repairs in excess of bid quantities in Pulsator
#3 (including labor and materials), reconfigure chemical metering pump piping, and
upgrade electrical to the Radio Building and Metal Storage Building, thereby increasing the
contract amount to $8,716,533.67; and,
WHEREAS, on May 25, 2010, the City Council of the City of Beaumont, Texas
passed Resolution No. 10 -144 authorizing Change Order No. 5, in the amount of
$155,026.00, to upgrade the Operations Building windows and doors to hurricane rating,
install concrete barriers at east side of Plant, install epoxy coating liner on Mixed Water
Channel floor and walls, install 10 concrete perimeter barriers between fence and filter
structure, install concrete perimeter barriers at north end of Plant, install concrete perimeter
barriers at Lawsons Canal Bridge on Marina Drive, and revise airlines at the pulsator
sludge valves, thereby increasing the contract amount to $8,871,559.67; and,
WHEREAS, on June 21, 2011, the City Council of the City of Beaumont, Texas
passed Resolution No. 11 -174 authorizing Change Order No. 6, in the amount of
$54,407.08, for the removal and shoring up of the filter media, improvements to the bulk
storage tank, repairs to the block wall coatings, improvements to the electrical wiring of the
Chemical Building, and the removal of Schedule 80 PVC piping and installation of
Schedule 40 galvanized steel piping as part of the wash water system in all three (3)
pulsators, thereby increasing the contract amount to $8,925,966.75; and,
WHEREAS, on October 30, 2012, the City Manager executed Change Order No.
7, in the amount of $5,337.00, thereby increasing the contract amount to $8,931,303.75;
and,
WHEREAS, on April 29, 2014, the City Council of the City of Beaumont, Texas
passed Resolution No. 14 -098 authorizing Change Order No. 8, in the amount of
$313,350.00, to furnish all labor, materials, and equipment to construct a bypass line to
transfer water from the inlet filters to the ground storage tank, thereby increasing the
contract amount to $9,244,653.75; and,
WHEREAS, Change Order No. 9, in the amount of $142,856.45, is required to
furnish all labor, materials and equipment to provide emergency repairs to remove the
concrete and backfill necessary areas around an existing 72 -inch line that transfers water
from the inlet filters to the ground storage tank, thereby increasing the contract amount to
$9,387,510.20;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 9 for emergency repairs in the amount of $142,856.45, thereby increasing the contract
amount to $9,387,510.20 for the Surface Water Treatment Plant Improvements Phase I
Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 9th day of
December, 2014.
,A
;s