HomeMy WebLinkAboutRES 14-225RESOLUTION NO.14 -225
WHEREAS, on April 9, 2013, the City Council of the City of Beaumont, Texas
passed Resolution No. 13 -082 awarding a contract in the amount of $12,330,865 to Allco,
LLC, of Beaumont, Texas, for the South Park Drainage Improvement Project; and,
WHEREAS, on August 12, 2013, the City Manager executed Change Order No. 1,
in the amount of $7,705 to furnish a temporary fence within the Chemtrade Chemical Plant,
thereby increasing the contract amount to $12,338,570; and,
WHEREAS, on October 21, 2013, the City Manager executed Change Order No.
2, in the amount of $9,863.99 for the construction of a concrete wingwall at the outfall
inside the Chemtrade Chemical Plant, thereby increasing the contract amount to
$12,348,433.99; and,
WHEREAS, on November 25, 2013, the City Manager executed Change Order No.
3, in the amount of $3,173.81 for the removal of a raised median for driveway access to
LIT and SETX Food Bank, thereby increasing the contract amount to $12,351,607.80; and,
WHEREAS, on February 20, 2014, the City Manager executed Change Order No.
4, in the amount of $5,665.38 for the addition of reinforcing steel in the concrete roadway,
thereby increasing the contract amount to $12,357,273.18; and,
WHEREAS, on March 4, 2014, the City Council of the City of Beaumont, Texas
passed Resolution No. 14 -057 authorizing the City Manager to execute Change Order No.
5, in the amount of $23,059.13, to include costs associated with realignment of the storm
sewerwithin the KCS railroad crossing easement and a deduction foreliminating the prime
coat and embankment material, thereby increasing the contract amount to $12,380,332.31;
and,
WHEREAS, on March 28, 2014, the City Manager executed Change Order No. 6,
in the amount of $6,294.22, for all costs associated with the installation of cement
stabilized backfill at the junction box on MILK feeder road, removal and installation of pipe
and inlets on East Lavaca, the removal and shoring costs and installation of field
modifications for a by -pass pumping access point, thereby increasing the contract amount
to $12,386,626.53; and,
WHEREAS, on May 27, 2014, the City Council of the City of Beaumont, Texas
passed Resolution No. 14 -119 authorizing the City Manager to execute Change Order No.
7, in the amount of $143,400, to include costs associated with bypass pumping of the
storm water within the construction area to the existing storm sewer system, thereby
increasing the contract amount to $12,530,026.53; and,
WHEREAS, Change Order No. 8, in the amount of $327,722.75, is required to
utilize the Hybrid Bore Process to install two new water lines under the railroad tracks and
special shoring due to the depth of the bore, thereby increasing the contract amount to
$12,857,749.28;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 8 for additional work described above, thereby increasing the contract amount by
$327,722.75 for a total contract amount of $12,857,749.28 for the South Park Drainage
Improvement Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 7th day of