HomeMy WebLinkAboutRES 14-086RESOLUTION NO.14-086
WHEREAS, on October 18, 2011, the City Council of the City of Beaumont, Texas,
passed Resolution No. 11-303 awarding a contract in the amount of $1,644,323 with
Brystar Contracting, Inc., of Beaumont, Texas, for the Sanitary Sewer Rehabilitation of
Small Diameter Mains Contract XXI Project; and,
WHEREAS, on August 14, 2012, the City Council of the City of Beaumont, Texas
passed Resolution No. 12-170 authorizing Change Order No. 1, in the amount of
$25,153.75, to furnish all necessary labor, materials, and equipment to pipeburst
approximately 2,140 linear feet of 6 -inch sanitary sewer lines with 8 -inch DR -17 HDPE;
delete 1,675 linear feet of 6 -inch sanitary sewer lines; remove and replace one existing
sanitary sewer manhole; furnish and install one end -of -line cleanout; replace two 4 -inch
short side service connections; replace one 4 -inch long side service connection; pre
televise three existing services; clean and televise approximately 465 linear feet of
deteriorated lines; and post televise 465 linear feet of rehabilitated sanitary sewer lines,
thereby increasing the contract amount to $1,669,476.75;
WHEREAS, on January 8, 2013, the City Council of the City of Beaumont, Texas
passed Resolution No. 13-001 authorizing Change Order No. 2 in the amount of $26,850
to furnish all necessary labor, materials, and equipment to pipeburst approximately 540
linear feet of 8 -inch sanitary sewer lines with 10 -inch DR -17 HDPE; furnish and install one
(1) sanitary sewer manhole; replace three (3) 4 -inch short side service connections;
replace two (2) 4 -inch long side service connections; pre televise five (5) existing services;
clean and televise approximately 540 linear feet of deteriorated lines; and post televise 540
feet of rehabilitated sanitary sewer lines, thereby increasing the contract amount to
1,696,326.75; and,
WHEREAS, Change Order No. 3 in the amount of ($45,870.91) is required to
furnish all necessary labor, materials, and equipment to pipeburst approximately 274.5
linear feet of 8 -inch sanitary sewer lines with 8 -inch DR -17 HDPE; furnish and install one
(1) sanitary sewer manhole; abandon seven (7) manholes in place; replace one 4 -inch long
side service connection; and, pre televise approximately 198.5 linear feet of deteriorated
lines. The proposed change order will also deduct 2,036 linear feet of 6 -inch sanitary
sewer lines; approximately 195 linear feet of 8 -inch sanitary sewer lines; stabilization of
nine (9) existing manholes; remove and replace 15 existing manholes with new ring and
cover; furnish and install five (5) end of line cleanouts; replace three (3) 4 -inch short side
service connections pre televise 86 existing services; and, post televise 2,056.5 linear feet
of rehabilitated sanitary sewer lines. This change order also includes the purchase of the
remaining materials on hand, thereby decreasing the contract amount to $1,650,455.84;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted;
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 3 in the amount of ($45,870.91), thereby decreasing the contract amount to
$1,650,455.84, forthe Sanitary Sewer Rehabilitation of Small Diameter Mains Contract XXI
Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 22nd day of
April, 2014.