HomeMy WebLinkAboutRES 14-044RESOLUTION NO.14 -044
WHEREAS, on March 20, 2012, the City Council of the City of Beaumont, Texas,
passed Resolution No. 12 -055 awarding a contract in the amount of $4,391,500 to Brystar
Contracting, Inc., of Beaumont Texas, for the Wastewater Treatment Plant Holding Pond
Project and Dredging of Ponds 1 and 2 Project; and,
WHEREAS, on May 15, 2012, the City Council of the City of Beaumont, Texas,
passed Resolution No. 12 -105 approving Change Order No. 1 in the amount of ($36,550)
for alternate materials related to the electrical components of the project, thereby
decreasing the contract amount to $4,354,950; and,
WHEREAS, on June 18, 2012, the City Manager executed Change Order No. 2 in
the amount of $9,000.00 to furnish all necessary supervision, labor, equipment, and
insurance to complete the loading and hauling of dirt from the City of Beaumont Waste
Water Treatment Plant to the dirt stockpile location on the City of Beaumont landfill in
tandem dump trucks, thereby increasing the contract amount to $4,363,950; and,
WHEREAS, on June 18, 2013, the City Council of the City of Beaumont, Texas,
passed Resolution No. 13 -129 approving Change Order No. 3 in the amount of $25,901.57
to delete the bar screen mechanism, furnish and install additional concrete for aeration
pads, increase Bid Item 3 for additional solids removal from Pond 1, provide for the
cleaning of solids from Pond 2, and delete Alternate Bid Item No. 2, thereby increasing the
contract amount to $4,389,851.57;; and,
WHEREAS. on September 10, 2013, the City Council of the City of Beaumont,
Texas, passed Resolution No. 13 -192 approving Change Order No. 4 in the amount of
$154,620 to provide the necessary supervision, labor, equipment, and insurance to load
and haul earthen material and construct an earthen levee sludge containment area,
thereby increasing the contract amount to $4,544,471.57; and,
WHEREAS, Change Order No. 5 in the amount of $22,457.61 is required to provide
the necessary supervision, labor, equipment, and insurance to install the proposed
Junction Box 12 on the existing dual 42" diameter effluent pipes due to a conflict with
existing electrical conduit banks, thereby increasing the contract amount to $4,566,929.18;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 5 for additional work described above, thereby increasing the contract amount by
$22,457.61 for a total contract amount of $4,566,929.18.