HomeMy WebLinkAboutRES 13-229 RESOLUTION NO.13-229
WHEREAS, on May 14, 2013, the City Council of the City of Beaumont, Texas
passed Resolution No. 13-110 awarding a contract in the amount of$1,124,900 to Goss
Building, Inc., of Beaumont, Texas, for the Municipal Court and EOC Building Third Floor
Renovation Project; and,
WHEREAS, a contingency allowance in the amount of$33,300 was included in the
above noted contract; and,
WHEREAS, Change Order No. 1 , in the amount of$9,877.57,was required to clean
water damage from unforeseen pipe damage in the fire protection sprinkler system and
additional work to provide code compliant fire protection sprinkler system upgrades to the
facility, thereby decreasing the contingency allowance to $23,422.43 and having no affect
on the total contract amount of $1,124,900; and,
WHEREAS, Change Order No. 2, in the amount of $7,939.80, was required to
provide and install an 8 inch backflow preventer and to replace an 8 inch pipe with a steel
band sleeve in accordance with State of Texas regulations, thereby decreasing the
contingency allowance to $15,482.63 and having no affect on the total contract amount of
$1 ,124,900; and,
WHEREAS, Change Order No. 3, in the amount of $24,320.87, is required to
relocate duct work, furnish and install partitions and doors, install panic hardware and
metal stud framing and drywall on all exposed masonry walls and partitions in the
toilet/shower areas. Contingency allowances in the amount of $15,482.63 have been
applied to the total cost of $24,320.87, thereby resulting in a change of a net amount of
$8,838.24, increasing the contract amount to $1,133,738.24;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 3 for additional work described above, thereby increasing the contract amount by
$15,482.63 for a total contract amount of$1 ,133,738.24 for the Municipal Court and EOC
Building Third Floor Renovation Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 15th day of
October, 2013.