HomeMy WebLinkAboutRES 13-195RESOLUTION NO. 13-195
BE IT RESOLVED BY THE CITY COUNCIL
OF THE CITY OF BEAUMONT:
THAT the FY 2014 Capital Program is hereby adopted. The Capital Program is
substantially in the form attached hereto as Exhibit "A." A public hearing was held August
27, 2013.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 17th day of
September, 2013.
f.
i
M or Becky A es -
RICH WITH OPPORTUNITY'
[1EA,t111ONT
T• E 0 X 0 A° S
May 14, 2013
City Council:
The proposed Capital Program for Fiscal Years 2014-2018 is hereby submitted. The Capital
Program is a plan prepared annually to provide for both short and long range physical
development within the City of Beaumont. The City Charter requires the submission of the
Capital Program to Council three (3) months prior to the final date for submission of the
budget, which is August 15th of each year. The Program is adopted with the annual
operating budget.
Generally, a capital improvement has the following characteristics: relatively high monetary
value (at least $100,000), long life (will last at least 10 years), and results in either the
creation of a capital asset, or the revitalization of one. Capital assets are resources owned
by the City which have monetary value, long-term character and will be held or used.
Examples are land, buildings, and improvements to land other than buildings. Included within
the above definition are the following specific items: purchase, improvement and
development of land; construction of new facilities for the delivery of City services;
remodeling of existing facilities; and the planningfengineering costs related to specific
improvements of the type listed above.
The Capital Program includes a listing of all Public Works, General Improvements and Water
and Sewer improvement projects along with project descriptions and cost estimates. Public
Works includes street and storm water drainage projects; General Improvements include
general municipal buildings and facility improvements. Water and Sewer includes all projects
related to water and sewer infrastructure.
Approved projects are classified in three phases* construction, design, or projects for
consideration. A project classified in the construction phase is currently under construction
or is projected to begin construction Within the recommended time schedule. Projects
classified as design have been or are currently being designed or projected to be designed
in the recommended time schedule. The design phase may also include projects where the
acquisition of rights-of-way or real property is currently underway or is projected to be
acquired in the recommended time schedule. Projects classified as for consideration will
be considered in the future as funding becomes available.
197
0.111 M
Financing for the Capital Program is provided by the "cash flow" approach, whereby debt is
issued to complete ongoing projects and to commence new projects. This approach provides
the most efficient use of citizens' dollars by allowing multi-year projects to be initiated without
issuing debt for the full cost of the projects at the time of project commencement. All
available funding sources are considered including Certificates of Obligation, grant funding
from various agencies, Water and Sewer Revenue Bonds, and available cash.
Based on a "cash flow" approach, the City issues Certificates of Obligation (CO's) on an as
needed basis, to provide sufficient cash flow for active Public Works and General
Improvement projects.
The Water Utilities Department has taken an aggressive approach to identify and implement
necessary improvements to the water and sewer systems. In many instances, these
renovations are required to meet federal and state mandates as well as meet the needs of
the City's growth. Funding for Water and Sewer projects is determined in a similar manner
as the Public Works and General Improvement projects in that it uses the cash flow
approach; however, Water Revenue Bonds are issued rather than tax supported Certificates
of Obligation. This type of bond is serviced utilizing revenues from water and sewer
customers.
Through projects in the Capital Program, the City of Beaumont strives to enhance the quality
of life for its residents. This plan represents our best effort to identify projects that provide the
greatest benefit to the citizens of Beaumont.
Respectfully Submitted,
L
Kyle Hayes
City Manager
198
PUBLIC WORKS PROJECTS
Construction Phase
Avenue A - Washington to US 69 S
Concord Road - Phase IV - East Lucas to Hwy. 105
Delaware Overlay - Concord to Dowlen
Magnolia - Gill to East Lucas
Magnolia Overlay - Fannin to Gill
Northwest Parkway
Old Dowlen - Dowlen to Hwy. 105
Seventh Street - IH -10 to Laurel
South Park Relief
Storm Water Master Plan
Street Rehabilitation Program
Washington - IH -10 to ML King
Design Phase
College Street - IH -10 to Goliad
Dowlen - College to Walden
Dowlen - US 69 N to Delaware
Gladys Street - IH -10 to Dowlen
Laurel - I1-1-10 to Office Park
North Street - ML King to Twenty -Third
Regina - Howell to Thomas
Washington - Langham to Major
Estimated
Cost
$ 7,400,000 [11
18,000,000 [2]
2,000,000
3,500,000 [3)
4,750,000
8,000,000 [4]
9,000,000 [5]
6,400,000 [4]
13,552,900 [6]
1,500,000
15,000,000
29,500,000 [4]
Estimated
Cost
12,700,000
15,500,000 [7]
16,000,000 [4]
5,000,000
6,490,000
12,800,000
2,200,000
13,000,000 [8)
[11 Includes 2009 Disaster Recovery Fund - Hurricane Ike funding of 36,400,000.
[2] Includes Federal Highway Administration funding up to $7,560,109
[3] Includes 2009 Disaster Recovery Fund - Hurricane Ike funding of $2,700,000.
[4] Includes Airport Oil and Gas Revenue.
[5] Includes TxDOT funding up to $4,000,000 and $5,000,000 from Airport Oil & Gas Revenues
[6) Includes 2009 Disaster Recovery Fund - Hurricane Ike funding of $11,339,400.
(7) Includes Federal Highway Administration funding of $2,764,800.
[8) Includes Federal Highway Admini tration funding of $3,080,D00.
Recommended
Time Schedule
FY 2014 - 2015
Recommended
Time Schedule
FY 2014 - 2015
PUBLIC WORKS PROJECTS
Projects for Consideration
Babe Zaharias Drive
Belvedere - Regina to Dead End
Caldwood Outfall
Dowlen Road - Delaware to Gladys
Downtown Improvements
Wall - Neches to ML King
Crockett/Laurel - Pearl to Magnolia
East Lucas - US 69 N to Pi;ie
Eleventh Street - Washington to US 69 N
Folsom Extension
Gulf Street - Live Oak to Delaware
High School Ditch
Howell Street - Regina to Sue
Irving Street - Buford to Washington
North Main Street - Calder to Railroad Tracks
Phelan Boulevard - IH -10 to Dowlen
Pine Street - IH -10 to Crockett
Sabine Pass - Emmett to ML King
Estimated
Cost
2,150,000
2,750,000
9,000,000
7,000,000
7,800,000
2,500,000
18,270,000
26,000,000
800,000
3,565,000
12,600,000
2,625,000
5,000,000
2,860,000
24,000,000
5,230,000
4,000,000
Recommended
Time Schedule
FY 2014 - 2018
GENERAL IMPROVEMENT PROJECTS
Construction Phase
Athletic Complex Tennis Center
Civic Center Improvements
Fire Station No, 1 Relocation - Phase I
Fire Station No. 2 Relocation
Fire Station No. 11 Relocation
Hike and Bike Trail Phase 11 - Major to Dowlen
Public Health Complex
Riverfront Development
Senior Center
Design Phase
Airport Hangar
Fire Station No. 1 Complex • Phase II
Fleet Fire Maintenance Facility
Tyrrell Park Nature and Birding Center
Proiects for Consideration
Fleet Service Center Improvements
Transportation Operations Shop
Estimated
Cost
3,300,000
500,000
6,500,000
2,400,000
3,000,000
826,400
8,200,000
5,000,000
4,500,000
1,500,000
4,500,000
2,000,000
3,500,000
2,500,000
2,600,000
[2]
[3]
[4]
[1] Grant awarded from Hurricane Ike Disaster Recovery Program in the amount of $2,400,000.
[2] Grant awarded from the Federal Transportation Enhancement Program in the amount of $661,120,
with a 20% match of $165,280.
[3] Grant awarded from Hurricane Ike Disaster Recovery Program in the amount of $7,000,000.
[4] Municipal Airport Fund.
Recommended
Time Schedule
FY 2014 - 2015
Recommended
Time Schedule
FY 2014 - 2015
Recommended
Time Schedule
FY 2014 - 2018
WATER AND SEWER PROJECTS
Construction Phase
Water Projects:
Additional Water Supply System
AMI /AMRlLeak Detection
Automatic Flushing Devices
Loeb Well No. 1 Electrical Improvements
Water Line and Fire Hydrant. Installation /Replacement
Water Treatment Plant Improvements - Phase II Construction
Weiss Bluff Pumping Station
Sewer Projects:
36" Longfellow Interceptor Rehabilitation
48" Interceptor Rehabilitation
54" Central Trunk Rehabilitatioi
Downtown Sanitary Sewer Lift Station
Florida Avenue & Fannett Road Interceptors
Lift Station Repairs
Primer Sanitary Sewer Lift Station
Sanitary Sewer Interceptor Rehabilitation - Harriot Street Lift
Station to the Wastewater Treatment Plant
Sanitary Sewer Rehabilitation - Small Mains (Pipe Bursting)
Wastewater Treatment Plant Electrical Improvements
Wastewater Treatment Plant: Underground Piping Rehabilitation
Wastewater Treatment Plant Sudge Thickener Rehabilitation
Wafer/Sewer for Street Projects:
Avenue A - Washington To US 69 S
Concord Road - Phase IV - East Lucas to Hwy. 105
Magnolia - Gill to East Lucas
Northwest Parkway
Old Dowlen - Dowlen to Hwy. 105
Seventh Street - IH -10 to Laurel
Washington - IH -10 to ML King
Estimated
Cost
$ 8,000,000
15,000,000
100,000
700,000
4,000,000
7,500,000
3,000,000
3,000,000
3,400, 000
4,410, 000
2,300, 000
2,400, 000
600,000
1,100,000
4,200,000
6,000,000
1,400,000
1,200,000
650,000
780,000
1,368,000
450,000
1,500,000
636,000
612,000
2,400, 000
Recommended
Time Schedule
FY 2014 - 2015
WATER AND SEWER PROJECTS
Desicin Phase
Water Projects:
36" Transmission Line
Bunns Bluff Pumping Station
Drinking Water Quality Assessment
Keith Road Water Line Installation - Phelan to Dishman Road
Water Bottling Plant
Weiss Canal Stabilization
Sewer Projects:
66" and 21" Trunk Line Rehab ; €itation
72" and 36" Trunk Line Rehabilitation
Arthur Lane, Holiday Street, Tyrrell Park and Voth Road Lift Stations
Degritter - Wastewater Treatment Plant
Sanitary Sewer Interceptors Rehabilitation - 24" through 48"
Sanitary Sewer Interceptors Rehabilitation - 24" through 36"
Sanitary Sewer Interceptor Rehabilitation - Matthew Road and
Phelan Blvd. to Major Drive North to Folsom
Wall and Avenue C Lift Station
Wastewater Treatment Plant Chlorine Disinfection
System Improvements
Wastewater Treatment Plant Clarifiers Rehabilitation
Water /Sewer for Street Projects:
College Street - IH -10 to Goliad
Delaware - Concord to Dowlen
Dowlen College to Walden
Dowlen US 69 N to Delaware
Gladys Street - iH -10 to Dowlen
Laurel ., IH -10 to Office Park
Magnolia - Laurel to Gill
North Street - ML King to Twenty -Third
Regina - Howell to Thomas
Washington - Langham to ;Major
Estimated
Cost
8,800,000
2,800,000
275,000
720,000
1,500,000
3,500,000
4,000,000
6,000,000
1,500,000
8,000,000
3,700,000
3,800,000
6,000,000
1,400,000
2,500,000
3,800,000
1,008,000
3,276,000
1,872,000
1,092,000
1,536,000
588,000
2,100,000
1,208,000
456,000
2,076,000
Recommended
Time Schedule
FY 2014 -2015
WATER AND SEWER PROJECTS
Projects for Consideration
Wastewater Treatment Plant Ground Improvements
Water /Sewer for Street Projects:
Babe Zaharias Drive
Belvedere - Regina to Dead End
Dowlen Road - Folsom to Gladys
East Lucas - US 69 N to Pine
Eleventh Street - Washingtor to US 69 N
Folsom Extension
Gulf Street - Live Oak to Delaware
Howell - Regina to Sue
Irving Street - Buford to Washington
North Main Street - Calder to Railroad Tracks
Phelan Boulevard - IH -10 to Dowlen
Pine Street - IH -10 to Crockett
Sabine Pass - Emmett to ML King
Estimated
Cost
50,000
380,000
756,000
2,304,000
528,000
220,000
624,000
467,000
539,000
204,000
708,000
528,000
1,020,000
Recommended
Time Schedule
FY 2014 - 2018