HomeMy WebLinkAboutRES 13-184 RESOLUTION NO.13-184
WHEREAS, on April 20, 2010, the City Council of the City of Beaumont, Texas,
passed Resolution No. 10-100 awarding a contract in the amount of $8,126,000 to C. F.
Jordan Construction, L.L.C., of Houston, Texas, for Alternates 1, 2, 3, 4, 5, 6 and 8 for the
construction of the Event Centre, Lake and Lawn in downtown Beaumont; and,
WHEREAS, on December 14, 2010, the City Council of the City of Beaumont,
Texas passed Resolution No. 10-326 approving Change Order No. 1 in the amount of
$60,101 that included costs associated with the unforseen casing and concrete work,
additional excavation and rough grading beyond the original scope of work, substitution of
aluminum composite exterior building panels, thereby increasing the contract amount to
$8,186,101 and extending the completion time by twenty-eight (28) days; and,
WHEREAS, on May 3, 2011, the City Council of the City of Beaumont, Texas
passed Resolution No. 11-138 approving Change Order No. 2 in the amount of $56,647
for additional costs incurred by the contractor, C.F. Jordan Construction, L.L.C., for the
excavation and removal of fill material, thereby increasing the contract amount to
$8,242,748; and,
WHEREAS, on June 20, 2011, Change Order No. 3 in the amount of$2,031 .00 was
executed to extend piping and locate isolation valves for accessibility, thereby increasing
the contract amount to $8,244,779 ; and,
WHEREAS, on August 17, 2011 , Change Order No. 4 in the amount of($7,850.00)
was executed for the use of alternate materials, thereby decreasing the contract amount
to $8,236,929; and,
WHEREAS, on December 20, 2011, the City Council of the City of Beaumont,
Texas passed Resolution No. 11-357 approving Change Order No. 5 in the amount of
$13,009 for additional framing material and electrical outlets, thereby increasing the
contract amount to $8,249,938; and,
WHEREAS, on February 7, 2012, the City Council of the City of Beaumont, Texas,
passed Resolution No. 12-023 approving Change Order No. 6 in the amount of $14,421
for the addition of a mechanical fastening system to granite pieces which are partially
submerged at the water's edge, the addition of bird screens in all four overflow spouts, and
the replacement of one overflow 8" nozzle with a 10" nozzle, thereby increasing the
contract amount to $8,264,359; and,
WHEREAS, on February 24, 2012, Change Order No. 7 in the amount: of $1,164
was executed for additional data drops and concrete curbs,thereby increasing the contract
amount to $8,265,523; and,
WHEREAS, Change Order No. 8, provided additional time for landscaping and did
not affect the total contract amount; and,
WHEREAS, on March 20, 2012, the City Council of the City of Beaumont, Texas,
passed Resolution No. 12-051 approving Change Order No. 9 in the amount of $44,863
for costs associated with the installation of an electrical panel on the mechanical building
located on the north side of the Event Centre, thereby increasing the contract amount to
$8,310,386; and,
WHEREAS, on April 24, 2012, Change Order No. 10 in the amount of$6,096 was
executed for the modification of the canopy to allow sprinkler pipe to be installed, the
installation of steel hangers for the large speaker, additional phone lines to the data
cabinet, and an additional electrical outlet, thereby increasing the contract amount to
$8,316,482; and,
WHEREAS, on June 18, 2012, Change Order No. 11 in the amount of$3,349 was
executed for the replacement of two (2) sinks in the catering area with deeper sinks and
different faucets than were originally specified, thereby increasing the contract amount to
$8,319,831; and,
WHEREAS, on June 18, 2012, Change Order No.12 in the amount of$2,509 was
executed for additional hardware for resin panels in the hall and vestibule area, thereby
increasing the contract amount to $8,322,340; and,
WHEREAS, Change Order No, 13 in the amount of ($25,462.45) is required for
deleting the installation of a water well in the lake in exchange for various other items
involved in the construction project as described in Exhibit "A," attached hereto; and,
WHEREAS, all disputed claims have been resolved and the project has been
inspected and completed and should be accepted;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 13 for work described above and in Exhibit "A," attached hereto; and,
BE IT FURTHER RESOLVED THAT the Downtown Event Centre Project be and
the same is hereby accepted; and,
BE IT ALSO RESOLVED THAT the City Manager is hereby authorized to make a
final settlement payment in the amount of$598,968.82 to C.F. Jordan Construction, L.L.C.;
and,
BE IT ALSO RESOLVED THAT the City Manager is hereby authorized to execute
all documents necessary to the settlement of the claims of C.F. Jordan Construction, L.L.C.
pertaining to the Event Centre Project.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 27th day of
August, 2013. , my AA�j*\Ik\
U �%11�1
U-1 - Mayor Becky Ames -
If I
Aw
-;
Proposed Change Order 13
Item No. Description Amount Days
Requested
CIOD046 Doors and hardware had to be changed from original $7,512.00
design ro meet TDI regulations
CIOD054 Due to field adjustment in curtain wall panel reduced $7,077.00
height, cost for the addition of metal panels
CIOD064 Architect specified hardwired faucets in outdoor $1,210.00
restrooms should have been air powered
CIOD048 Technology services needed additional power source in $2,642.00
data room
CIOD065 Metal Address Numbers installed on exterior of $815.00
building
CIOD062 During construction, egress doors height changed to $340,00
meet TD],exit lights specified were too large, had to
reorder
CIOD03 7 Window frames on south side had to be demolished and $410.00
reinstal led to match brick alignment
Directive 41 Delete Irrigation Well <$135,410>
CIOD007 Structural Steel changes to beam size for canopy. $21,936.00 19
Materials were changed from original specifications
CIOD024 Additional framing material required to meet $23,423.75 11
engineered shop drawings
C:IOD027 Design changes in structural beams for cantelevered $13,048.00 17
canopy resulted in addition of moment welds
CIOD030 Modification to window wall to control movement $14,516.00 9
CIOD036 & Irrigation system redesigned resulting in delay to $30,426.80
CIOD044 landscape contractor. Provided additional services to
maintain live oak trees and grounds during this period.
CIOD061 Modified toilet partitions to reduce swaying $1,591.00
Lake-Overflow Modification <$15,000>
Total <$25,462.45> 56
EXHIBIT "A"