HomeMy WebLinkAboutRES 13-038RESOLUTION NO. 13 -038
WHEREAS, on June 26, 2012, the City Council of the City of Beaumont, Texas,
passed Resolution No.12 -139 awarding a contract in the amount of $332,100 to Allco, Inc.,
of Beaumont, Texas, for the East Lucas Drainage Improvement Rehabilitation Project: and,
WHEREAS, Change Order No. 1 in the amount of $1,991 was required for all cost
associated with the items to resolve drainage conflict with the proposed sidewalk, thereby
increasing the project amount to $334,091; and,
WHEREAS, Change Order No. 2 in the amount of ($74.75) is required to adjust the
quantities actually used during the performance of the project, thereby decreasing the
contract amount to $334,016.25; and,
WHEREAS, the project has been inspected and completed in accordance with the
terms and conditions of the contract and should be accepted;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 2 to adjust quantities actually used during the performance of the project, thereby
decreasing the contract amount by ($74.75) for a total contract amount of $334,016.25;
and,
BE IT FURTHER RESOLVED THAT the East Lucas Drainage Improvement
Rehabilitation Project be and the same is hereby accepted; and,
BE IT ALSO RESOLVED THAT the City Manager is hereby authorized to make final
payment in the amount of $34,115.66 to Allco, Inc.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 12th day of
February, 2013.