HomeMy WebLinkAboutRES 13-018RESOLUTION NO. 13 -018
WHEREAS, on March 20, 2012, the City Council of the City of Beaumont, Texas,
passed Resolution No. 12 -057 awarding a contract in the amount of $738,473 to
Horseshoe Construction, Inc., of LaPorte, Texas, for the Sanitary Sewer Rehabilitation of
Small Diameter Mains Contract XXII Project; and,
WHEREAS, on June 5, 2012, the City Council of the City of Beaumont, Texas,
passed Resolution No. 12 -122 authorizing Change Order No. 1 in the amount of $90,900
to furnish all necessary labor, materials, and equipment to rehabilitate approximately 1,900
linear feet of 6 -inch sanitary sewer lines located south of Trinidad Street and north of
LaSalle Street between Magnolia Avenue and Berkley Avenue, thereby increasing the
contract amount to $829,373;
WHEREAS, Change Order No. 2 in the amount of ($26,567) is required to adjust
quantities resulting from approved field changes and actual construction, thereby
decreasing the contract amount to $802,806;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 2 to adjust quantities resulting from approved field changes and actual construction,
thereby decreasing the contract amount by ($26,567) for a total contract amount of
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 22nd day of
January, 2013.