HomeMy WebLinkAboutRES 12-114 RESOLUTION NO. 12 -114
WHEREAS, on January 19, 2010,the City Council of the City of Beaumont, Texas,
passed Resolution No. 10-010 awarding a contract in the amount of $4,992,554.15 to
Reytec Construction Resources, Inc., of Houston, Texas, for the Fannin Street Drainage
Improvement Project; and,
WHEREAS, on June 22, 2010, the City Council of the City of Beaumont, Texas,
passed Resolution No. 10-167 for Change Order No. 1 in the amount of$257,361.10 to
add and install new waterlines, fire hydrants, gate valves and fittings, and water
connections, thereby increasing the contract amount to $5,249,915.25; and,
WHEREAS, Change Order No.2 in the amount of$7,605.00 was signed by the City
Manager on November 6,2010,thereby increasing the contract amount to$5,257,520.25;
and,
WHEREAS, on January 18, 2011, the City Council of the City of Beaumont, Texas
passed Resolution No. 11-026 for Change Order No. 3 to furnish and install 386 linear feet
of two-inch force main and water & sanitary sewer connections with appurtenances,
thereby increasing the contract amount to $5,285,848.25; and,
WHEREAS, on March 22, 2011, the City Council of the City of Beaumont, Texas
passed Resolution No. 11-108 for Change Order No. 4 in the amount of$449,778.75 to
reconstruct Eighth Street from Stagg to College Street from an existing two lane asphalt
roadway to a concrete roadway with two lanes in each direction with sidewalks on each
side and furnish and install 1195 linear feet of eight(8)inch water main and sanitary sewer
connections with appurtenances,thereby increasing the contract amount to$5,735,627.00;
and,
WHEREAS, Change Order No. 5 in the amount of$2,400.00 was signed by the City
Manager on June 14,2011,thereby increasing the contract amount to$5,738,027.00;and,
WHEREAS, Change Order No.6 in the amount of($39,575.58)is required to adjust
the estimated quantities actually used during the performance of the project, thereby
decreasing the contract amount to $5,698,451.42;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 6 for additional work described above, thereby decreasing the contract amount by
($39,575.58)for a total contract amount of$5,698,451.42; and,
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to make
final payment in the amount of$175,803.54 to Reytec Construction Resources, Inc.for the
Fannin Street Drainage Improvement Project.