HomeMy WebLinkAboutRES 12-052 RESOLUTION NO. 12-052
WHEREAS, on April 20, 2010, the City Council of the City of Beaumont, Texas,
passed Resolution No. 10-101 awarding a contract in the amount of $2,105,056.80 to
Brystar Contracting, Inc. for the East Lucas Lift Station and Force Main and Interceptor
Rehabilitation Project; and,
WHEREAS, on August 9, 2011, the City Council of the City of Beaumont, Texas,
passed Resolution No. 11-212 approving Change Order No. 1 in the amount of
$37,472.05, thereby increasing the contract amount to $2,142,528.85; and,
WHEREAS, proposed Change Order No. 2, in the amount of$29,589.66, includes
an increase to the allowance for electrical service, additional embedment material and
additional 36" HDPE gravity sanitary sewer line, a decrease in the amount of 12" PVC
sanitary sewer line, deduction of two (2) air release valves, a deduction in the number of
replaced short side services and deductions in the amount for bypass pumping, special
shoring and cement stabilized sand, thereby increasing the contract amount to
$2,172,118.51;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 2 in the amount of $29,589.66, thereby increasing the contract amount to
$2,172,118.51.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 20th day of
March, 2012.
y - Mayor Becky Ames -
1�