HomeMy WebLinkAboutRES 12-023 RESOLUTION NO. 12-023
WHEREAS, on April 20, 2010, the City Council of the City of Beaumont, Texas,
passed Resolution No. 10-100 awarding a contract in the amount of$8,126,000 to C. F.
Jordan Construction, L.L.C., of Houston, Texas, for Alternates 1, 2, 3, 4, 5, 6 and 8 for the
construction of the Event Center, Lake and Lawn in downtown Beaumont; and
WHEREAS, on December 14, 2010, the City Council of the City of Beaumont,
Texas passed Resolution No. 10-326 for Change Order No. 1 in the amount of$60,101
that included costs associated with the unforseen casing and concrete work, additional
excavation and rough grading beyond the original scope of work, substitution of aluminum
composite exterior building panels, thereby increasing the contract amount to $8,186,101
and extending the completion time by twenty-eight (28) days;
WHEREAS, on May 3, 2011, the City Council of the City of Beaumont, Texas
passed Resolution No. 11-138 for Change Order No. 2 in the amount of $56,647 for
additional costs incurred by the contractor, C.F. Jordan Construction, L.L.C., for the
excavation and removal of fill material, thereby increasing the contract amount to
$8,242,748;
WHEREAS,on June 20,2011, Change Order No.3 in the amount of$2,031.00 was
executed to extend piping and locate isolation valves for accessibility, thereby increasing
the contract amount to $8,244,779 ; and,
WHEREAS, on August 17, 2011, Change Order No. 4 in the amount of($7,850.00)
was executed for the use of alternate materials, thereby decreasing the contract amount
to $8,236,929; and,
WHEREAS, on December 20, 2011, the City Council of the City of Beaumont,
Texas passed Resolution No. 11-357 for Change Order No. 5 in the amount of$13,009 for
additional framing material and electrical outlets, thereby increasing the contract amount
to $8,249,938; and,
WHEREAS, Change Order No. 6 in the amount of $14,421 is necessary for the
addition of a mechanical fastening system to granite pieces which are partially submerged
at the water's edge, the addition of bird screens in all four overflow spouts, and the
replacement of one overflow 8" nozzle with a 10" nozzle, thereby increasing the contract
amount to $8,264,359;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 6 for additional work described above, thereby increasing the contract amount by
$14,421 for a total contract amount of$8,264,359.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 7th day of
February, 2012.