HomeMy WebLinkAboutRES 11-354 RESOLUTION NO. 11-354 WHEREAS, on June 29, 2010, the City Council of the City of Beaumont, Texas, passed Resolution No.10-173 awarding a contract in the amount of $9,879,522.15 to Reytec Construction Resources, Inc., of Houston,Texas,for the Calder Avenue Drainage and Pavement Improvement Project - Phase III; and, WHEREAS, Change Order No. 1 in the amount of$94,928 was required for adding construction items and reducing construction item quantities to the Calder Avenue Drainage and Pavement Improvement Project- Phase 111,thereby increasing the contract amount to $9,974,450.15; and, WHEREAS, Change Order No. 2 in the amount of$9,850.00 was required for costs associated with the existing drainage and the proposed waterline installation conflicts, thereby increasing the contract amount to $9,984,300.15 ; and, WHEREAS, Change Order No. 3 in the amount of $68,697.30 was required for adding construction items and reducing construction item quantities necessary to resolve drainage and water line conflicts, thereby increasing the contract amount to $10,052,997.45; and, WHEREAS, Change Order No. 4 in the amount of ($188,276.85) is required for items to resolve tree,tree grate& pit, sidewalk and retaining wall adjustments and sanitary sewer line adjustments, thereby decreasing the contract amount to $9,864,720.60; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the statements and findings set out in the preamble to this resolution are hereby, in all things, approved and adopted; and, THAT the City Manager be and he is hereby authorized to execute Change Order No. 4 for additional work described above, thereby decreasing the contract amount by ($188,276.85) for total contract amount of$9,867,079.20. PASSED BY THE CITY COUNCIL of the City of Beaumont this the 13th day of December, 2011. - or Becky Ames