HomeMy WebLinkAboutRES 11-354 RESOLUTION NO. 11-354
WHEREAS, on June 29, 2010, the City Council of the City of Beaumont, Texas,
passed Resolution No.10-173 awarding a contract in the amount of $9,879,522.15 to
Reytec Construction Resources, Inc., of Houston,Texas,for the Calder Avenue Drainage
and Pavement Improvement Project - Phase III; and,
WHEREAS, Change Order No. 1 in the amount of$94,928 was required for adding
construction items and reducing construction item quantities to the Calder Avenue
Drainage and Pavement Improvement Project- Phase 111,thereby increasing the contract
amount to $9,974,450.15; and,
WHEREAS, Change Order No. 2 in the amount of$9,850.00 was required for costs
associated with the existing drainage and the proposed waterline installation conflicts,
thereby increasing the contract amount to $9,984,300.15 ; and,
WHEREAS, Change Order No. 3 in the amount of $68,697.30 was required for
adding construction items and reducing construction item quantities necessary to resolve
drainage and water line conflicts, thereby increasing the contract amount to
$10,052,997.45; and,
WHEREAS, Change Order No. 4 in the amount of ($188,276.85) is required for
items to resolve tree,tree grate& pit, sidewalk and retaining wall adjustments and sanitary
sewer line adjustments, thereby decreasing the contract amount to $9,864,720.60;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 4 for additional work described above, thereby decreasing the contract amount by
($188,276.85) for total contract amount of$9,867,079.20.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 13th day of
December, 2011.
- or Becky Ames