HomeMy WebLinkAboutRES 11-320 RESOLUTION NO. 11-320
WHEREAS, on December 14, 2010, the City Council of the City of Beaumont,
Texas, passed Resolution No. 10-322 awarding a contract in the amount of$3,022,510.00
to Russell Marine, LLC, of Channelview, Texas, for the Riverfront Park Bank Stabilization
Project; and,
WHEREAS, Change Order No. 1 in the amount of $41,190.00 was required for
unforeseen work due to the failure of the concrete bulkhead wall, thereby increasing the
contract amount to $3,063,700.00; and,
WHEREAS, Change Order No. 2 in the amount of $35,953.24 was required for
removing and disposing submerged timber pilings and the replacement of a damaged 36
inch outfall pipe, thereby increasing the contract amount to $3,099,653.24;
WHEREAS, Change Order No. 3 in the amount of$11,275.00 was required for the
replacement of approximately 850 square feet of sidewalk, 14 linear feet of concrete cap,
as well as the installation of two (2) additional bollards, thereby increasing the contract
amount to $3,110,928.24; and,
WHEREAS, Change Order No. 4 in the amount of($1,250.00)was required for the
elimination of hydro-mulching, thereby decreasing the contract amount to$3,109,678.24;
and,
WHEREAS, Change Order No. 5 in the amount of($21,600.00) is required for the
reduction of flowable fill material, thereby decreasing the contract amount to
$3,088,078.24;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 5 for additional work described above, thereby decreasing the contract amount by
($21,600.00) for a total contract amount of$3,088,078.24.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 15th day of
November, 2011.
ayor Becky Ames -