HomeMy WebLinkAboutRES 11-259 RESOLUTION NO. 11-259
WHEREAS, on March 8, 2011, the City Council of the City of Beaumont, Texas,
passed Resolution No. 11-096 awarding a contract in the amount of$948,949.55 to Brystar
Contracting, Inc., of Beaumont, Texas, for the Cartwright/Corley Drainage Project to
include drainage boxes, street pavement and water& sewer utility service lines; and,
WHEREAS, Change Order No. 1 in the amount of$38,800 was required to furnish
all labor, equipment, materials, and supervision associated with installing a new sanitary
sewer line on Corley Street between 5th and 6th Streets on the north side of the road,
thereby increasing the contract amount to $987,749.55; and,
WHEREAS, Change Order No. 2 in the amount of$72,092 is required for adding
construction items for sidewalks and driveways to the Cartwright/Corley Drainage Project,
thereby increasing the contract amount to $1,059,841.55;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 2 for additional work described above, thereby increasing the contract amount by
$72,092, for a total contract amount of$1,059,841.55.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 13th day of
September, 2011.
ti - ayor Becky Ames -