HomeMy WebLinkAboutRES 11-230 RESOLUTION NO. 11-230
WHEREAS, on June 2, 2009, the City Council of the City of Beaumont, Texas,
passed Resolution No. 09-165 awarding a contract in the amount of $24,616,416.25 to
BRH-Garver Construction, L.P., of Houston, Texas, for the Calder Avenue Drainage and
Pavement Improvement Project, Phase II; and
WHEREAS, on May 25, 2010, the City Manager signed Change Order No. 1 in the
amount of($7,119.38), thereby decreasing the contract amount to $24,609,296.87; and
WHEREAS, Change Order No.2 in the amount of$224,647.57 was required to add
and delete construction item quantities for roadway and drainage system improvements,
thereby increasing the contract amount to $24,833,944.44; and,
WHEREAS, Change Order No. 3 in the amount of ($649,931.89) is required for
adding construction items and reducing construction item quantities, thereby decreasing
the contract amount to $24,184,012.55;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
That the City Manager be and he is hereby authorized to execute Change Order
No. 3 for additional work described above, thereby decreasing the contract amount by
($649,931.89)for a total contract amount of$24,184,012.55.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 16th day of
August, 2011. h04