WHEREAS, on June 29, 2010, the City Council of the City of Beaumont, Texas,
passed Resolution No. 10-174 awarding a contract in the amount of$3,844,851.18 to C.
F. Jordan Construction, L.L.C., for the Event Center Area Paving and Drainage
Improvements Project; and,
WHEREAS, Change Order No. 1 in the amount of$156,279.43 was required for the
installation of newwater mains and appurtenances,thereby increasing the contract amount
to $4,001,130.61; and,
WHEREAS, Change Order No. 2 in the amount of $87,556.40 is required to add
item quantities to the contract, thereby increasing the contract amount to $4,088,687.01;
and,
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 2 in the amount of $87,556.40, thereby increasing the contract amount to
$4,088,687.01.
PASSED BY THE CITY COUP a City of Beaumont this the 9th day of
August, 2011. ~ '
Mayor Becky Ames -
• r
CITY OF BEAUMONT
DATE: 19 JULY 2011
PROJECT: EVENT CENTER AREA PAVING AND DRAINAGE IMPROVEMENTS
OWNER: CITY OF BEAUMONT
CONTRACTOR: CF JORDAN CONSTRUCTION,L.L.C.
CHANGE ORDER NO.: 02
4iil3
Add Construction Items and/or quantities to the Contract:
Item Item Description Unit Original New Unit Amount
No. Code Quantity Quantity Price
DRAINAGE AND PAVING
INSTALL 2-1/2"x 200 LF PVC CONDUIT FOR ENTERGY RE-FEED
4640 001 TO BLDG @ JEFFERSON COR CROCKETT(COMP IN PL)(INCL LF 0 200.00 $35.02 $7,004.00
CLEAN UP)
4640 002 INSTALL 3"x 1350 LF PVC SCHD 40 CONDUIT FOR FIBER OPTIC LF 0 1350.00 $37.52 $50,649.00
WITH 5-GRND BOX(COMP.IN PL.)
4640 003 INSTALL 8"x 108 LF PVC W/2-24"x 24"GRATE INLETS INCL. LS 0 1.00 $9,667.00 $9,667.00
CEM STAB SAND BKFL(COMP.IN PL.)@ CROCKETT&NECHES
INSTALL 10"x 160 LF HDPE DRAIN&6"x 60 LF x 6 EA.DOWN
4640 004 SPOUT DRAINS @ EXIST BLDG AT CROCKETT COR NECHES, IS 0 1.00 $15,089.00 $159089.00
INCL.12"x 12"GRATE(COMP.IN PL.)(INCL FITTINGS&EX
BRICK RESTORATION)
INSTALL 4"PVC CONDUIT(SCHD 40xINCL 30 LF SCHD 80,
618 001 BENDS,ELBOWS,COUPLINGS&PLUGSXCOMPL.IN PLACE) LF 0 230.00 $22.38 $5,147.40
CROSSING JEFFERSON
ADD TOTAL AMOUNT $87 56.40
ORIGINAL CONTRACT AMOUNT: $3,844,851.18
NET FROM PREVIOUS CHANGE ORDERS: $49001,130.61
TOTAL AMOUNT OF THIS CHANGE ORDER: $879556.40
PERCENT OF THIS CHANGE ORDER: 2.28%
TOTAL PERCENT CHANGE ORDER TO DATE: 6.34%
NEW CONTRACT AMOUNT: $4,088,687.01
`•`` ':
TA :•••::........:•.•:•.•:•.•.•............................:.:..•.•.•.•.•.•••••.•.••.•.••.•.•
ACCEPTED BY:
KENNETH COUSINS,CF JORDAN
CONSTRUCTION,LLC
APPROVED BY: ,I aww
v
HASSAN SHOMALZADEH,P.E.
CHIEF ENGINEER L l
PATRIC DONART,P.E. KYLE HAYES,CITY MANAGER
PUBLIC WORKS DIRECTOR
ATTESTED BY:
TINA BROUSSARD,CITY CLERK