HomeMy WebLinkAboutRES 11-212 RESOLUTION NO. 11-212
WHEREAS, on April 20, 2010, the City Council of the City of Beaumont, Texas,
P assed Resolution No. 10-101 awarding a contract in the amount of $2,105,056.80 to
Brystar Contracting, Inc. for the East Lucas Lift Station and Force Main and Interceptor
Rehabilitation Project; and,
WHEREAS, Change Order No. 1 in the amount of$37,472.05 is required for the
removal and disposal of trees on or adjacent to the lift station site, adjustments to an
existing 36"RCP storm line to allow for the installation of the proposed 24"gravity sanitary
sewer line, replacement of proposed light fixtures, modifications to the proposed generator
plug, installation of a bronze plaque, and adjustment to the unit price of item Al2 to match
the unit price as bid. Also included is additional labor to install the proposed sanitary sewer
force main under Regent It Subdivision, and additional labor and materials to complete the
tie-in of the proposed force main at Interstate 10, thereby increasing the contract amount
to $2,142,528.85; and,
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and,
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 1 in the amount of $37,472.05, thereby increasing the contract amount to
$2,142,528.85.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 9th day of
August, 2011.
M or Becky Ames -
g c3 0
� w i
i� '