HomeMy WebLinkAboutRES 11-204 RESOLUTION NO. 11-204 WHEREAS, on December 14, 2010, the City Council of the City of Beaumont, Texas, passed Resolution No. 10-322 awarding a contract in the amount of$3,022,510.00 to Russell Marine, LLC, of Channelview, Texas, for the Riverfront Park Bank Stabilization Project; and, WHEREAS, Change Order No. 1 in the amount of $41,190.00 was required for unforeseen work due to the failure of the concrete bulkhead wall, thereby increasing the contract amount to $3,063,700.00; and, WHEREAS, Change Order No. 2 in the amount of $35,953.24 was required for removing and disposing submerged timber pilings and the replacement of a damaged 36 inch outfall pipe, thereby increasing the contract amount to $3,099,653.24; WHEREAS, Change Order No. 3 in the amount of $11,275 is required for the replacement of approximately 850 square feet of sidewalk, 14 linearfeet of concrete cap, as well as the installation of two (2) additional bollards, thereby increasing the contract amount to $3,110,928.24. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF BEAUMONT: THAT the statements and findings set out in the preamble to this resolution are hereby, in all things, approved and adopted; and THAT the City Manager be and he is hereby authorized to execute Change Order No. 3 for additional work described above, thereby increasing the contract amount by $11,275 for a total contract amount of$3,110,928.24. PASSED BY THE CITY COUNCIL of the City of Beaumont this the 26th day of July, 2011. Ulayor Becky Ames - RICH WITH OPPORTUNITY BEAU' 'M-','0N* T • E - B » A - $ CHANGE ORDER#3 PROJECT: Riverfront Park Bank Stabilization OWNER: City of Beaumont P.O.Box 3827 Beaumont,TX 77704 CONTRACTOR: Russell Marine LLC 16828 Market St. Channel view,TX 77530 On this the 26te day of July,2011 the following change to the Contract Documents is hereby made: Item 1 Necessity of change: Russell Marine,LLC has submitted a change order request for additional work recommended by the engineer to repair sidewalk failure and to help prevent standing water. The contractor has requested fifteen(15)calendar days be added to the contract time. Description: This change includes the cost of replacing approximately 850 square feet of sidewalk, 14 linear feet of concrete cap,as well as the installation of two(2) additional bollards. ORIGINAL CONTRACT AMOUNT . . . . . . .. . .. . . . . . . . . ......... .. . . . . .. .. . . $3,022,510.00 AMOUNT OF PREVIOUS CHANGE ORDERS . . . . . .. ..... ... . ..... .. . . .... . . . . $77,143.24 TOTAL AMOUNT OF THIS CHANGE ORDER .. . ............... . . . . . . . ... . .. . $11,275.00' ADJUSTED CONTRACT AMOUNT TO DATE ... .. . . ... .......... .. . . . . .. . .. $3,110,928.24 PERCENTAGE OF CHANGE-THIS CHANGE ORDER . . . ... ..... . . . . . . .. . . . . . . .. .0.37% PERCENTAGE OF CHANGE TO DATE . . . . .. .. .. . . . ........ . . . . . . . . . .. . . . . . . . . . 2.93% ADDITIONAL°CONTRACT TIME-CHANGE ORDER#3 ...... . . . .. . 15 CALENDAR DAYS APPROVED BY: Russell Marine,LLC City Manager City of Beaumont F ER CH- �. 9 . pS. CONTRACT AMENDMENTS Form 9-4 Construction Contract Change Order Approval Request Owner(Contractor Locality): Contract For(project description): Date July 26, 2011 City of Beaumont Riverfront Park Bank PO Box 3827 Stabilization _ Project.No. CP0910-58 Beaumont,TX 77704 Phone #: 409-880-3721 Contractor: Engineer: DR Contract No. DRS010012 Russell Marine Uoyd Engineering Inc. 16828 Market St 9418 Mills Rd. Channelview,TX 77530 Houston,Tx 77070 Change Order No. 3 Agreement Date: 12/14/10 Phone#: 281-477-6985 Phone #: 281-960-0011 Engineer's Project No. You are hereby requested to comply with the following changes from the contract plans and specifications: Item Description of Changes-Quantities, Units, Unit Prices, Decrease in Increase in Contract No. Change in Completion Scheduled, Etc. Contract Price Price 1 Replace approx. 850 sq.ft sidewalk, 14 I.f. concrete $11,275 cap, and install two (2) additional bollards Disaster Recovery Program Project Implementation Manual Page 1 of 5 CHAPTER 9 S. CONTRACT AMENDMENTS Change in Contract Price Change in Contract Time Original Contract Price: $3,022,510.00 Original Contract Time: 180 days Previous Change Order(s) Net Change From Previous No. 1 to No. 2 $77,143.24 Change Orders 0 days Contract Price Prior to Contract Time Prior to this Change Order $3,099,653.24 this Change Order 180 days Net Increase/Decrease of Net Increase/Decrease of this Change Order $11,275.00 this Change Order 15 days Contract Price With all Contract Time With all Approved Change Orders $3,110,928.24 Approved Change Orders 195 days Cumulative % Change in Contract Price: 2.93% DR Division reimbursement of costs APPROVED: ACCEPTED: approved by this change order is subject to approval by TDRA.REC MMENDED: t By: By:y: y: ENGINEER(Authorized Signature) OWNER(Authorized Signature) CONTRACTOR(Authorized Signature) 9-43- 11 �- Date: Date: Date: PGrantee: City of Beaumont Disaster Recovery Program Project Implementation Manual Page 2 of 5 CHAPrER 9 s. CONTRACT AMENDMENTS JUSTIFICATION FOR CHANGE DRS Contract No.: DRS010012 Change Order No. 3 1. Will this Change Order increase or decrease the number of beneficiaries? ❑ Increase ❑ Decrease $-No Change If there is a change, how many beneficiaries will be affected? Total tJM 2. Effect of this change on scope of work: 8 Increase ❑ Decrease ❑ No Change 3. Effect on operation and maintenance costs: ❑ Increase ❑ Decrease $No Change 4. Are all prices in the change order dependent upon unit prices found in the original bid? ❑ Yes $ No If"No", explain: Work resulting from this change order was due to sidewalk and concrete cap failure. Costs associated with this change order will be provided by local funds. 5. Will this change be completed within the contract period? B Yes ❑ No If"No", expected completion date: (completion date) Disaster Recovery Program Project Implementation Manual Page 3of5 CHAPTER 9 CONTRACT AMENDMENTS 6. Has this change created new circumstances or environmental conditions which may affect the project's impact, such as concealed or unexpected conditions discovered during actual construction? ❑ Yes B-No If"Yes", is an Environmental Re-assessment required? ❑ Yes ❑ No 7. Is the Texas Commission on Environmental Quality(TCEQ) clearance still valid? 8 Yes ❑ No 8. Is the TCEQ permit approval still valid? (sewer projects only) ❑ Yes ❑ No 9.Are the handicapped access requirements/approval still valid(if applicable)? $ Yes ❑ No 10.Are other Disaster Recovery contractual special condition clearance still valid? 8 Yes ❑ No (If no, specify): Disaster Recovery Program Project Implementation Manual Page 4 of 5 CHAPTER 9 04)s CONTRACT AMENDMENTS NOTE: * Generally, a cumulative change in the contract price in excess of 25% cannot be approved. * Generally, items not included or identifying unit costs in the original bid documents cannot be approved as change order items. Disaster Recovery Program Project Implementation Manual Page 5of5