WHEREAS, on June 29, 2010, the City Council of the City of Beaumont, Texas,
passed Resolution No. 10-173 awarding a contract in the amount of $9,879,522.15 to
Reytec Construction Resources, Inc., of Houston, Texas, for the Calder Avenue Drainage
and Pavement Improvement Project- Phase III; and
WHEREAS, Change Order No. 1 in the amount of$94,928 was required for adding
construction items and reducing construction item quantities to the Calder Avenue
Drainage and Pavement Improvement Project- Phase 111, thereby increasing the contract
amount to $9,974,450.15; and,
WHEREAS, Change Order No.2 in the amount of$9,850.00 was required for costs
associated with the existing drainage and the proposed waterline installation conflicts,
thereby increasing the contract amount to $9,984,300.15 ; and
WHEREAS, Change Order No. 3 in the amount of$68,697.30 is required for adding
construction items and reducing construction item quantities necessary to resolve drainage
and water line conflicts, thereby increasing the contract amount to $10,052,997.45;
NOW, THEREFORE, BE IT RESOLVED BY THE
CITY COUNCIL OF THE CITY OF BEAUMONT:
THAT the statements and findings set out in the preamble to this resolution are hereby, in
all things, approved and adopted; and
THAT the City Manager be and he is hereby authorized to execute Change Order
No. 3 for additional work described above, thereby increasing the contract amount by
$68,697.30 for a total contract amount of$10,052,997.45.
PASSED BY THE CITY COUNCIL of the City of Beaumont this the 19th day of July,
2011.